OPINION AND ORDER
LAFFITTE, District Judge.
Pending before the Court is the issue of how and in what order the legal theories presented in this case will be tried. This
case
arises out of the construction of a project known as the “Mayaguez Composting Facility.” In 1987 the Puerto Rico Aqueduct and Sewer Authority (“PRASA”) contracted the engineering and architecture firm of Le-brón Associates (“Lebrón”) to design the facility. PRASA also contracted Constructora Lluch, S.E., (“Lluch”) in May 1988 to build the facility. In October 1988, Lluch subcontracted Plaintiff Richmond Steel, Inc. (“RSI”) to manufacture and install the steel components of the facility. In October 1989, before RSI completed its work, a portion of the steel structure collapsed. RSI brought this claim for declaratory relief and monetary damages. As is common in multi-party construction cases, a flurry of counterclaims, cross-claims, and third-party claims followed. Each party alleges that the others are responsible for the collapse.
The trial is scheduled for June 21, 1993. The majority of the claims in this case are based on allegations of negligence. However, in its amended cross-claim
, PRASA has brought an action under Article 1483 of the Puerto Rico Civil Code. Following further reflection on the history, purpose, and case law anent this article, the Court
sua
sponte
dismisses PRASA’s claims brought under it. However, the Court will allow PRASA to proceed with its claims based in a theory of negligence.
DISCUSSION
The article under which PRASA brings its claims reads as follows:
Liability of contractor and architect for collapse of building
The contractor of a building which may have been destroyed by reason of defects in the construction shall be liable for the losses and damages if said building should collapse within ten (10) years, to be counted from the completion of the construction; and during the same time -the same liability'shall be incurred by the architect who may have directed the work if the collapse is due to defects in the ground or in the direction.
If the cause should be the noncompli-anee of the contractor with the conditions of the contract, the action for indemnity may be brought within fifteen (15) years.
P.R.Laws Ann. tit. 31, § 4124 (1991). This article, known in Spanish as the
plazo decenal,
has its origins in Roman law.
Federal Ins. Co. v. Dresser Ind., Inc.,
111 D.P.R. 96, 101 n. 1, 11 Official translations 125, 132 n. 1 (1981);
Géigel v. Mariani,
85 P.R.R. 43, 45 (1962). Such a provision is found in many civil code jurisdictions.
See generally Rivera v. Las Vegas Dev. Co.,
107 D.P.R. 384, 388-89, 7 Official translations 425, 429-31 (1978);
Géigel,
85 P.R.R. at 45. The
plazo decenal
provides a jurisdictional period after which a claim may no longer be brought.
Oliveras-Salas v. Puerto Rico Highway Auth.,
884 F.2d 1532, 1534 (1st Cir.1989);
Martinez v. Calzadilla,
756 F.Supp. 78, 80-82 (D.P.R.1991).
Moreover, article 1483 is both a source of specific liability and a time limitation on that liability.
In re San Juan DuPont Plaza Hotel Fire Litigation,
687 F.Supp. 716, 728 (D.P.R.1988). It serves to protect the owner of a building from, and make the contractor or architect liable for,
hidden defects
that the building may have at the time of delivery.
Constructora Bauzá, Inc. v. García López,
91 JTS 99, 9077 (1991);
Gonzalez v. Agostini,
79 P.R.R. 481, 490-92 (1956);
Felix Davis v. Vieques Air Link,
892 F.2d 1122, 1127-28 (1st Cir.1990). Under article 1483, the owner has ten years from the date of delivery of the construction to bring an action against the contractor or architect.
Bartolomei v. Superior Court,
98 P.R.R. 484, 486 (1970); II-II José Puig Brutau,
Fundamentos de Derecho Civil,
at 454
(2d rev. ed. 1982). The reasoning behind article 1483 is that there may be undiscovera-ble hidden defects in a building when the owner receives it. It is only with the passage of time that these defects will become apparent. The owner's acceptance of the building should not constitute a waiver of subsequent claims he may have against the party responsible for these defects:
González,
79 P.R.R. at 489; José Ramón Velez Torres,
Los Contratos,
at 434-36 (1985); 10-II José Maria Manresa,
Codigo Civil Español,
at 709 (6th rev. ed. 1969); 24-11 Q.M. Scaevola,
Codigo Civil,
at 95 (2d rev. ed. 1951); 2-II Marcel Planiol,
Treatise on the Civil Law,
at 147 (Louisiana State Law Institute .trans., 11th ed. 1939). '
The language of article 1483 indicates that PRASA can not bring a claim under it. The article’s ten-year period is counted from “the completion of the construction.” In the case before the Court, the structure was never completed; the collapse occurred during the construction. Thus, the ten-year jurisdictional period has not begun. The purpose of article 1483 also indicates that it is inapplicable to the facts of this case. The article is intended to protect an owner from
hidden
defects that emerge
after
the work has. been
delivered
to him.
González,
79 P.R.R. at 490-92;
Vieques Air Link,
892 F.2d at 1127-28. The defect here — the collapsed structure — was not hidden, it was readily apparent. Moreover, a completed composting structure was never delivered to PRASA. Article 1483 does not apply in the case of a building that has collapsed before it has been completed and delivered.
See Brasher
v.
City of Alexandria,
215 La. 887, 931-32, 41 So.2d 819, 834 (1949) (The equivalent article in the Louisiana Civil Code is not applicable where there has not been a completion by the builder or formal acceptance by the owner.). The Court finds persuasive the Louisiana Supreme Court’s ruling in
Brasher
on the Louisiana Civil Code.
Accordingly, the Court holds that PRASA does not have a cause of action under article 1483 for the collapsed structure in this case.
Free access — add to your briefcase to read the full text and ask questions with AI
OPINION AND ORDER
LAFFITTE, District Judge.
Pending before the Court is the issue of how and in what order the legal theories presented in this case will be tried. This
case
arises out of the construction of a project known as the “Mayaguez Composting Facility.” In 1987 the Puerto Rico Aqueduct and Sewer Authority (“PRASA”) contracted the engineering and architecture firm of Le-brón Associates (“Lebrón”) to design the facility. PRASA also contracted Constructora Lluch, S.E., (“Lluch”) in May 1988 to build the facility. In October 1988, Lluch subcontracted Plaintiff Richmond Steel, Inc. (“RSI”) to manufacture and install the steel components of the facility. In October 1989, before RSI completed its work, a portion of the steel structure collapsed. RSI brought this claim for declaratory relief and monetary damages. As is common in multi-party construction cases, a flurry of counterclaims, cross-claims, and third-party claims followed. Each party alleges that the others are responsible for the collapse.
The trial is scheduled for June 21, 1993. The majority of the claims in this case are based on allegations of negligence. However, in its amended cross-claim
, PRASA has brought an action under Article 1483 of the Puerto Rico Civil Code. Following further reflection on the history, purpose, and case law anent this article, the Court
sua
sponte
dismisses PRASA’s claims brought under it. However, the Court will allow PRASA to proceed with its claims based in a theory of negligence.
DISCUSSION
The article under which PRASA brings its claims reads as follows:
Liability of contractor and architect for collapse of building
The contractor of a building which may have been destroyed by reason of defects in the construction shall be liable for the losses and damages if said building should collapse within ten (10) years, to be counted from the completion of the construction; and during the same time -the same liability'shall be incurred by the architect who may have directed the work if the collapse is due to defects in the ground or in the direction.
If the cause should be the noncompli-anee of the contractor with the conditions of the contract, the action for indemnity may be brought within fifteen (15) years.
P.R.Laws Ann. tit. 31, § 4124 (1991). This article, known in Spanish as the
plazo decenal,
has its origins in Roman law.
Federal Ins. Co. v. Dresser Ind., Inc.,
111 D.P.R. 96, 101 n. 1, 11 Official translations 125, 132 n. 1 (1981);
Géigel v. Mariani,
85 P.R.R. 43, 45 (1962). Such a provision is found in many civil code jurisdictions.
See generally Rivera v. Las Vegas Dev. Co.,
107 D.P.R. 384, 388-89, 7 Official translations 425, 429-31 (1978);
Géigel,
85 P.R.R. at 45. The
plazo decenal
provides a jurisdictional period after which a claim may no longer be brought.
Oliveras-Salas v. Puerto Rico Highway Auth.,
884 F.2d 1532, 1534 (1st Cir.1989);
Martinez v. Calzadilla,
756 F.Supp. 78, 80-82 (D.P.R.1991).
Moreover, article 1483 is both a source of specific liability and a time limitation on that liability.
In re San Juan DuPont Plaza Hotel Fire Litigation,
687 F.Supp. 716, 728 (D.P.R.1988). It serves to protect the owner of a building from, and make the contractor or architect liable for,
hidden defects
that the building may have at the time of delivery.
Constructora Bauzá, Inc. v. García López,
91 JTS 99, 9077 (1991);
Gonzalez v. Agostini,
79 P.R.R. 481, 490-92 (1956);
Felix Davis v. Vieques Air Link,
892 F.2d 1122, 1127-28 (1st Cir.1990). Under article 1483, the owner has ten years from the date of delivery of the construction to bring an action against the contractor or architect.
Bartolomei v. Superior Court,
98 P.R.R. 484, 486 (1970); II-II José Puig Brutau,
Fundamentos de Derecho Civil,
at 454
(2d rev. ed. 1982). The reasoning behind article 1483 is that there may be undiscovera-ble hidden defects in a building when the owner receives it. It is only with the passage of time that these defects will become apparent. The owner's acceptance of the building should not constitute a waiver of subsequent claims he may have against the party responsible for these defects:
González,
79 P.R.R. at 489; José Ramón Velez Torres,
Los Contratos,
at 434-36 (1985); 10-II José Maria Manresa,
Codigo Civil Español,
at 709 (6th rev. ed. 1969); 24-11 Q.M. Scaevola,
Codigo Civil,
at 95 (2d rev. ed. 1951); 2-II Marcel Planiol,
Treatise on the Civil Law,
at 147 (Louisiana State Law Institute .trans., 11th ed. 1939). '
The language of article 1483 indicates that PRASA can not bring a claim under it. The article’s ten-year period is counted from “the completion of the construction.” In the case before the Court, the structure was never completed; the collapse occurred during the construction. Thus, the ten-year jurisdictional period has not begun. The purpose of article 1483 also indicates that it is inapplicable to the facts of this case. The article is intended to protect an owner from
hidden
defects that emerge
after
the work has. been
delivered
to him.
González,
79 P.R.R. at 490-92;
Vieques Air Link,
892 F.2d at 1127-28. The defect here — the collapsed structure — was not hidden, it was readily apparent. Moreover, a completed composting structure was never delivered to PRASA. Article 1483 does not apply in the case of a building that has collapsed before it has been completed and delivered.
See Brasher
v.
City of Alexandria,
215 La. 887, 931-32, 41 So.2d 819, 834 (1949) (The equivalent article in the Louisiana Civil Code is not applicable where there has not been a completion by the builder or formal acceptance by the owner.). The Court finds persuasive the Louisiana Supreme Court’s ruling in
Brasher
on the Louisiana Civil Code.
Accordingly, the Court holds that PRASA does not have a cause of action under article 1483 for the collapsed structure in this case.
The Puerto Rico Supreme Court has not addressed the issue of whether a claim under article 1483 may be brought by an owner before completion or acceptance of a construction. Based on the language and purpose of article 1483, discussed in the above-cited treatises and cases, it is reasonable to conclude that the Puerto Rico Supreme Court would hold that such a claim may not be brought..
Moreover, a survey of the facts in cases where the Puerto Rico Supreme Court considered the article supports the conclusion that PRASA does not have a claim under it. In these cases there has been a delivery of the work and a defect that arose subsequent to the delivery.
See, e.g., Roselló Cruz v. Garcia,
116 D.P.R. 511, 512-13, 16 Official translations 626, 629 (1985);
Interstate Gen. Corp. v. Soto,
113 D.P.R. 298, 299, 13 Official translations 389, 391 (1982);
Fantauzzi v. Pleasant Homes, Inc.,
113 D.P.R. 132, 133, 13 Official translations 173, 174 (1982);
Carreras v. González Santos,
111 D.P.R. 819, 820-21, 11 Official translations 1037, 1039-40 (1981);
Acevedo Hernández v. Viñas Sorbá,
111 D.P.R. 633, 635, 11 Official translations 797, 800 (1981);
Maldonado Pérez v. Las Vegas Dev.,
111 D.P.R. 573, 573-74, 11 Official translations 716, 717 (1981);
Dresser,
111 D.P.R. at 99, 11 Official translations at 129;
Rivera,
107 D.P.R. at 384-85, 7 Official translations at 425;
De Jesús v. Ponce Housing Corp.,
104 D.P.R. 885, 886, 4 Official translations 1241, 1243 (1976);
Pereira v. I.B.E.C.,
95 P.R.R. 28, 34-35 (1967). The Court has found no case where an action was brought under article 1483 for defects that had arisen before
the completion of the work and before the owner’s acceptance of it.
While PRASA may not bring an action here under article 1483, it is not without a remedy. PRASA’s amended cross-claim alleges negligence on the part of the other parties involved in the construction of the structure. Therefore, the Court will treat its claim as one based in a theory of negligence. In a claim under article 1483, there is a rebuttable presumption of fault on the part of the builder or the architect.
Viñas Sorbá,
111 D.P.R. at 638, 11 Official translations at 804. The owner need only show that the ruin was caused by defects in the construction or in the ground.
Corp. Presiding Bishop CJC v. Purcell,
117 D.P.R. 714, 723-24, 17 Official translations 854, 865 (1986). The contractor or architect then has the burden to show by a preponderance of the evidence that the ruin was caused not by his work but by an unforeseeable and unpreventable force majeure.
Roselló Cruz,
116 D.P.R. at 519, 16 Official translations at 637. However, PRASA will not be the beneficiary of these presumptions. Rather, it, like the other claimants in this case, will have the burden of showing by a preponderance of the evidence that the other parties were negligent in their work on the structure. ■
IT IS SO ORDERED.