Derek & Dana Contracting, Inc. v. United States

32 Cont. Cas. Fed. 73,356, 7 Cl. Ct. 627, 1985 U.S. Claims LEXIS 1021
CourtUnited States Court of Claims
DecidedMarch 25, 1985
DocketNo. 507-83C
StatusPublished
Cited by1 cases

This text of 32 Cont. Cas. Fed. 73,356 (Derek & Dana Contracting, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Derek & Dana Contracting, Inc. v. United States, 32 Cont. Cas. Fed. 73,356, 7 Cl. Ct. 627, 1985 U.S. Claims LEXIS 1021 (cc 1985).

Opinion

OPINION

REGINALD W. GIBSON, Judge:

This suit arises out of a contract entered into by defendant with plaintiff, Derek & [628]*628Dana Contracting, Inc. (D & D), a closely-held entity with its principal place of business situated in Salina, Utah, for the construction of the Ft. Duchesne Health Center (health center) in Ft. Duchesne, Utah. Plaintiff contends, inter alia, that the defendant was fully aware when it accepted plaintiffs bid that it did not contain costs for the installation of the Modular Storage System (MSS). Because of such awareness, the plaintiff argues that the defendant is bound by plaintiff's interpretation of the contract which was that the costs for the MSS would be treated as an equitable adjustment. Contrastingly, the defendant denies knowledge (actual or constructive), prior to, at, or after bid opening, that the plaintiff’s bid did not contain costs for the installation of the MSS when the contract was awarded. Rather, the defendant contends that the plaintiff should be bound by its lump-sum bid which was unconditionally tendered to include all of the contract requirements. Thus, this fact-intensive case presents the court with the burden of resolving factual disputes where it is clear that the evidence adduced at trial was patently contradictory.

Jurisdiction over this case is premised on 28 U.S.C. § 1491 and the Contract Disputes Act of 1978, 41 U.S.C. § 601, et seq. Based on a thorough review of the evidence including but not limited to an evaluation of the credibility of the witnesses, the court finds that plaintiff is entitled to an equitable adjustment limited as delineated hereinafter.

FACTS

Certain of the following background facts, found pursuant to RUSCC 52(a), are not in dispute in that they are for the most part set forth in the Joint Stipulation of Facts. Additional operative facts, as were adduced at trial, are otherwise specifically found by the court.

On August 3, 1981, Invitation for Bids (IFB) No. 181810030 was issued to prospective bidders, including D & D, for the construction of the Ft. Duchesne Health Center, Ft. Duchesne, Utah. Said IFB was issued by the Regional Office of Facilities Engineering & Construction (ROFEC), located in Denver, Colorado. Bid opening was set for 2:30 p.m. on September 23, 1981, at ROFEC’s offices in Denver.

McCaleb Associates, Inc., of Edmund, Oklahoma (the Architect) prepared the plans and specifications for the construction of the Ft. Duchesne Health Center. By reason of section 11C3 of the contract specifications, the Modular Casework System (otherwise described as the Modular Storage System (MSS)), one of the components of this project, was required to be installed in the health center.

The MSS was to include, inter alia, counter service, pedestal storage, material supply storage, shelf storage, movable wall partitions, and hanging attachments. In short, the MSS specifications described an entirely separate modular system with removable, replaceable, and interchangeable components capable of easy assembling, dismantling, and repositioning. All components and accessories of this system were to be manufactured by one qualified manufacturer and all work was to be performed under the direction of one qualified MSS contractor (section 11C3.03(A)4 and 5).

Stipulated qualifications for MSS bidders were delineated in section 11C3.03, under the heading “Quality Assurance.” Additionally, section 11C3.04(C) provided further as follows:

C. Qualified MSS Bidders: The Architect will issue an Addendum identifying the bidders qualified to bid the work of this section no later than 72 hours prior to bid opening. (Emphasis added.)

Also, the general provisions of the contract contained the standard material and workmanship clause, that read in pertinent part as follows:

Unless otherwise specifically provided in this contract, reference to any ... material ... by trade name, make or catalog number, shall be regarded as establishing a standard of quality and shall not be construed as limiting competition, and the Contractor may, at his option, use [629]*629any ... material ... which, in the judgment of the Contracting Officer, is equal to that named. (Emphasis added.)

In that connection, Herman Miller Company’s products were referenced repeatedly in the MSS specifications by using the words “Similar to Herman Miller Co.,” with the related product catalog number following (e.g., Similar to Herman Miller Co./Struc. product No. 00308). Additionally, there were no provisions in the contract that “otherwise specifically provided” that Herman Miller’s products should not be regarded as establishing the standard of quality to meet the MSS specifications.

Prior to bid opening (i.e., September 23, 1981), or anytime thereafter, defendant, through its Architect, failed to issue the Addendum, as required, identifying “bidders qualified to bid the work of [the MSS] section.” The defendant also failed to advise the prime proposed bidders that section 11C3.04(C) would not be complied with. At the trial, the Architect, Mr. Karkaú, testified that he prepared the Addendum by September 14, 1981, and upon notifying defendant (ROFEC) of said fact, he was advised by ROFEC (Mr. Holtrop) that there was insufficient time to mail the Addendum to the eight prospective bidders (prime contractors). This conclusion was averred in spite of the fact that only one qualified MSS bidder (i.e., Amsco Unicell) was identified by the Architect on the Addendum to be disseminated to eight prospective bidders, and the contractual requirement was that the Architect simply “issue” the Addendum no later than 72 hours prior to bid opening, which was scheduled for 2:30 p.m. on September 23, 1981. See Plaintiff’s Exhibit 3.

In addition, approximately one week prior to bid opening, when contacted by the Architect's office regarding another matter, plaintiff inquired about the dissemination of the Addendum listing qualified MSS bidders and was advised that the list would be made available near the date of bid opening as provided in the specifications. Notwithstanding the foregoing, said Addendum was never issued to the prime bidders.

Against this background, the court finds that while prior to bid opening plaintiff made no written inquiries or requests to any distributors of Herman Miller products for the submission of a bid on the MSS, nor to the Architect or the contracting officer about the MSS, it did make telephonic contact with Herman Miller several weeks prior to bid opening. And, on bid opening day D & D further attempted to contact Herman Miller Company and Space Designs in an effort to solicit their bids for the installation of the MSS, on the assumption that Herman Miller was designated by the Architect as a qualified bidder on the MSS. Herman Miller, of San Francisco, California, at an earlier date, advised plaintiff that it would not provide a firm bid until the day of bid opening. Nevertheless, on the date of bid opening, Herman Miller Company advised D & D that it was unaware of the project and in turn referred it to Space Designs, a local representative in Utah.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

North American Construction Corp. v. United States
56 Fed. Cl. 73 (Federal Claims, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
32 Cont. Cas. Fed. 73,356, 7 Cl. Ct. 627, 1985 U.S. Claims LEXIS 1021, Counsel Stack Legal Research, https://law.counselstack.com/opinion/derek-dana-contracting-inc-v-united-states-cc-1985.