Nucor Steel v. PUB. UTILITY COM'N OF TEX.

26 S.W.3d 742, 2000 WL 1228664
CourtCourt of Appeals of Texas
DecidedOctober 5, 2000
Docket03-99-00698-CV
StatusPublished
Cited by26 cases

This text of 26 S.W.3d 742 (Nucor Steel v. PUB. UTILITY COM'N OF TEX.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nucor Steel v. PUB. UTILITY COM'N OF TEX., 26 S.W.3d 742, 2000 WL 1228664 (Tex. Ct. App. 2000).

Opinion

MARILYN ABOUSSIE, Chief Justice.

This is an appeal from a fuel reconciliation proceeding under the Public Utility Regulatory Act (“PURA”). 1 See Tex. Util. Code Ann. § 36.203 (West 1998) (hereinafter “PURA § _”). The district court affirmed in part and reversed and remanded in part an order of the Public Utility Commission of Texas (“the Commission”). We will reverse in part and render judgment in accordance with the Commission’s order.

STATUTORY OVERVIEW

Under PURA, a regulated electric utility such as appellee TXU Electric Company (“TXU”) 2 may not automatically pass its *745 actual fuel costs through to its customers. See PURA § 36.201 (West Supp.2000). Instead, the Commission designs a rate for the utility that takes into account projected fuel costs in the form of a fixed “fuel factor”; the Commission periodically adjusts this factor and reconciles fuel costs the utility charged using the factor against fuel costs the utility actually incurred. See id. § 36.203 (West 1998).

Section 36.203, entitled “Fuel Cost Recovery; Adjustment of Fuel Factor,” provides, “The commission by rule shall provide for the reconciliation of a utility’s fuel costs on a timely basis.” Id. § 36.203(e). According to an undisputed conclusion of law, this case was governed by the pre-1993 version of rule 23.23(b)(2)(H). That rule placed on the utility the burden of proving that: (1) it generated efficiently; (2) it maintained effective cost controls; and (3) it negotiated the lowest reasonable fuel cost for its non-affiliated contracts. See 17 Tex. Reg. 7067 (1992), amended, 18 Tex. Reg. 836 (1993). For fuels acquired from affiliated entities, the utility also carried the burden of establishing that (1) the affiliate’s fuel-related expenses were reasonable and necessary and (2) the affiliate charged the utility no more than it charged others for items of the same class. See id. The rule disallowed recovery of profit or return on equity to the affiliate; authorized the Commission to investigate the affiliate’s operations; required the affiliate to maintain specific financial records, which would be available to the Commission; and disallowed reconciliation of an affiliate’s increased fuel cost when the events and conditions that caused the increased costs were within the utility’s control. See id.

PROCEDURAL BACKGROUND 3

In December 1995, TXU sought to reconcile its total fuel and purchased power costs for the period between July 1, 1992 and June 30, 1995. 4 Appellants Nucor Steel (“Nucor”), the Office of Public Utility Counsel (“OPUC”), 5 and the Cities of Arlington, et ai 6 were among the entities that intervened in the proceeding. Only two issues from the reconciliation proceeding are implicated in this appeal: (1) whether TXU should have been allowed to recover fuel expenses incurred under pre-1983 long-term gas contracts entered into by its affiliate Texas Utilities Fuel Company (TUFCO) and (2) whether TXU should have been allowed to recover the cost of fuel used to replace lost capacity resulting from a chimney collapse and nineteen-month outage of TXU’s Monticello Steam Electric Station unit three (“MOSES Three”).

An administrative law judge (“ALJ”) at the State Office of Administrative Hearings conducted a contested case hearing and issued a proposal for decision (“PFD”) that recommended allowing TXU to recover the costs of the replacement fuel for MOSES Three. The ALJ also recommended disallowing specific, imprudently incurred fuel costs; allowing TXU to recover for other gas purchased from TUF-CO; and concluding that res judicata barred attacks on TUFCO’s pre-1983 long-term gas contracts for alleged conflicts with federal law.

*746 With respect to the long-term gas contracts, the Commission agreed with the ALJ and concluded that res judicata barred consideration of whether the contracts conflicted with federal law. 7 The Commission adopted findings and conclusions disallowing the imprudently incurred costs and allowing recovery of the remaining amounts paid to TUFCO. But the Commission disagreed with the ALJ regarding the MOSES Three replacement fuel, finding instead that “[t]he $66,982,000 in replacement power costs associated with the MOSES Unit No. 3 chimney collapse is not reasonable and should be disallowed.”

TXU, the Cities, and Nucor each filed suit for judicial review of the Commission’s order. See PURA § 15.001 (West 1998); Tex. Gov’t Code Ann. § 2001.174 (West 2000). The district court denied all of the Cities’ and Nucor’s challenges and affirmed the portion of the order awarding the costs incurred under the long-term gas contracts. The district court overruled one of TXU’s points of error but sustained the rest and reversed the Commission’s order in part, remanding the cause to the Commission for entry of an order allowing TXU to recover the additional fuel costs resulting from the chimney collapse. The Commission, the OPUC, 8 the Cities, and Nucor then filed appeals with this Court.

DISCUSSION

Pre-1983 Gas Contracts

The Commission found that TXU purchased gas through TUFCO and that TUFCO’s pre-1983 long-term well-head production contracts without market-out provisions 9 were a factor causing TXU’s gas costs during the reconciliation period to exceed the average gas costs of other investor-owned utilities in Texas. In their first issues, Nucor and the Cities argue that the Commission erred in allowing TXU to recover costs incurred under these long-term contracts.

Res Judicata

In its order, the Commission concluded that “[a]ll issues regarding the prudent negotiation of the contracts executed during a prior reconciliation period should have been litigated in the fuel proceeding covering that reconciliation period.” Nu-cor and the Cities contend that the Commission erred in applying the doctrine of res judicata in this situation because fuel reconciliations are separate proceedings limited to finite periods of time and the result in one proceeding cannot be res judicata as to another. They further contend that this argument was not ripe before 1990 and could not have been raised in a previous reconciliation. We disagree.

The Cities’ and Nucor’s argument to the Commission is stated in Nucor’s brief:

During the period November 1978 through August 1981, federal law, the Power Plant and Industrial Fuel Use Act of 1978(FUA), [Act of November 9, 1978, Pub.L. No. 95-620, 92 Stat.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

AEP Texas Central Co. v. Public Utility Commission
286 S.W.3d 450 (Court of Appeals of Texas, 2009)
CenterPoint Energy Houston Electric, LLC v. Public Utility Commission
212 S.W.3d 389 (Court of Appeals of Texas, 2006)
Entergy Gulf States, Inc. v. Public Utility Commission
173 S.W.3d 199 (Court of Appeals of Texas, 2005)
Cities of Alvin v. Public Utility Commission
143 S.W.3d 872 (Court of Appeals of Texas, 2004)
American Electric Power Co. v. Public Utility Commission
123 S.W.3d 33 (Court of Appeals of Texas, 2004)
Reliant Energy, Inc. v. Public Utility Commission
101 S.W.3d 129 (Court of Appeals of Texas, 2003)
GTE Southwest, Inc. v. Public Utility Commission
102 S.W.3d 282 (Court of Appeals of Texas, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
26 S.W.3d 742, 2000 WL 1228664, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nucor-steel-v-pub-utility-comn-of-tex-texapp-2000.