All Seasons Construction, Inc. v. United States

55 Fed. Cl. 175, 2003 U.S. Claims LEXIS 10, 2003 WL 179779
CourtUnited States Court of Federal Claims
DecidedJanuary 23, 2003
DocketNo. 02-1895 C
StatusPublished
Cited by7 cases

This text of 55 Fed. Cl. 175 (All Seasons Construction, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
All Seasons Construction, Inc. v. United States, 55 Fed. Cl. 175, 2003 U.S. Claims LEXIS 10, 2003 WL 179779 (uscfc 2003).

Opinion

OPINION

MEROW, Judge.

This is a post-award protest in which plaintiff, All Seasons Construction, Inc. (“All Seasons”), alleges that the Department of Veteran Affairs (“VA”) improperly rejected its bid as non-responsive. The matter is now before the Court on plaintiffs requests for preliminary and permanent injunctive relief and the parties’ cross-motions for summary judgment on the administrative record. Plaintiff seeks to enjoin the VA from taking any further action with respect to the contract it entered into with Witherington Construction (“With-erington”) under Invitation for Bid (“IFB”) No. 667-29-02 for the construction of replacement operating rooms. For the reasons below, plaintiffs motions are DENIED and defendant’s motion for summary judgment is GRANTED.

Background

On July 10, 2002, the VA, pursuant to IFB No. 667-29-02, issued a solicitation for a construction project at Overton Brooks Administration Medical Center in Shreveport, Louisiana, Project No. 667-02-042. Administrative Record (“AR”) 7. The solicitation called for the demolition and removal of existing buildings and construction of a new addition consisting of four operation rooms. Id. The solicitation and four amendments were issued via the Business Opportunities System. AR 11. At the time of the bid opening on August 20, 2002, four bids were received and recorded on the Abstract of Bids. Id. All Seasons was the apparent low bidder with its base bid of $3,361,000. Id. Witherington was the second-lowest bidder with its bid of $3,505,000. AR 85-86. All Season’s bid was submitted with a bid bond, for the penal sum of 20% of the bid price. AR 11; 87-88. Plaintiffs bid bond was submitted on Standard Form 24, which states that “[a]ny person signing in a representative capacity (e.g., an attorney-in-fact) must furnish evidence of authority if that representative is not a member of the firm, partnership, or joint venture, or an officer of the corporation involved.” AR 87-88; 48 C.F.R. § 53.338(a). The bid bond was signed by All Seasons’ president, Mr. Edward L. Angel, and David A. Montgomery, the attorney-in-fact for Hartford Casualty Insurance Co. (“Hartford”), All Seasons’ surety. The surety’s seal was crimped next to the attorney-in-fact’s signature. AR 11; 87.

The bid bond was accompanied with a power of attorney, which is comprised of three parts. The first part authorizes David A. Montgomery and Dale R. Montgomery of Bossier City, Louisiana as the attorneys-in-fact of the surety and is evidenced by the signatures of Paul A. Bergenholtz, Assistant Secretary, and John P. Hyland, Assistant Vice President of Hartford. AR 11; 89-90. It states that the “Companies hereby unambiguously affirm that they are and will be bound by any mechanically applied signatures applied to this Power of Attorney.” AR 89. The second part is a notary public certification of the signature of Mr. Hyland on the first part of the power of attorney. AR 11; 89-90. The third part of the power of attorney, captioned “Certificate” is signed by Colleen Mastroianni, Assistant Vice President of Hartford who certifies that the “fore[177]*177going is a true and correct copy of the Power of Attorney executed by said Companies, which is still in full force and effect as of August 9, 2002.” Id.

The VA conducted a review of All Seasons’ bid for compliance with the nontechnical requirements of the IFB. As a result of the responsiveness review, the contracting officer (“CO”), Mr. Terry Galbraith, rejected All Seasons’ bid. AR 90. In a letter dated August 29, 2002, the CO informed plaintiff that its bid was non-responsive because:

the Bid Bond you provided is accompanied by a Power of Attorney that is not an original and not accompanied by an original certification of validity. In Schrepfer Industries, Inc., B-286825[, 2001 WL 118871] February 12, 2001 the Comptroller General held that a bid bond that was accompanied by a photocopied power of attorney is unacceptable “because [a] photocopied power of attorney does not establish unequivocally at the time of bid opening that the bond would be enforceable against the surety in the event that the bidder fails to meet its obligations.” Therefore, on the basis of that authority and in accordance with Federal Acquisition Regulation [sic] (FAR 14.404-2(a) and (k)), your bid bond is rejected because it is non-responsive.

Letter from Terry L. Galbraith, CO, to All Seasons. AR 90.

Subsequently, the VA awarded the contract to the second-lowest bidder, Withering-ton. On September 13, 2002, plaintiff submitted a protest with the General Accounting Office (“GAO”) alleging that the CO’s decision was arbitrary and capricious because the power of attorney was a computer printer generated original document with mechanically applied signatures. In its Agency Report to the GAO, the VA argued that All Seasons’ bid was non-responsive because the power of attorney lacked an original corporate seal. On December 6, 2002, the GAO denied All Seasons’ protest. All Seasons Constr., Inc., 2002 WL 31761471, B-291166.2, 2002 CPD ¶ 212 (Comp.Gen. Dec. 6, 2002). The GAO concluded that the power of attorney “looks more like a photocopy than a document generated by a computer printer. This fact in itself would be sufficient to justify rejection of the bid under the long standing rule, cited above, that photocopied powers of attorney are not acceptable.” Id. at *2, n. 1. The GAO went on to uphold the CO’s decision on the alternative basis that the mechanically applied signatures were affixed to the power of attorney after it had been generated. Therefore, it was reasonable for the CO to conclude that the power of attorney did not definitively establish at the time of the bid opening that the bond would be enforceable against the surety. Furthermore, the GAO held that the certification on the power of attorney was of questionable validity because the date was inserted after the document was created.1 On December 17, 2002, plaintiffs complaint and motions for injunctive relief were filed in this Court.

Discussion

Standard of Review

Cross-Motions for Judgment on the Administrative Record

Motions for judgment on the administrative record are reviewed under the rules governing motions for summary judgment. See Clifton v. United States, 31 Fed.Cl. 593, 596 (1994), aff'd, 66 F.3d 345, 1995 WL 540183 (Fed.Cir.1995). A motion for summary judgment “is an appropriate vehicle to scrutinize an agency’s procurement actions because the issues are matters of contractual and regulatory interpretation.” Analytical & Research Tech. v. United States, 39 Fed.Cl. 34, 43 (1997) (citing Stone Forest Indus., Inc. v. United States, 32 Fed.Cl. 424, 426 (1994)). Summary judgment is appropriate where there are no genuine issues of material fact and the moving party is entitled to [178]*178judgment as a matter of law. RCFC 56(c)2; Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 247, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986); Olympus Corp. v. United States, 98 F.3d 1314, 1316 (Fed.Cir.1996).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Synergy Solutions, Inc. v. United States
133 Fed. Cl. 716 (Federal Claims, 2017)
King Metal Buildings, Inc. v. Renasant Insurance, Inc.
159 So. 3d 567 (Court of Appeals of Mississippi, 2014)
Science Applications International Corp. v. United States
108 Fed. Cl. 235 (Federal Claims, 2012)
CBY Design Builders v. United States
105 Fed. Cl. 303 (Federal Claims, 2012)
DMS All-Star Joint Venture v. United States
90 Fed. Cl. 653 (Federal Claims, 2010)
Hawaiian Dredging Construction Co. v. United States
59 Fed. Cl. 305 (Federal Claims, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
55 Fed. Cl. 175, 2003 U.S. Claims LEXIS 10, 2003 WL 179779, Counsel Stack Legal Research, https://law.counselstack.com/opinion/all-seasons-construction-inc-v-united-states-uscfc-2003.