Pedernales Electric Cooperative, Inc. v. Public Utility Commission

809 S.W.2d 332, 1991 Tex. App. LEXIS 1247, 1991 WL 72449
CourtCourt of Appeals of Texas
DecidedMay 8, 1991
Docket3-90-147-CV
StatusPublished
Cited by45 cases

This text of 809 S.W.2d 332 (Pedernales Electric Cooperative, Inc. v. Public Utility Commission) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pedernales Electric Cooperative, Inc. v. Public Utility Commission, 809 S.W.2d 332, 1991 Tex. App. LEXIS 1247, 1991 WL 72449 (Tex. Ct. App. 1991).

Opinion

ABOUSSIE, Justice.

Appellants 1 are wholesale customers of the Lower Colorado River Authority (LCRA) that challenge a rate design decision of the appellee Public Utility Commission (PUC or the Commission). In Docket No. 8400, the Commission refused to reinstate a voltage differential between 138 kilovolt (“kV”) customers and 69 kV customers. The voltage differential had been collapsed as a result of the Commission’s order in an earlier rate case. Application of Lower Colorado River Authority for Authority to Change Rates, Docket No. 8032, 14 P.U.C.Bull. 1566 (Sept. 22, 1988). Appellants sought judicial review of the Commission’s decision in the district court of Travis County, which affirmed the Commission on all points. From that final judgment, appellants appeal to this Court.

Appellants complain that the district court erred in affirming the order of the Commission because by its decision the Commission treated two groups of customers alike, even though the evidence and Commission findings determined that they were two distinct classes; thus, the Commission violated the anti-discrimination provision of the Public Utility Regulatory Act (“PURA”), Tex.Rev.Civ.Stat.Ann. art. 1446c, § 38 (Supp.1991). In addition, they argue that the PUC violated the Texas Administrative Procedure and Texas Register Act (“APTRA”) either because its findings of fact were not based on substantial evidence or because its decision was arbitrary and capricious. See Tex.Rev.Civ. Stat.Ann. art. 6252-13a, § 19(e)(5), (6) (Supp.1991). They also assert that the Commission violated APTRA by failing to include required underlying fact findings and by basing its decision on a vote trade between two Commissioners. See APTRA §§ 16(b); 19(e)(3) (Supp.1991). One appellant urges that the Commission erred in refusing to allow it to present rebuttal testimony. We will affirm the judgment of the trial court.

The Controversy

LCRA sells electricity at wholesale to forty-four customers of varying size. These customers take delivery at voltage levels of 138 kV, 69 kV, and 12.5 kV. The interests of 12.5 kV customers are not in issue. The controversy centers on whether the LCRA should be allowed to continue treating wholesale customers which receive electricity at 138 kV and 69 kV levels as members of one customer class.

Because it is easier and more economical to transport electricity at high voltage levels, the low voltage electricity generated by LCRA is transformed to higher voltage levels through a “step-up transformer.” LCRA uses transmission and subtransmission levels of 345 kV, 138 kV, and 69 kV. Electricity that is transmitted on the 345 kV lines must be “stepped down” to the lower voltage lines at which its customers take delivery. All of LCRA’s 345 kV lines are connected directly to 138 kV transformation facilities. Some LCRA customers take delivery at this level. The electricity delivered at the 69 kV level must go through additional LCRA-owned transformation facilities to step the electricity down to the level at which the customer can receive it.

In 1985, the Commission approved a rate design based on a voltage differential that established one charge for delivery at the 69 kV level and a lower charge for delivery at the 138 kV level. Application of Lower *335 Colorado River Authority for Authority to Change Rates, Docket No. 6027, 11 P.U. C.Bull. 125 (June 10, 1985). In LCRA’s next rate case, the parties entered into a stipulation that provided for the continuation of the voltage rate differential. Application of Lower Colorado River Authority for a Rate Increase, Docket No. 7512, 14 P.U.C.Bull. 156 (Oct. 22, 1987).

In a still later rate case, LCRA requested that the differential be continued unchanged. Application of Lower Colorado River Authority to Change Rates, Docket No. 8032, 14 P.U.C.Bull. 1566 (Sept. 22, 1988). An intervenor, Bluebonnet Electric Cooperative, Inc. (“Bluebonnet”), requested that the voltage differential between 138 kV and 69 kV be collapsed so there would be one delivery rate for both 138 kY customers and 69 kV customers. LCRA did not present testimony refuting Bluebonnet’s position. The Commission ordered the voltage differential collapsed for rate design purposes.

Forty-two days after the Commission ordered the voltage differential collapsed in Docket No. 8032, LCRA filed Docket 8400, from which this appeal arises. Application of Lower Colorado River Authority for Authority to Change Rates, Docket No. 8400,15 P.U.C.Bull. 969 (July 11,1989). In Docket No. 8400, much of the evidence regarding rate design focused on the terms of a stipulation sponsored by the majority of the parties. The stipulation would have implemented a transmission-facilities credit in place of a voltage differential as a means of compensating the 138 kV customers on LCRA’s system. The hearing examiner recommended rejection of the stipulation due to lack of time for its full evaluation. The Commission adopted that recommendation but rejected the hearing examiner’s recommendation to reinstate the voltage differential. Instead, the Commission decided that LCRA should retain the voltage differential collapse ordered in Docket No. 8032 to maintain consistency in LCRA’s rate design.

The Commission’s order adopted the hearing examiner’s report, with some modifications, and made the report part of its order. The controversy in the present cause centers around finding of fact no. 59, concerning the voltage differential. As recommended in the examiner’s report, finding of fact no. 59 would have reinstated the voltage differential and would have substantiated the reasons for the reinstatement in considerable detail. Her report suggested the following:

59. The voltage level differential between 69 kV and 138 kV transmission lines should be reinstated, because as discussed in Section IV.C.3 of this Examiner’s Report, the evidence establishes that:
a. The 138 kY and 69 kV lines do not carry out the same function;
b. Over 95 percent of the power generated by LCRA is fed into the transmission system at the 138 kV level or above;
c. 69 kV lines primarily serve the function of carrying from the high voltage lines to customers at the distribution level;
d. The 69 kV lines serve as a link to the end-use customers, a function that could be classified as subtransmission;
e. LCRA transmission system reliability is not dependent on the 69 kV lines;
f. Because the fixed costs associated with the construction and maintenance of the 69 kV subtransmission system are not costs necessarily incurred by LCRA’s 138 kV customers, those costs should not be borne by 138 kV customers;
g. During normal operations, power generated at the 345 kV and 138 kV transmission levels flows through the high voltage transmission facilities to the 69 kV transmission facilities to supply power at the distribution level;
h.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nucor Steel-Texas v. Public Utility Commission
363 S.W.3d 871 (Court of Appeals of Texas, 2012)
City of Port Neches v. Railroad Commission of Texas
212 S.W.3d 565 (Court of Appeals of Texas, 2006)
Nucor Steel v. PUBLIC UTILITY COM'N OF TEX.
168 S.W.3d 260 (Court of Appeals of Texas, 2005)
Nucor Steel v. PUB. UTILITY COM'N OF TEX.
26 S.W.3d 742 (Court of Appeals of Texas, 2000)
State Ex Rel. Miller v. DeCoster
608 N.W.2d 785 (Supreme Court of Iowa, 2000)
Gilpin County Board of Equalization v. Russell
941 P.2d 257 (Supreme Court of Colorado, 1997)
Holiday Inns, Inc. v. State
931 S.W.2d 614 (Court of Appeals of Texas, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
809 S.W.2d 332, 1991 Tex. App. LEXIS 1247, 1991 WL 72449, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pedernales-electric-cooperative-inc-v-public-utility-commission-texapp-1991.