United States v. Great Falls Manufacturing Co.

112 U.S. 645, 5 S. Ct. 306, 28 L. Ed. 846, 1884 U.S. LEXIS 1913
Supreme Court of the United States·Decided December 22, 1884·No. 111·Published·Cited by 170 cases

Opinion

Mr. Justice Harlan

delivered the opinion of the court. He recited the facts as above stated, and continued:

The articles of agreement of November 20, 1862, between *654 the Secretary of the Interior and the Great Falls Manufacturing Company, made ample provision for the protection of the public interests; for, the right was reserved to the party dissatisfied, to proceed by suit in equity in the proper court of this District, for the purpose of having the award set aside or changed, and of obtaining such a decree, subject to review by this court, as was just and equitable. There is no doubt of the good faith of the effort of the parties to accommodate their differences, or that it was of the highest importance to the government that the obstacles should be removed to the successful completion of the work, upon which large sums had been expended. In the opinion of the court below, and in the arguments of counsel, the authority of the Secretary of the Interior to make the government a party to that agreement is discussed. But, in the view we take, it is unnecessary to determine that question. Our decision may be satisfactorily placed on other grounds.

, From the report and documents transmitted to Congress by President Fillmore, it appears that, in the judgment of the Engineer Department, the best mode of supplying the cities of Washington and Georgetown with wholesome water, wras by an aqueduct from the Great Falls of the Potomac; also, that such a plan necessarily involved the construction of a dam at that point in the river. Ex. Doc. (Senate) No. 48, pp. 2, 35, 48, 32d Cong. 2d Sess. By the annual report, under date of December 4, 1863, of Mr. Usher, Secretary of the Interior, Congress was informed that “ certain parties having from time to time made claim to heavy damages for the diversion of the water from the Potomac River,” his immediate predecessor, “ with a view to settle and end this claim, entered into an agreement of arbitration with the claimants.” The parties referred to were the present claimants, as appears by the agreement of arbitration, by the official documents submitted to Congress, and by the proceedings in the courts of Maryland for an assessment of the damages which the proposed dam should cause to the Great Falls Manufacturing Company. The Secretary said: “ Pursuant to this agreement, the arbitrators met from time to time, and finally submitted their award, by which they adjudged in *655 favor of the claimants upon each and all of the plans and modes submitted to them, being three [four] in number, for the construction of the dam across the Potomac, and also $12,000 for their own fees as arbitrators, and $761.84 for the expenses of arbitration. The sums being large, I did not feel justified in- applying the existing appropriation for the completion of the aqueduct to the payment thereof, preferring to submit the whole matter to Congress for its determination. It appears from the report of the experienced engineer in charge of the work, as must be obvious to every observer, that an ample supply of water for the use of the cities of Washington and Georgetown, for many years to come, can be obtained from the Potomac by the erection of a tight dam, extending from the Maryland shore to Gonrús Island, to a height which will give á head of six feet in the aqueduct, and yield a daily supply of 65,000,000 gallons,” etc. After expressing the opinion that such a dam could not work injury to the proprietors of the water rights claimed at the Great Falls, the Secretary recommended that a reasonable sum be appropriated to pay the expenses of the arbitration, and that the -cost previously estimated of a dam across the main channel be diminished to that of the proposed dam over the east channel.

In conformity with that recommendation, Congress, by the act of July 4,1864, made the appropriation of $150,000 for the purpose of constructing the proposed dam of solid masonry, and for paying the existing liabilities and the expenses connected with the engineering, superintendence, and repairs of the aqueduct. Immediately thereafter a contract -was made for the construction of that dam. In his next annual report, under date of December 5, 1864, the Secretary informed Congress that the work upon the dam and the aqueduct required the expenditure of the additional sum of $51,945. For that amount an appropriation was promptly made. With the Secretary’s report was transmitted to Congress that of the engineer in charge, who stated that “ the question of land damages and water rights at the Great Falls still remains unsettled.” The dam was completed to its present height in 1867, and is used as an indispensable part of the system by which the cities *656 of Washington and Georgetown have been supplied with water. Beyond doubt, the land and the water rights and privileges in question have for nearly twenty years been held' and used by officers and agents of the government, without any compensation whatever having been made therefor to the claimant. By what authority have they appropriated to public use the property of the claimant ? The answer to this question will determine whether the present demand of the claimant arises out of an implied contract, and, therefore, enforceable by suit against the United States in the Court of Claims.

It seems clear that these property rights have been held and used by the agents of the United States, under the sanction of legislative enactments by Congress; for, the appropriation of money specifically for the construction of the dam from the Maryland shore to Conn’s Island was, all the circumstances considered, equivalent to an express direction by the legislative and executive branches of the government to its officers to take this particular property for the public objects contemplated by the scheme for supplying the capital of the nation with wholesome water. The making of the improvements necessarily involves the taking of the property; and if, for the want of formal proceedings for its condemnation to public use, the claimant was entitled, at the beginning of the work, to have the agents of the government enjoined from prosecuting it until provision, was made for securing, in some way, payment of the compensation required by the Constitution — upon which question we express no opinion — there is no sound reason why the claimant might not waive that right, and, electing to regard the action of the government as a taking under its sovereign right of eminent domain, demand just compensation. Kohl v. United States, 91 U. S. 367, 374. In that view, we are of opinion that the United States, having by its agents, proceeding under the authority of an act qf Congress, taken the property of the claimant for public use, are under an obligation, imposed by the Constitution, to make compensation. The law' will imply a promise to make the required compensation, Avhere property, to which the government asserts no title, is taken, pursuant to an act of Congress, as private property to *657 be applied for public uses.

Free access — add to your briefcase to read the full text and ask questions with AI

United States v. Great Falls Manufacturing Co., 112 U.S. 645, 5 S. Ct. 306, 28 L. Ed. 846, 1884 U.S. LEXIS 1913 (1884).

112 U.S. 645 (United States v. Great Falls Manufacturing Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Lion Raisins, Inc. v. United States
416 F.3d 1356 (Federal Circuit, 2005)
No. 97-5055
146 F.3d 1358 (Federal Circuit, 1998)
Public Service Commission v. Highfield Water Co.
441 A.2d 1031 (Court of Appeals of Maryland, 1982)
Bunch v. Barnett
376 F. Supp. 23 (D. South Dakota, 1974)
Cereghino v. State Highway Commission
370 P.2d 694 (Oregon Supreme Court, 1962)
Mississippi State Highway Commission v. McCardle
137 So. 2d 793 (Mississippi Supreme Court, 1962)
Seneca Nation of Indians v. Brucker
162 F. Supp. 580 (District of Columbia, 1958)
Gladys Laycock v. United States
230 F.2d 848 (Ninth Circuit, 1956)
Thibodo v. United States
187 F.2d 249 (Ninth Circuit, 1951)
23 Tracts of Land v. United States
177 F.2d 967 (Sixth Circuit, 1949)
Griffin v. United States
77 F. Supp. 197 (Court of Claims, 1948)
Angelle v. State
34 So. 2d 321 (Supreme Court of Louisiana, 1948)
Moyle v. Salt Lake City
176 P.2d 882 (Utah Supreme Court, 1947)
Miramar Co. v. City of Santa Barbara
143 P.2d 1 (California Supreme Court, 1943)
Hunter v. City of Mobile
13 So. 2d 656 (Supreme Court of Alabama, 1943)
Rose v. State of California
123 P.2d 505 (California Supreme Court, 1942)
Yearsley v. W. A. Ross Construction Co.
309 U.S. 18 (Supreme Court, 1940)
State Ex Rel. Board of County Commissioners v. Bruce
69 P.2d 97 (Montana Supreme Court, 1937)