First Enterprise v. United States

61 Fed. Cl. 109, 2004 U.S. Claims LEXIS 155, 2004 WL 1474560
CourtUnited States Court of Federal Claims
DecidedJune 25, 2004
DocketNo. 04-0082C
StatusPublished
Cited by22 cases

This text of 61 Fed. Cl. 109 (First Enterprise v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
First Enterprise v. United States, 61 Fed. Cl. 109, 2004 U.S. Claims LEXIS 155, 2004 WL 1474560 (uscfc 2004).

Opinion

OPINION AND ORDER

BLOCK, Judge.

I. INTRODUCTION

To what degree may a court interfere with an administrative agency’s budgetary process in a construction project? That is the dilemma facing the court when deciding the issues arising in this post-award bid protest case. Plaintiff, First Enterprise, challenges the U.S. Department of Veterans Affairs (“agency” or ‘VA”) award of a contract to DJM Construction Co., Inc. (“DJM”) for the construction of a specialty clinic at the VA Greater Los Angeles Healthcare Center. [111]*111Plaintiff essentially contends that the VA did not allocate sufficient funds for its construction project because it unlawfully ignored an independent cost estimate, and that plaintiffs wrongly-rejected bid gave the agency the best value. Among other things, the plaintiff asks the court to enjoin the agency from awarding the contract to another bidder. The defendant counters that the agency acted reasonably in all respects. This controversy thus implicates the role of the judiciary — Hamilton’s “least dangerous branch” — in the modern world of administrative agency enforcement of congressional spending mandates.

Before the court are the parties’ cross-motions for summary judgment on the administrative record pursuant to Rule 56.1 of the Rules of the Court of Federal Claims (“RCFC”) and plaintiffs petition for a permanent injunction. The parties completed briefing on April 26, 2004, and oral argument on the motions was held on June 9, 2004. This court has jurisdiction under the Administrative Dispute Resolution Act of 1996, Pub.L. No. 104-320, § 12, 110 Stat. 3870, 3874-75 (1996), which amended the Tucker Act to provide this court with jurisdiction to entertain post-award bid protests. After carefully reviewing the parties’ briefs and after oral argument, the court grants summary judgment in favor of the government and denies plaintiffs cross motion and petition for injunctive relief.

II. BACKGROUND

The facts in this case derive from the administrative record. On August 6, 2003, the Los Angeles branch of the VA issued solicitation No. 600-249-03RT (“Solicitation”) for the consolidation and relocation of Prosthetic Treatment Center, Optometrie Clinic, and Ophthalmology Clinic into building No. 304, for the VA Greater Los Angeles Healthcare Center. The procurement was set aside for 8(a) minority contractors through an invitation for bids (“IFB”) and all offers were sealed. Admin. R. at 36. The IFB required bidders to submit offers for the main item bid, as well as offers for five alternate bid items. The main bid item consisted of “general construction, alterations, mechanical and electrical work, laboratory equipment, utility systems, [and] necessary removal of existing structures,” and the alternate bid items progressively deducted portions of the work from the main bid item. Id. at 38.

In requesting funding for the project, the agency used its own construction estimate of $3,218,781 (“construction estimate”) and added 7.5% for construction contingency costs, $50,000 for impact costs and $406,394 for estimated architect/engineering fees. Admin. R. at 3. The agency submitted a project funding request for $3,916,584 (“agency estimate”) and received an allocation in that amount for the project budget. Admin. R. at 126. The agency then spent $366,000 on the design of the project, leaving $3,551,000 available for construction. Admin. R. at 164 (11:18:36 to 11:19:02). Prior to issuing the Solicitation for the construction portion of the project, however, the agency hired C.P. O’Halloran Associates, Inc. to develop an independent government estimate (“O’Halloran estimate”) for the project construction. This estimate listed construction costs at $3,596,111. Admin. R. at 5.

With the $3,551,000 remaining in its project budget, the agency issued the Solicitation and received bids from four offerors: First Enterprise, Ace Engineering, Inc. (“Ace”), DJM and Stronghold Engineering, Inc. Admin. R. at 44-15. Although the agency based its request for funding on its own construction estimate of $3,218,781 plus contingency, impact and design costs, the agency used the O’Halloran estimate of $3,596,111 to review the bids. Admin. R. at 44. After publicly opening the bids, the agency chose the low bid for alternate bid item 5, submitted by Ace. A short time after the agency designated Ace the awardee, Ace asked to withdraw its bid because Ace had made clerical errors in its calculations. Id. at 54. The agency investigated Ace’s request, determined that Ace’s bid contained an error and permitted Ace to withdraw from the procurement. Id. at 72-73.

Although First Enterprise became the low bidder for each bid item after Ace’s withdrawal, it is important to note that its bid for each alternate bid item exceeded the [112]*112$3,551,000 remaining in the project budget.1 Since all offers were above both the remaining allocated amount of $3,551,000 and the O’Halloran estimate, the agency deemed the bids “unreasonable” and converted the Solicitation from an IFB to a request for proposals (“RFP”), which was to be negotiated. Id. at 79, 84. The construction requirements for the RFP remained the same; however, the agency amended the Solicitation to include a sixth alternate bid item to help ensure award of the contract. Id. at 75.

On September 26, 2003, after reviewing the proposals from the three remaining companies, the agency awarded the contract to the lowest offeror, DJM, for its bid of $2,989,000 on alternate bid item 6.2 Then, on October 3, 2003, plaintiff filed a bid protest action with the General Accounting Office (“GAO”). After GAO denied plaintiff’s petition, plaintiff filed a post-award 'bid protest in this court on January 22, 2004. A scheduling order was issued on January 28, 2004. This court then conducted a telephone conference with representatives of First Enterprise and the government, in which plaintiff withdrew its petition for a preliminary injunction, as well as its motion for expedited and expanded discovery. Order, February 4, 2004. This court also granted leave for plaintiff to file a first amended complaint, and requested the parties to submit motions for summary judgment in accordance with RCFC 56.1.

III. STANDARDS

A. Jurisdiction and Standard of Review

The Court of Federal Claims has jurisdiction, pursuant to the Tucker Act, 28 U.S.C. § 1491(b)(1) (2003), “to render judgment on an action by an interested party objecting to a solicitation by a Federal agency for bids or proposals for ... the award of a contract or any alleged violation of statute or regulation in connection with a procurement or a proposed procurement.” The standard of review is whether the procuring agency’s conduct was arbitrary and capricious. See 28 U.S.C. § 1491(b)(4) (2003) (“In any action under this subsection, the courts shall review the agency’s decision pursuant to the standards set forth in section 706 of title 5.”).3 Regarding this standard, the Supreme Court has stated that:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
61 Fed. Cl. 109, 2004 U.S. Claims LEXIS 155, 2004 WL 1474560, Counsel Stack Legal Research, https://law.counselstack.com/opinion/first-enterprise-v-united-states-uscfc-2004.