Coalition of Cities for Affordable Utility Rates v. Public Utility Commission of Texas

798 S.W.2d 560, 1990 WL 130240
CourtTexas Supreme Court
DecidedNovember 28, 1990
DocketC-9287
StatusPublished
Cited by126 cases

This text of 798 S.W.2d 560 (Coalition of Cities for Affordable Utility Rates v. Public Utility Commission of Texas) is published on Counsel Stack Legal Research, covering Texas Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Coalition of Cities for Affordable Utility Rates v. Public Utility Commission of Texas, 798 S.W.2d 560, 1990 WL 130240 (Tex. 1990).

Opinions

OPINION

DOGGETT, Justice.

In this appeal certain consumers of a public utility urge that it be denied a second opportunity to prove the same facts as justification for an electric rate increase. We agree that the public utility regulatory scheme set forth by the legislature provides that once is enough. The doctrines of res judicata and collateral estoppel bar such relitigation before the Public Utility Commission (“PUC”).

Gulf States Utilities Company (“GSU”) sought a rate increase which required the PUC to determine whether the $4.5 billion that GSU spent for completion of the River Bend Nuclear Power Plant was a prudently incurred cost.1 This expense was challenged by the petitioners2 who intervened in the rate case before the PUC. As GSU has noted, “[ejvery factual, legal and policy [562]*562issue was thoroughly explored and canvassed”, during the resulting hearings that continued for 132 days and cost ratepayers approximately $12 million. Thereafter the PUC issued a final order containing the following findings of fact and conclusions of law that are central to the present controversy:

Finding 164: The preponderance of the evidence in this case establishes that $2,273 billion of River Bend capital costs were prudently and reasonably incurred. The evidence is inadequate to support a finding of either prudence or imprudence with regard to construction costs in excess of $2,273 billion, with the exception of the costs related to the 50-month schedule and TDI, addressed in Findings of Fact Nos. 133 and 145.
Finding 164A: GSU’s share of all River Bend capital costs in excess of $2,273 billion should be excluded from plant in service at this time for lack of sufficient evidence as to the prudence and reasonableness of those costs. The amount which should be included in plant in service, given GSU’s 70 percent share of the plant, is $1.5911 billion.
Conclusion of Law 10: Pursuant to PURA Sections 16(a), 38, 39(a), and 41,3 the Commission may reexamine on rehearing or in a subsequent proceeding the prudence and reasonableness of those River Bend construction costs regarding which the evidence is inadequate to support a finding of either prudence or imprudence.
Conclusion of Law 15: Under PURA Section 40 a utility must prove its conduct to have been prudent when decisions or expenditures are reasonably challenged.
Conclusion of Law 18: $1,453,520,982 of GSU’s share of end-of-test-year River Bend capital costs should not be included from GSU’s rate base as invested capital used and useful in rendering service to the public pursuant to PURA Sections 38, 39, and 41.
Conclusion of Law 18A: GSU has not met its burden of proving that the capital costs of River Bend above a reasonable Definitive Cost Estimate of $2.273 billion were reasonably and prudently incurred.

In summary, the PUC found that GSU had failed to prove that any expenses in excess of $2.273 billion were prudently incurred. Two of the three commissioners voted to allow GSU further opportunity to prove the prudence of an additional $1.453 billion, which apparently represented GSU’s share of cost overruns on the project. In taking this action, the PUC rejected its hearing examiner’s proposed conclusion of law that res judicata would prohibit reexamination of the prudence issue.

GSU appealed the final order and simultaneously initiated a new proceeding before the PUC on the same prudence question.4 The petitioners also appealed and, based on res judicata, obtained from the trial court a permanent injunction preventing further consideration of this issue by the PUC. The court of appeals, however, dissolved the permanent injunction and ruled that the doctrine of res judicata was inapplicable because the PUC had specifically reserved the right to rehear the prudence issue in conclusion of law 10. 777 S.W.2d 814, 816. The court cited no authority to support its res judicata holding, but merely compared the PUC action to a severance authorized by Texas Rule of Civil Procedure 41. Id. at 817. Because we disagree with this conclusion, we reverse the court of appeals’ judgment.

In Bonniwell v. Beech Aircraft Corp., 663 S.W.2d 816, 818 (Tex.1984), we considered the doctrines of res judicata and collateral estoppel. Res judicata, a matter judicially determined, bars the retrial of claims pertaining to the same cause [563]*563of action which has been finally adjudicated. Collateral estoppel or issue preclusion is more narrow, precluding only the relitigation of identical issues of fact that have been actually litigated. To invoke either doctrine, the prior judgment must involve, the same issues, subject matter, and parties or those in privity.

Texas has made limited use of res judi-cata in an administrative context.5 See Sexton v. Mount Olivet Cemetery Ass’n, 720 S.W.2d 129, 138-142 (Tex.App.—Austin 1986, writ ref’d n.r.e.). Voicing an awareness of the usefulness of res judicata in administrative proceedings, this court in Westheimer Indep. School Dist. v. Brochette, 567 S.W.2d 780, 787 (Tex.1978), expressed a strong preference that “[cjontin-ued litigation of issues or piecemeal litigation should be discouraged” in state regulatory agencies.

Ironically, GSU was the first party to urge the applicability of res judicata and collateral estoppel in this proceeding. GSU maintained initially that the doctrines precluded the PUC from considering the prudence of the River Bend construction, which it had previously authorized by granting a certificate of convenience and necessity. Additionally, counsel for the PUC acknowledged during oral arguments before this court that res judicata would prohibit relitigation regarding the $2,273 billion found prudent by the PUC. Petitioners correctly characterize the PUC’s position as seeking to apply res judicata to the portion of costs that GSU proved and rejecting its application to costs not proved.

Excepting the oral argument of counsel for GSU, everyone involved in these proceedings agrees with the court of appeals that res judicata could apply to PUC rate-making “[ujnder proper circumstances ” 777 S.W.2d at 815. The more narrow question we confront is whether the doctrine should be rejected because of any aspect of this particular proceeding, the PUC’s final order, or the statute by which the order was authorized. At issue here is not increased operating expenses or the appropriate rate of return — factors that can change over time. Rather, every fact involved is historical; the amount and wisdom of these construction expenditures will remain constant no matter how many times the PUC permits relitigation addressing them.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

in Re: Rigney Construction & Development, LLC
Court of Appeals of Texas, 2017
New Talk, Inc. v. Southwestern Bell Telephone Co.
520 S.W.3d 637 (Court of Appeals of Texas, 2017)
Raghunath Dass, P.E. v. Texas Board of Professional Engineers
517 S.W.3d 252 (Court of Appeals of Texas, 2017)
Andrew Whallon, Dahlia Garcia and Richard Grayshaw v. City of Houston
462 S.W.3d 146 (Court of Appeals of Texas, 2015)
in Re Michael N. Blair
408 S.W.3d 843 (Texas Supreme Court, 2013)
Commission for Lawyer Discipline v. Jeffrey M. Stern
355 S.W.3d 129 (Court of Appeals of Texas, 2011)
Igal v. Brightstar Information Technology Group, Inc.
250 S.W.3d 78 (Texas Supreme Court, 2008)
In Re General Agents Insurance Co. of America, Inc.
244 S.W.3d 622 (Court of Appeals of Texas, 2008)
Graves v. Alders
132 S.W.3d 12 (Court of Appeals of Texas, 2004)
Entergy Gulf States, Inc. v. Public Utility Commission of Texas
112 S.W.3d 208 (Court of Appeals of Texas, 2003)
Ramirez v. Texas State Board of Medical Examiners
99 S.W.3d 860 (Court of Appeals of Texas, 2003)
Turnage v. JPI Multifamily, Inc.
64 S.W.3d 614 (Court of Appeals of Texas, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
798 S.W.2d 560, 1990 WL 130240, Counsel Stack Legal Research, https://law.counselstack.com/opinion/coalition-of-cities-for-affordable-utility-rates-v-public-utility-tex-1990.