David Boland, Inc.

CourtArmed Services Board of Contract Appeals
DecidedMarch 30, 2023
Docket63007, 63008
StatusPublished

This text of David Boland, Inc. (David Boland, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
David Boland, Inc., (asbca 2023).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeals of - ) ) David Boland, Inc. ) ASBCA Nos. 63007, 63008 ) Under Contract No. W91278-16-D-0013 ) Task Order No. W912QR-18-F-0567 )

APPEARANCES FOR THE APPELLANT: Denis L. Durkin, Esq. Baker & Hostetler LLP Orlando, FL

W. Barron A. Avery, Esq. Brian V. Johnson, Esq. Baker & Hostetler LLP Washington, DC

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney David C. Brasfield, Jr., Esq. Kristine M. Knodel, Esq. Engineer Trial Attorneys U.S. Army Engineer District, Mobile

OPINION BY ADMINISTRATIVE JUDGE SWEET ON APPELLANT’S MOTION FOR RECONSIDERATION

On December 14, 2022, appellant David Boland, Inc. (Boland) moved for reconsideration of our November 14, 2022, decision in David Boland, Inc., ASBCA Nos. 63007, 63008, 23-1 BCA ¶ 38,242 (Decision), which denied Boland’s motions for summary judgment, and granted the government’s cross-motions for summary judgment. Motions for reconsideration are only appropriate if they are based upon newly discovered evidence, mistakes in the findings of fact, or errors of law. Green Valley Co., ASBCA No. 61275, 18-1 BCA ¶ 37,044 at 180,330. “Motions for reconsideration do not afford litigants the opportunity to take a ‘second bite at the apple’ or to advance arguments that properly should have been presented in an earlier proceeding.” Dixon v. Shinseki, 741 F.3d 1367, 1378 (Fed. Cir. 2014) (citations and quotations omitted).

The gist of our earlier opinion was that the task order at issue, which required Boland to provide trailers for use by military personnel while their offices were being repaired and expanded, also required the provision of appropriate telecommunications for those trailers, despite the fact that the government had initially, erroneously approved Boland’s plans which did not include the provision of such telecommunications. Here, Boland argues that we should reconsider the Decision because we improperly dismissed Boland’s claims regarding the Base Defense Operations Center (BDOC), and Counts III (Unabsorbed Overhead) and IV (Breach of Contract—Compensable Delay) of ASBCA Nos. 63007 and 63008. As discussed below, Boland fails to establish that reconsideration of the Decision’s dismissal of Boland’s BDOC claims is appropriate. However, the Decision made an error of law to the extent that it dismissed Counts III and IV of ASBCA Nos. 63007 and 63008 in their entirety because we had not read the allegations in those counts of Boland’s complaints as expansively as we should have. Therefore, the motion for reconsideration is granted in part, and denied in part.

DISCUSSION

I. BDOC Claims

Boland fails to establish that reconsideration of the Decision’s dismissal of Boland’s BDOC claims is appropriate. Boland first argues that the dismissal was inappropriate because a November 30, 2021, supplemental contracting officer final decision (COFD) admitted that the addition of a BDOC constituted a compensable change (app. mot. 1 at 4-5, ex. A). However, the supplemental COFD is not new evidence because it is dated November 30, 2021 (app. mot. at ex. A)—well before Boland moved for summary judgment on April 22, 2022. Boland, 23-1 BCA ¶ 38,242 at 185,696. Nor did the Decision make a mistake in its findings of fact or an error of law by not addressing whether the supplemental COFD admitted that the addition of a BDOC constituted a compensable change, id., because Boland failed to even mention the supplemental COFD in its motions for summary judgment and responses to the government’s cross-motions for summary judgment; let alone argue that the supplemental COFD admitted that the addition of a BDOC constituted a compensable change. (63007 app. msj at 26-28; 63008 app. msj at 29-32; see generally app. reply in support of msj). Therefore, arguing now that the supplement COFD admitted that the addition of a BDOC constituted a compensable change constitutes an improper attempt to take a second bite at the apple by advancing arguments that properly should have been—but were not—presented earlier. Dixon, 741 F.3d at 1378. In any event, we would not be bound by the COFD’s findings. Sand Point Services, LLC, ASBCA Nos. 61819, 61820, 19-1 BCA ¶ 37,412 at 181,860 n.1.

1 For ease of understanding, we cite to: (1) appellant’s motion for reconsideration as “app. mot. at_”; (2) appellant’s motion for summary judgment in ASBCA No. 63007 as “63007 app. msj at_”; (3) appellant’s motion for summary judgment in ASBCA No. 63008 as “63008 app. msj at _”; and (4) appellant’s reply in support of its motion for summary judgment and response to the government’s cross-motion for summary judgment in ASBCA Nos. 63007 and 63008 as “app. reply in support of msj at _”. 2 Second, Boland argues that the Decision erroneously found that Boland had failed to make any arguments about the BDOC separate from its telecommunications systems arguments, Boland, 23-1 BCA ¶ 38,242 at 185,896 n.2, because Boland stated in its ASBCA No. 63008 2 motion for summary judgment that:

(1) “[T]he B-353 Task Order did not require the installation or construction of a Base Defense Operations Center (‘BDOC’) in the project’s Trailers,” (63008 app. msj at 1);

(2) “The Base RFP did not provide for a BDOC,” (id. at 12);

(3) “[T]he Government expressly removed the requirement for a BDOC,” (id.);

(4) “USACE’s Directive to Design and Build a Telecommunications System and the BDOC Temp Requirement Constituted Constructive Change[s] as a Matter of Law,” (id. at 33 (emphasis added));

(5) “[T]he Government’s directive to design and install the Telecommunications System and the BDOC Temp Requirement for the Security Facility Trailers constituted constructive change[s],” (id. (emphasis added)); and

(6) “USACE compelled Boland to perform work not required under the terms of the B-353 Security Facility Task Order when it directed Boland to design and install the Telecommunications System and the BDOC Temp Requirement in the Security Facility Trailers,” (id. at 34 (emphasis added); see also app. mot. at 5-6).

However, those first three statements merely are general factual assertions about the BDOC in the Introduction or Statement of Undisputed Material Facts, which are devoid of any argument (63008 app. msj at 1, 12). Moreover, the last three statements confirm that Boland’s arguments about the BDOC were intertwined with its arguments about the telecommunications systems because, as the bolded language indicates, Boland addressed the BDOC and telecommunications systems together (id. at 33-34). Thus, the Decision did not make a mistake in its findings of fact or an error of law by concluding that Boland

2 Boland’s ASBCA No. 63007 motion for summary judgment contained even fewer references to the BDOC, only referring to it twice in the Introduction, and once in a footnote (63007 app. msj at 1, 15). 3 failed to make any arguments about the BDOC separate from the telecommunications systems. 3

Third, Boland argues in its reply brief that a BDOC is fundamentally different than a telecommunications system because a BDOC is a physical structure or a room, while a telecommunications system is a system (app. reply at 6-8). That is an argument that properly should have been—but was not—presented in connection with the summary judgment motions (see 63007 app. msj at 29-40; 63008 app. msj at 33-44; app. reply in support of msj at 5-57). Therefore, it is not an appropriate basis for a motion for reconsideration. Dixon, 741 F.3d at 1378.

II. Counts III and IV of ASBCA Nos. 63007 and 63008

The Decision made an error of law to the extent that it dismissed Counts III and IV of ASBCA Nos. 63007 and 63008 in their entirety.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dixon v. Shinseki
741 F.3d 1367 (Federal Circuit, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
David Boland, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/david-boland-inc-asbca-2023.