Dillingham Construction, Inc. v. Milwaukee Metropolitan Sewerage District

629 F. Supp. 406, 1986 U.S. Dist. LEXIS 29079
CourtDistrict Court, E.D. Wisconsin
DecidedFebruary 21, 1986
DocketCiv. A. 86-C-177
StatusPublished
Cited by6 cases

This text of 629 F. Supp. 406 (Dillingham Construction, Inc. v. Milwaukee Metropolitan Sewerage District) is published on Counsel Stack Legal Research, covering District Court, E.D. Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dillingham Construction, Inc. v. Milwaukee Metropolitan Sewerage District, 629 F. Supp. 406, 1986 U.S. Dist. LEXIS 29079 (E.D. Wis. 1986).

Opinion

DECISION AND ORDER

REYNOLDS, Chief Judge.

Plaintiffs brought this action on February 18, 1986, to prevent the Milwaukee Metropolitan Sewerage District (MMSD) from entering into a construction contract with Traylor Brothers and Traylor Brothers, Inc./Frontier Kemper Construction, Inc., (Traylor). Plaintiffs’ bid for the contract in question was rejected by MMSD because Traylor’s bid was roughly 2 million dollars lower. Plaintiff claims that Traylor’s bid should not have been accepted because Traylor’s bid had a blank space where the amount of the required penalty bond should have been inserted. The court has diversity jurisdiction over this action.

Counsel for MMSD has informed the court that after this action was com *408 menced, but before the court announced this decision, MMSD awarded the contract to Traylor on February 20, 1986. The court will nonetheless decide the question before it because the court’s equity powers would still allow the court to set aside the contract in the event that the court found merit in Dillingham’s contention that Traylor was not “the lowest responsible bidder complying with the invitation to bid____” Wis.Stats. § 66.904(2).

The parties agree on the facts. Traylor submitted the low bid for the project but left blank the space in which it was to specify the amount of its penal bond, which bond was required by the bid invitation to be for an amount no less than five percent of the cost of the project. In the event that a low bidder refused to sign a contract with MMSD after being awarded the bid, the surety of the penal bond agrees to pay MMSD the amount of the bond in liquidated damages.

Traylor did execute a bid bond with its surety, and, as is apparently the custom in the trade, the space for the amount of the bond was empty when the surety delivered the bond to Traylor. Traylor failed to write in the amount of the penal sum before submitting its bid. The day after the bids were opened and the omission had become apparent, representatives of Traylor and its surety signed an affidavit stating that the amount of the penal sum should have been five percent and that both Traylor and the surety bound themselves to the terms of the bond. Five days later Traylor and the surety executed a new bid bond for five percent of the contract price and the commission received that the following day.

Despite the defect in Traylor’s bid, and after careful consideration of the question, MMSD decided to accept the bid of Traylor. Plaintiff brought this action on February 18, 1986, in an attempt to prevent MMSD from awarding the contract on February 20, 1986.

The Seventh Circuit Court of Appeals recently held that a preliminary injunction should be granted “only if the harm to the plaintiff if the injunction is denied, multiplied by the probability that the denial would be error (that the plaintiff, in other words, will win at trial), exceeds the harm to the defendant if the injunction is granted, multiplied by the probability that granting the injunction would be an error.” American Hospital Supply Corp. v. Hospital Products Ltd., 780 F.2d 589, 593 (7th Cir.1986). The interest of third parties and the public is to be calculated with the harms to the defendant or the plaintiff, depending on where the public interest lies. Id. The inquiry is designed to help “figure out whether granting the injunction would be the error minimizing course of action, which depends on the probability that the plaintiff is in the right and on the costs to the plaintiff, the defendant, or others of granting or denying the injunction.” Id. at 594.

The formula set forth above is designed to minimize the costs of mistake that can result when a judge is forced to act on an incomplete record. Id. at 593. That problem does not present itself here because there is no substantial dispute as to the facts and the legal question is ready for decision on the merits. The court finds that MMSD acted within its discretion when it chose to accept the low bid of Traylor despite Traylor’s failure to include the sum of its penal bond in the application.

The Wisconsin Supreme Court has explained the reasons for state statutes designed to assure competitive bidding on public works projects.

Public policy considerations operate to restrict the rights of a bidder on a public contract. Competitive bidding requirements were intended for the benefit and protection of the public. They are designed to prevent fraud, collusion, favoritism and improvidence in the administration of public business as well as to insure that the public receives the best work or supplies at the most reasonable price practicable.

Nelson, Inc. v. Sewerage Commission of Milwaukee, 72 Wis.2d 400, 408, 241 N.W.2d 390 (1976).

*409 Wis.Stat. § 66.904(2)(c) requires the commission to award the contract “to the person who it finds is the lowest responsible bidder complying with the invitation to bid ... unless it rejects all bids or relets the contract.” (emphasis supplied). Subsection (3)(a) provides that “[t]he commission may permit or require ... a bond for the benefit of the district to be filed with any bid or proposal as liquidated damages in an amount that, in the judgment of the commission, will protect the district from any loss if the bid is accepted ... and the bidder fails to execute a contract____” (emphasis supplied). Paragraph fourteen of the the Invitation to Bidders stated that “[b]ids must be accompanied by ... a bid bond ... in an amount not less than 5 percent of the total amount of the bid.”

The parties agree that Wisconsin law controls but there is no Wisconsin precedent that is on point. Plaintiff contends that Wisconsin would look to federal law and directs the court to two decisions of the Comptroller General, both of which held that, under federal procurement law, failure to state the amount of the penal bond in the bid application renders the bid non-responsive. The defendants argue that the few relevant Wisconsin cases could be interpreted to allow Traylor’s bid, that Wisconsin would not necessarily follow the Comptroller, and that other jurisdictions have found that the failure to include the penal sum in the bond is not fatal.

The court has carefully considered the authorities presented and is satisfied that Wisconsin law has not yet answered the question, and that resort to other jurisdictions does not provide a definitive answer. The instant action is rather novel in that here, the losing bidder is asserting the defect as a means to disqualify the winner, whereas the question is normally raised either by a surety who refuses to pay on the bond, or by a bidder who is disqualified for its failure to fill in the blank. This court must determine what the Supreme Court of Wisconsin would decide if faced with this question.

The court is well aware of the special emphasis Wisconsin places upon clean and open government.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Interstate Rock Products, Inc. v. United States
50 Fed. Cl. 349 (Federal Claims, 2001)
Power Sytems Analysis, Inc. v. City of Bloomer
541 N.W.2d 214 (Court of Appeals of Wisconsin, 1995)
Powder Horn Constructors, Inc. v. City of Florence
754 P.2d 356 (Supreme Court of Colorado, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
629 F. Supp. 406, 1986 U.S. Dist. LEXIS 29079, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dillingham-construction-inc-v-milwaukee-metropolitan-sewerage-district-wied-1986.