Tenaska Washington Partners, L.P. v. United States

34 Fed. Cl. 434, 1995 U.S. Claims LEXIS 214, 1995 WL 669652
CourtUnited States Court of Federal Claims
DecidedNovember 9, 1995
DocketNo. 95-420C
StatusPublished
Cited by6 cases

This text of 34 Fed. Cl. 434 (Tenaska Washington Partners, L.P. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tenaska Washington Partners, L.P. v. United States, 34 Fed. Cl. 434, 1995 U.S. Claims LEXIS 214, 1995 WL 669652 (uscfc 1995).

Opinion

OPINION

MILLER, Judge.

This case is before the court after argument on defendant’s motion to dismiss or stay and to compel arbitration and plaintiffs cross-motion to enforce the parties’ arbitration agreement if they are required to arbitrate their dispute. A partnership seeks to hold the Bonneville Power Administration, an agency within the Department of Energy, liable for breach of a written contract to develop electrical power, including construction of a power plant. The Government terminated the contract after construction began, but before the power plant was built. At issue is whether, under the terms of the contract, defendant can compel plaintiff to participate in arbitration proceedings. Plaintiff insists that, if arbitration is ordered, the Government must be bound to any decision and that the arbitration provision must be enforced insofar as it requires the Government to continue to perform its contractual obligation to make payments on the contract pending arbitration.

FACTS

The following characterization of the case is gleaned from the pleadings. For the purpose of ruling on the parties’ cross-motions, the court need not make any findings of fact.

On July 16, 1992, the Bonneville Power Administration (“BPA”), an agency within the Department of Energy (“DOE”), and Te-naska Washington Partners II, L.P. (“plaintiff’), a Washington State partnership, entered into a Letter of Intent specifying terms upon which BPA proposed to acquire all of the electrical output of the Frederickson Generation Project. The proposed plant was a combined-cycle combustion turbine unit with a net gathering capacity of 248 megawatts to be constructed by plaintiff in the Frederickson Industrial Area in the State of Washington. BPA selected plaintiffs project as a result of a competitive bidding process. The Letter of Intent provided, among other things, that plaintiff would terminate efforts to sell electric power and energy from the project to other potential customers and that BPA would sign a Power Purchase Agreement with plaintiff only after BPA completed required regulatory processes.

On April 1,1994, plaintiff and BPA entered into a Power Purchase Agreement. Under the terms of the agreement, BPA agreed to purchase and take from plaintiff, and plaintiff agreed to sell and deliver to BPA, for a period of 20 years, the entire net electrical output of the Frederickson Generation Project. In furtherance of the agreement, plaintiff entered into contracts with a consortium of banks to provide financing for the project and with other entities to construct, operate, maintain, and provide fuel supplies and transportation for the project. Construction of the project began in 1994.

On April 17,1995, at a meeting in Chicago, Illinois, Judith Johansen, BPA’s Vice President, Generation Supply, orally informed plaintiff that BPA would not perform its obligations under the agreement. In an April 20,1995 letter, Ms. Johansen confirmed that BPA determined that it was excused from further performing its obligations under the terms of the agreement because of alleged supervening events. The letter stated: “As a consequence of events supervening the agreement, BPA’s primary purposes in acquiring the power resource ... have been frustrated and the resource has ceased to have value to BPA.” The letter also stated that “BPA has determined that it is excused from any further obligations under the Agreement, after April 17, 1995,” and returned the letter of credit securing plaintiff’s performance obligations under the agreement.

Following exhaustion of procedures for claims under the Contract Disputes Act of 1978, 41 U.S.C. §§ 601-613 (1988 & Supp. V 1993), on June 23, 1995, plaintiff instituted suit in the United States Court of Federal Claims alleging that BPA breached the [437]*437agreement. On June 27, 1995, four days after filing in this court, plaintiff filed in the United States Court of Appeals for the Ninth Circuit a “Petition for Review Under the Northwest Power Act (Precautionary)” (the “Ninth Circuit Petition”), alleging that BPA breached the parties’ agreement. Shortly thereafter, on July 6, 1995, plaintiff filed in the Ninth Circuit a motion to transfer the matter to the Court of Federal Claims pursuant to 28 U.S.C. § 1631 (1988 & Supp. V 1993). On the same date, plaintiff filed in this court a “Notice of Filing of Precautionary Petition for Review,” asserting that its pending Ninth Circuit Petition did not divest the court of jurisdiction pursuant to 28 U.S.C. § 1500 (1988 & Supp. Y 1993), because the Petition was “expressly precautionary” and the Ninth Circuit lacked subject matter jurisdiction. On August 22, 1995, at plaintiffs request, its Ninth Circuit petition was transferred to the Court of Federal Claims.1

The agreement included an arbitration clause which reads in full:

DISPUTE RESOLUTION Pending resolution of a disputed matter, the Parties shall continue performance of their respective obligations pursuant to this Agreement. Disputes regarding any matter relating to this Agreement shall be discussed by the Authorized Representatives who shall use their best efforts to amicably and promptly resolve the dispute. Should the Authorized Representatives be unable to resolve any controversy or claim arising out of or relating to this Agreement, or the breach thereof, the Parties agree that the controversy or claim shall be settled by arbitration in accordance with the Commercial Arbitration Rules of the American Arbitration Association, and judgment upon the award rendered by the Arbitrator(s) may be entered in any court having jurisdiction thereof.

Because of changes in legal posture, the sequence of arguments contained in the parties’ briefs deserves special attention. On July 31, 1995, anticipating filing a motion to compel arbitration, as purportedly required under the contract, defendant filed a Motion for a Protective Order Staying Discovery. Plaintiff opposed the motion, arguing that BPA lacked constitutional or statutory authority to enter binding arbitration. On August 22, 1995, defendant filed its Motion To Dismiss or Stay and To Compel Arbitration, and plaintiff opposed and cross-moved. Plaintiff emphasized the lack of constitutional and statutory authority and the inapplicability of the arbitration clause to this type of dispute. Defendant replied with a brief of extraordinary import. Defendant argued that long-standing opinions of the Department of Justice regarding the constitutionality of binding arbitration had been reviewed and reversed through a memorandum dated September 7, 1995 from the Office of Legal Council (the “OLC”).

Defendant requests a dismissal or stay of the proceedings and an order compelling plaintiff to submit its claim to arbitration based on the terms of the agreement. Defendant takes the position that the arbitration clause is binding on the parties and thus that arbitration is mandatory. Plaintiff and defendant have cross-moved on the basis of the plain language of the contract. In addition, plaintiff cross-moves for an order that, if it is required to submit to arbitration, 1) the award entered by the arbitrators will be binding on both parties, and 2) BPA must continue performance of the agreement pending resolution of the dispute.

DISCUSSION

Free access — add to your briefcase to read the full text and ask questions with AI

Related

County of Santa Clara v. Trump
267 F. Supp. 3d 1201 (N.D. California, 2017)
Electronic Privacy Information Center v. Department of Justice
584 F. Supp. 2d 65 (District of Columbia, 2008)
Electric Lightwave, Inc. v. Richardson
106 F. Supp. 2d 1063 (D. Oregon, 1999)
Frillz, Inc. v. Lader
925 F. Supp. 83 (D. Massachusetts, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
34 Fed. Cl. 434, 1995 U.S. Claims LEXIS 214, 1995 WL 669652, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tenaska-washington-partners-lp-v-united-states-uscfc-1995.