David Boland, Inc.

Armed Services Board of Contract Appeals·Decided September 20, 2024·No. 59313, 60294·Published

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeals of - ) ) David Boland, Inc. ) ASBCA Nos. 59313, 60294 ) Under Contract No. W912P8-10-C-0079 )

APPEARANCES FOR THE APPELLANT: Daniel Lund, III, Esq. Phelps Dunbar New Orleans, LA

Denis L. Durkin, Esq. Michael S. Vitale, Esq. Baker & Hostetler LLP Orlando, FL

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney William G. Meiners, Esq. Engineer Trial Attorney U.S. Army Engineer District, New Orleans

OPINION BY ADMINISTRATIVE JUDGE CATES-HARMAN

These appeals arise from a U.S. Army Corps of Engineers (USACE or Corps) contract awarded to David Boland, Inc. (Boland or appellant) to construct T-wall and I-wall as part of a flood prevention project in New Orleans, Louisiana. Boland brought this appeal on behalf of its primary subcontractor, Target Construction, Inc. (Target). On July 1, 2011, Boland filed its initial claim seeking $10,397,574 for the increase in Target’s total direct costs relating to alleged delays caused by passing trains between August 7, 2010 and May 21, 2011 (ASBCA No. 59313). On November 4, 2014, the claim was revised downward to $7,892,922, including additional costs incurred by Boland (ASBCA No. 60294). Boland’s revised claim is based upon the same set of facts as its first, but this submission utilized a modified total cost methodology. The contracting officer (CO) issued a final decision on July 23, 2015, which Boland appealed to the Board on October 16, 2015. The Board has jurisdiction over these appeals under the Contract Disputes Act of 1978, 41 U.S.C. §§ 7101-7109. A three-day hearing was held in New Orleans. Only entitlement is before the Board for decision. For the reasons stated below, we deny the appeals. FINDINGS OF FACT

Solicitation and Award

1. On March 5, 2010, USACE issued Solicitation No. W912P8-10-B-0054 (R4, tab 75 at GOV001674). This solicitation sought firms interested in performing work pursuant to USACE’s Lake Pontchartrain and Vicinity (LPV) Hurricane Protection Project, Lakefront Airport T-Walls, LPV 105.02 East Reach (R4, tab 75 at GOV001670-71). The work specified in the solicitation involved the replacement and construction of floodwalls along Haynes Boulevard in New Orleans, Louisiana (id. at GOV001676).

2. On May 13, 2010, USACE awarded Boland Contract No. W912P8-10-C- 0079 for the completion of specific flood prevention work in the amount of $19,472,000. The contract incorporated the solicitation (R4, tab 39 at GOV000958; tab 75 at GOV001674-80).

3. The contract required the construction of approximately 5,700 feet of T-wall and approximately 2,200 feet of I-wall (tr. 1/21-22; R4, tab 75 at GOV001671). This entailed structural concrete work, pile driving, and earthwork on a site adjacent to two operational railroad tracks (see id. at 1/21-22; R4, tab 75 at GOV002219, GOV002254, GOV002437).

4. The railroad tracks adjacent to the worksite were under the control of the Alabama Great Southern Railroad Company (the Railroad)), which, according to the parties, is a subsidiary of Norfolk Southern Railway Company (Norfolk Southern) (see R4, tab 10 at GOV000088; tab 75 at GOV001824-25, GOV001934; gov’t statement of undisputed material facts in support of its motion for summary judgment at ¶ 8 and app. resp. at ¶ 8).

5. The contract incorporated via full text Federal Acquisition Regulation (FAR) 52.243-4, CHANGES (JUN 2007) (the Changes Clause). The Changes Clause provided:

(a) The Contracting Officer may, at any time, without notice to the sureties, if any, by written order designated or indicated to be a change order, make changes in the work within the general scope of the contract including changes—

(1) In the specifications (including drawings and designs);

2 (2) In the method or manner of performance of the work;

(3) In the Government-furnished property or services; or

(4) Directing acceleration in the performance of the work.

(b) Any other written or oral order (which, as used in this paragraph (b), includes direction, instruction, interpretation, or determination) from the Contracting Officer that causes a change shall be treated as a change order under this clause; provided, that the Contractor gives the Contracting Officer written notice stating

(1) the date, circumstances, and source of the order and

(2) that the Contractor regards the order as a change order.

(c) Except as provided in this clause, no order, statement or conduct of the Contracting Officer shall be treated as a change under this clause or entitle the Contractor to an equitable adjustment.

(d) If any change under this clause causes an increase or decrease in the Contractor’s cost of, or the time required for, the performance of any part of the work under this contract, whether or not changed by any such order, the Contracting Officer shall make an equitable adjustment and modify the contract in writing. However, except for an adjustment based on defective specifications, no adjustment for any change under paragraph (b) of this clause shall be made for any costs incurred more than 20 days before the Contractor gives written notice as required. In the case of defective specifications for which the Government is responsible, the equitable adjustment shall include any increased cost reasonably incurred by the Contractor in attempting to comply with the defective specifications.

(e) The Contractor must assert its right to an adjustment under this clause within 30 days after

3 (1) receipt of a written change order under paragraph (a) of this clause or

(2) the furnishing of a written notice under paragraph (b) of this clause, by submitting to the Contracting Officer a written statement describing the general nature and amount of the proposal, unless this period is extended by the Government. The statement of proposal for adjustment may be included in the notice under paragraph (b) above.

(f) No proposal by the Contractor for an equitable adjustment shall be allowed if asserted after final payment under this contract.

(R4, tab 75 at GOV001771)

6. The contract incorporated via full text FAR 52.249-10, DEFAULT (FIXED- PRICE CONSTRUCTION) (APR 1984) (the Default clause). The Default clause provided in relevant part:

(b) The Contractor’s right to proceed shall not be terminated nor the Contractor charged with damages under this clause, if—

(1) The delay in completing the work arises from unforeseeable causes beyond the control and without the fault or negligence of the Contractor. Examples of such causes include

....

(x) unusually severe weather, or delays of subcontractors or suppliers at any tier arising from unforeseeable causes beyond the control and without the fault or negligence of both the Contractor and the subcontractors or suppliers . . ..

(R4, tab 75 at GOV001782-83) (emphasis added)

4 7. The contract incorporated via full text FAR 52.236-15, SCHEDULES FOR CONSTRUCTION CONTRACTS (APR 1984) (R4, tab 75 at GOV001767-68). This clause provided, in relevant part:

(b)The Contractor shall enter the actual progress on the chart as directed by the Contracting Officer, and upon doing so shall immediately deliver three copies of the annotated schedule to the Contracting Officer. If, in the opinion of the Contracting Officer, the Contractor falls behind the approved schedule, the Contractor shall take steps necessary to improve its progress, including those that may be required by the Contracting Officer, without additional cost to the Government.

Free access — add to your briefcase to read the full text and ask questions with AI

David Boland, Inc., (asbca 2024).

David Boland, Inc. (David Boland, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related