Interstate Rock Products, Inc. v. United States

50 Fed. Cl. 349, 2001 U.S. Claims LEXIS 176, 2001 WL 1095301
CourtUnited States Court of Federal Claims
DecidedSeptember 17, 2001
DocketNo. 01-408 C
StatusPublished
Cited by18 cases

This text of 50 Fed. Cl. 349 (Interstate Rock Products, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Interstate Rock Products, Inc. v. United States, 50 Fed. Cl. 349, 2001 U.S. Claims LEXIS 176, 2001 WL 1095301 (uscfc 2001).

Opinion

OPINION

BUSH, Judge.

This pre-award bid protest is before the court on cross-motions for summary judgment. The solicitation at issue was for award of a project that entails the grading, drainage and asphaltic surfacing of 16.33 kilometers of roadway in the Bryce Canyon National Park. Plaintiff, Interstate Rock Products, Inc. (Interstate; Interstate Rock), challenges the Federal Highway Administration’s (FHWA) determination that its bid was rendered nonresponsive due to the omission of the penal sum on the required bid bond. For the reasons set forth below: (1) Interstate Rock Products, Inc.’s Motion for Summary Judgment on the Administrative Record and request for injunctive relief is denied; (2) Defendant’s Cross-Motion for Summary Judgment Upon the Administrative Record and Opposition to Plaintiffs Motion for Summary Judgment on the Administrative Record and for Injunctive Relief is granted; and (3) Gilbert Western Corporation’s Opposition to Interstate Rock Products, Inc.’s Motion for Summary Judgment upon the Administrative Record and Gilbert’s Cross-Motion for Summary Judgment is granted.

BACKGROUND

I. Factual Background

Interstate Rock is a Utah corporation with its principal place of business in Hurricane, Utah. On April 1, 2001, FHWA issued a pre-solicitation notice stating that solicitation documents were to be made available on April 10, 2001, for a project consisting of the grading, drainage and asphaltic surfacing of 16.33 kilometers of roadway in the Bryce Canyon National Park. This solicitation was identified as “UT PRA BRCA (10)2, Rainbow Point Rim Road.” AR at 8.1

Of particular significance in this case is a provision contained under block 13 of Standard Form 1442 of the solicitation that provides:

A bid guarantee of not less than 20 percent of the bid amount is required with any bid in excess of $25,000. If the bidder fails to accompany the bid with the required bid guarantee, such failure may require rejection of the bid. See Contract Clause 52.228-1, Bid Guarantee. If the bid guarantee is a bid bond, it must be submitted on Standard Form 24.

AR at 16.

Also germane to this case is a contract clause included in the solicitation based on Federal Acquisition Regulation (FAR) 52.228-1, Bid Guarantee, that provides as follows:

[351]*351(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier’s check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds, (1) to unsuccessful bidders as soon as practicable after the opening of bids, and (2) to the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.

(c) The amount of the bid guarantee shall be 20 percent of the bid price or $3,000,000, whichever is less.

(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.

(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.

AR at 49.2

On April 19, 2001, plaintiff apparently notified its bonding agent, Mr. Budd O. Scow, of Certified Insurance Services, Inc., that it needed a bid bond in the penal sum of 20% of the bid amount in order to respond to FHWA solicitation UT PRA BRCA (10)2 on May 10, 2001. In turn, the bonding agent ordered from the United States Fidelity & Guaranty Company (USF & G) a bond in the penal sum of 20% of the bid amount. In this order, the bonding agent referenced the project number, UT PRA BRCA 10(2), and advised the surety that the engineer’s estimate for the project was $5-10 million. USF & G is an approved surety under United States Treasury Department Regulations.

On April 25, 2001, the surety issued a proper bid bond in the penal sum of 20% of the bid amount. A copy of this bid bond is attached to the complaint as exhibit 2 and is also included in the AR at 498. Because, however, parts of this bid bond were illegible, apparently due to lack of clarity in facsimile transmission, the plaintiffs bonding agent asked the surety to replace the April 25, 2001 bond with one that was more legible.

The surety then issued a more legible copy of the bond that was identical to the April 25, 2001 bond in all but one critical respect. In the new version of the bid bond, the penal sum was left blank, apparently through inadvertent error. It was this new version of the bid bond, lacking the inclusion of the penal sum, that plaintiff submitted with its bid. The bid bond states “[w]e, the Principal and Surety(ies), are firmly bound to the United States of America (hereinafter called the Government) in the above penal sum.” AR at 281.

On May 10, 2001, sealed bids for the subject solicitation were opened. Interstate Rock was the apparent low bidder with a bid price of $10,463,922.60. The only other bid was submitted by Intervenor, Gilbert Western Corporation of West Jordan, Utah (Gilbert; Gilbert Western), and was in the amount of $11,003,340.00. The government engineer’s estimate was for $10,485,182.50.

Of particular importance in this case is FHWA’s May 21, 2001 letter to plaintiff stating that its bid had been declared nonrespon-sive “due to the omission of the penal sum on [Interstate’s] bid bond.” AR at 494. At[352]*352tached to this letter were copies of the following two Comptroller General Decisions in support of the agency’s decision: Matter of M/V Constructor Co., B-232572, Sept. 20, 1998, 88-2 CPD ¶ 272, 1988 WL 227922; Matter of Kennedy Electric Co., Inc., B-239687, May 24, 1990, 90-1 CPD ¶ 499, 1990 WL 277996.3 This letter was written by Ms. Suzanne M. Schmidt, P.E., Contract Development Engineer for FHWA.

On May 22, 2001, Mr. Michael T. Madsen, Controller of Interstate Rock, responded via letter on behalf of Interstate Rock and offered to provide FHWA with a copy of the original bid bond that had been furnished by the surety that contained no omissions and was complete although it was partially illegible. In this letter, plaintiff articulated its view that “[t]he surety’s obligation was manifested prior to the bid, and the clerical error then, only represented a minor informality and the bid should be responsive.” AR at 497. In this letter, plaintiff also presented an argument that its case is distinguishable from those attached to FHWA’s May 21, 2001 letter for the following reasons:

[W]e can present a properly filled out bid bond that was prepared prior to the bid. Only after noting that the form was not as clear as desired was the bond changed and the typing error done.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hartford Fire Insurance Co. v. United States
254 F. Supp. 3d 1333 (Court of International Trade, 2017)
King Metal Buildings, Inc. v. Renasant Insurance, Inc.
159 So. 3d 567 (Court of Appeals of Mississippi, 2014)
Systems Application & Technologies, Inc. v. United States
100 Fed. Cl. 687 (Federal Claims, 2011)
Urban Development Solutions, LLC v. District of Columbia
992 A.2d 1255 (District of Columbia Court of Appeals, 2010)
Autoridad de Carreteras y Transportación v. CD Builders, Inc.
177 P.R. 398 (Supreme Court of Puerto Rico, 2009)
Tip Top Constraction, Inc. v. United States
563 F.3d 1338 (Federal Circuit, 2009)
SP Systems, Inc. v. United States
86 Fed. Cl. 1 (Federal Claims, 2009)
NVT Technologies, Inc. v. United States
73 Fed. Cl. 459 (Federal Claims, 2006)
CW Government Travel, Inc. v. United States
61 Fed. Cl. 559 (Federal Claims, 2004)
Hunt Building Co. v. United States
61 Fed. Cl. 243 (Federal Claims, 2004)
First Enterprise v. United States
61 Fed. Cl. 109 (Federal Claims, 2004)
Great Lakes Dredge & Dock Co. v. United States
60 Fed. Cl. 350 (Federal Claims, 2004)
Tel-Instrument Electronics Corp. v. United States
56 Fed. Cl. 174 (Federal Claims, 2003)
All Seasons Construction, Inc. v. United States
55 Fed. Cl. 175 (Federal Claims, 2003)
CESC Plaza Ltd. Partnership v. United States
52 Fed. Cl. 91 (Federal Claims, 2002)
Gaeta v. Ridley School District
788 A.2d 363 (Supreme Court of Pennsylvania, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
50 Fed. Cl. 349, 2001 U.S. Claims LEXIS 176, 2001 WL 1095301, Counsel Stack Legal Research, https://law.counselstack.com/opinion/interstate-rock-products-inc-v-united-states-uscfc-2001.