PRASA v. Constructory Lluch

CourtCourt of Appeals for the First Circuit
DecidedJanuary 20, 1999
Docket98-1331
StatusPublished

This text of PRASA v. Constructory Lluch (PRASA v. Constructory Lluch) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
PRASA v. Constructory Lluch, (1st Cir. 1999).

Opinion

United States Court of Appeals For the First Circuit

No. 98-1331

PUERTO RICO AQUEDUCT AND SEWER AUTHORITY, Plaintiff, Appellant,

v.

CONSTRUCTORA LLUCH, INC., AND CNA CASUALTY OF PUERTO RICO, INC., Defendants, Appellees.

APPEAL FROM THE UNITED STATES DISTRICT COURT

FOR THE DISTRICT OF PUERTO RICO

[Hon. Hctor M. Laffitte, U.S. District Judge]

Before

Torruella, Chief Judge,

Hall, Senior Circuit Judge,

and Lipez, Circuit Judge.

Carlos A. Rodrguez-Vidal, with whom Goldman Antonetti & Crdova was on brief, for appellant. Jos M. Biaggi-Junquera, with whom Jos Enrique Otero was on joint brief, for appellees.

February 18, 1999 TORRUELLA, Chief Judge. Before the Court is plaintiff- appellant Puerto Rico Aqueduct and Sewer Authority's ("PRASA") appeal from the district court's denial of PRASA's motion for a second partial new trial on damages. At the first partial new trial, the jury awarded PRASA no damages despite an earlier verdict finding defendant-appellee Constructora Lluch, Inc. ("Lluch") to be negligent and in breach of the construction contract between the two. PRASA also appeals from a jury award on Lluch's counterclaims against PRASA for breach of contract and for amounts owed on the contract. For the reasons stated in this opinion, we affirm the judgment awarding Lluch $756,471.59 on its counterclaims, but vacate the judgment awarding PRASA no damages on its claims and remand for a second partial new trial on the issue of damages. BACKGROUND This case arises out of the collapse, during construction, of the steel roof structure of the Mayaguez Composting Facility in October of 1989. PRASA entertained bids for the project and eventually awarded the project's design to Lebrn Associates, an engineering and architecture firm. In May of 1988, PRASA entered into a construction contract with Lluch to build the facility. Several months later, Lluch subcontracted with Richmond Steel, Inc. ("RSI") to manufacture and install the facility's steel components, including the roof. The Mayaguez facility was to be a compost treatment plant comprised of a main building to deposit and treat compost and a separate administrative building. The main building was designed as two adjacent bays with three lines of columns to support two separate steel frame roofs. Among the plans and specifications developed by Lebrn was a procedure to be followed for the preparation and consolidation of the soil. Under the procedure, Lluch was required: (1) to place a permanent landfill on the site; (2) to install wicks and pertinent instrumentation; (3) to place a surcharge on the site; and (4) to leave the surcharge undisturbed for a period of seven and a half months. However, before the consolidation of the soil was completed, Lluch removed the surcharge from the soil in order to begin the concrete construction and in order to allow RSI to begin the steel erection. On October 22, 1989, after RSI had erected a substantial part of the east portion of the steel roof structure, the uncompleted west portion of the steel roof structure collapsed. After the collapse, Lluch removed the collapsed steel frames and debris, began to repair the damaged columns, and continued with construction of the remaining phases of the project, all with PRASA's authorization and under PRASA's supervision. After Lluch had substantially completed the construction of the project -- with the exception of the steel roof structure -- PRASA demolished the entire project, over Lluch's objection. On October 10, 1990, this action was filed in United States District Court for the District of Puerto Rico by RSI, seeking monetary and declaratory relief against PRASA, Lluch, Lebrn, and their bonding and surety companies. Several counterclaims, cross-claims, and third-party claims followed, most of which were dismissed before trial. Included in those rulings, the district court dismissed PRASA's cross-claim under Article 1483 of the Puerto Rico Civil Code against Lluch and RSI. See Richmond Steel, Inc. v. Legal and Gen. Assurance Soc'y, Ltd., 825 F. Supp. 443, 445 (D.P.R. 1993). At the first trial in 1993, some of the parties entered into various stipulations, including the dismissal of original plaintiff RSI. The district court then realigned the parties to continue the trial. As a result, PRASA became the plaintiff, and Lluch, Lebrn, and CNA Casualty of Puerto Rico, Inc. ("CNA") remained as defendants. On August 9, 1993, after a twenty-four day trial, the jury, in a special verdict form, found: (1) that Lluch improperly removed the surcharge from the construction site or in some other way breached its contract with PRASA by negligent construction work; (2) that this breach caused the collapse of the roof structure; (3) that this breach caused damages to PRASA; (4) that PRASA's demolition of the remains of the structure was unjustified; and (5) that PRASA suffered $4,587,202.77 in damages as a result of Lluch's breach. With regard to the counterclaims against PRASA, the jury found: (1) that PRASA breached its contract with Lluch; (2) that this breach caused damages to Lluch in the amount of $138,758; (3) that PRASA owed Lluch $617,713.59 for work performed on the contract; and (4) that PRASA owed Lebrn $40,148.28 on the contract. As a result of these findings, the jury awarded: (1) $4,587,202.77 to PRASA for Lluch's negligence and breach of contract; (2) $756,471.59 to Lluch on its counterclaims against PRASA for breach of contract and money owed on the contract; and (3) $40,148.28 to Lebrn on its counterclaim against PRASA for money owed on the contract. On October 15, 1993, the district court issued a judgment consistent with the damages awarded by the jury. In an order issued the same day, the district court advised counsel that all post-trial motions were required to be filed or renewed within 10 days of the date of the judgment. On October 21, 1993, CNA and Lluch filed a timely motion for a new trial on PRASA's claims. On November 4, 1993 -- twenty days after the entry of judgment -- PRASA filed a motion for judgment as a matter of law with regard to Lluch's counterclaims. On July 27, 1994, the court granted CNA and Lluch's motion for a new trial, subject to PRASA's acceptance of a remittitur. The court concluded that the jury award was excessive in light of the evidence presented. The court then gave PRASA the option of accepting a remitted award of $1,224,000 or a partial new trial on damages. PRASA opted for a new trial. On March 24, 1995, the court denied PRASA's motion for judgment as a matter of law on Lluch's counterclaims. The court found that the evidence was sufficient to allow a reasonable jury to reach a verdict in favor of Lluch on those claims. On February 7, 1996, the court set the scope of the partial new trial on damages for PRASA's claims. The court held that the new trial would be limited only to the extent of PRASA's damages at the time of the collapse. The court concluded that, because the jury in the first trial found that PRASA was unjustified in demolishing the structure, damages would be limited to the cost to repair the collapse as of October 22, 1989, the date of the collapse. At the partial new trial, PRASA presented evidence that the soil conditions at the site were unstable and were experiencing settlement beyond what was expected. PRASA's experts testified that the soil had to be improved in order to repair the collapse, either through placing a new surcharge on the site or by installing piles to support the structure. PRASA's experts testified that only the option of installing piles was feasible, but that it would cost in excess of $6 million to do.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bankers Trust Co. v. Mallis
435 U.S. 381 (Supreme Court, 1978)
Kersey v. Dennison Manufacturing Co.
3 F.3d 482 (First Circuit, 1993)
Acevedo Villalobos v. Hon. Hernandez
22 F.3d 384 (First Circuit, 1994)
Credit Francais International v. Bio-Vita, Ltd.
78 F.3d 698 (First Circuit, 1996)
Fernandez v. Corporacion Insular De Seguros
79 F.3d 207 (First Circuit, 1996)
City of Cleveland v. Peter Kiewit Sons' Co.
624 F.2d 749 (Sixth Circuit, 1980)
Jesse Forrestal, Etc. v. Henry G. Magendantz
848 F.2d 303 (First Circuit, 1988)
Carlos Torres-Troche v. Municipality of Yauco
873 F.2d 499 (First Circuit, 1989)
Chat Phav v. Trueblood, Inc.
915 F.2d 764 (First Circuit, 1990)
Frankie L. Barber v. Whirlpool Corporation
34 F.3d 1268 (Fourth Circuit, 1994)
Michael Johnson v. National Sea Products, Ltd.
35 F.3d 626 (First Circuit, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
PRASA v. Constructory Lluch, Counsel Stack Legal Research, https://law.counselstack.com/opinion/prasa-v-constructory-lluch-ca1-1999.