CenterPoint Energy Houston Electric, LLC v. Public Utility Commission

212 S.W.3d 389, 2006 Tex. App. LEXIS 4740, 2006 WL 1501263
CourtCourt of Appeals of Texas
DecidedJune 2, 2006
Docket03-05-00565-CV
StatusPublished
Cited by11 cases

This text of 212 S.W.3d 389 (CenterPoint Energy Houston Electric, LLC v. Public Utility Commission) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
CenterPoint Energy Houston Electric, LLC v. Public Utility Commission, 212 S.W.3d 389, 2006 Tex. App. LEXIS 4740, 2006 WL 1501263 (Tex. Ct. App. 2006).

Opinion

OPINION

JAN P. PATTERSON, Justice.

CenterPoint Energy Houston Electric, LLC and Texas Genco, LP (collectively “CenterPoint”), successors to a former integrated utility serving the Houston area, 1 appeal a district-court judgment that affirmed an order of the Public Utility Commission in a fuel reconciliation proceeding under the Public Utility Regulatory Act (PURA). 2 See Tex. UtiLCode Ann. § 36.203 (West 1998). In its order, the Commission disallowed the recovery of certain fuel expenses because they were not reasonable and necessary. We affirm the judgment.

The Controversy

A fuel reconciliation proceeding is the means by which a regulated utility’s reasonable and necessary fuel and purchased power expenses are finalized. Because a regulated utility, such as CenterPoint, is not permitted under PURA to automatically pass through to ratepayers its fuel and purchased power costs, it must reconcile its fuel revenues and expenses to avoid over- or under-recovery of the costs set by the Commission in the form of a fixed fuel factor.

This appeal concerns CenterPoint’s request for recovery of purchased power costs under a Joint Operating Agreement (“JOA”) that CenterPoint entered into with City Public Service of San Antonio (“CPS”), San Antonio’s municipally owned utility, arising out of litigation and then settlement between the parties over the management of the South Texas Nuclear Project (“STP”). CenterPoint urges that the Joint Operating Agreement enabled CenterPoint and CPS to reduce their costs and that CenterPoint carried its burden in the proceedings to demonstrate that its fuel expenses during the reconciliation period were reasonable and necessary. The Commission and intervenor City of Houston contend that (i) the purpose of the Joint Operating Agreement was to settle litigation over CenterPoint’s imprudent mismanagement of the South Texas Nuclear Project, (ii) the benefits of the Joint Operating Agreement are overstated, and (iii) these costs are not recoverable through CenterPoint’s fuel factor and should be disallowed.

The Nature of a Fuel Reconciliation Proceeding

Instead of allowing a regulated utility to pass its actual fuel costs through to its customers, the Commission designs a rate for the utility that takes into account projected fuel costs in the form of a fixed “fuel factor.” Tex. UtiLCode Ann. § 36.203. The Commission periodically adjusts this factor and reconciles fuel costs the utility *394 charged using the factor against fuel costs the utility actually incurred. See id. Section 36.203 provides for the timely adjustment of a utility’s fuel factor, with or without a hearing, and the reconciliation of a utility’s fuel costs. Id. In a fuel reconciliation proceeding, the utility carries the burden of proving that its eligible fuel expenses during the reconciliation period were “reasonable and necessary expenses” to provide reliable service to its customers. 16 Tex. Admin. Code § 25.236(d)(1)(A) (2004). 3 The scope of the proceeding includes “any issue” related to determining the reasonableness of the electric utility’s fuel expenses during the reconciliation period. Id. § 25.236(d)(2).

This is CenterPoint’s final fuel reconciliation, and the final fuel balance will be included in its true-up proceeding. See Tex. Util-Code Ann. § 39.202(c) (West Supp.2005). The final balance from the true-up proceeding will be applied to the rates charged by CenterPoint as the transmission and distribution provider affiliated with the former integrated utility. Id. § 39.262 (West Supp.2005).

FACTUAL AND PROCEDURAL BACKGROUND

On July 1, 2002, CenterPoint filed a petition to reconcile its revenues collected under the fuel factors with the actual fuel and purchased power costs incurred for the period August 1, 1997, through January 20, 2002. The Commission referred the application to the State Office of Administrative Hearings for a contested case hearing before an administrative law judge. Several parties, including the City of Houston, intervened in the proceeding, challenging CenterPoint’s claimed expenses. The parties filed a stipulation resolving certain of the claimed expenses, leaving in dispute a total of $202 million over four issues, which were reserved for a hearing.

These remaining expenses related to the recovery of CenterPoint’s purchased power costs under the JOA that CenterPoint had entered into with CPS in 1996.

The Joint Operating Agreement

The terms and the allocation of savings arising from the joint operations of Cen-terPoint and CPS are at the core of this dispute. The JOA arose out of CPS’s claim against HL & P over its operation of the STP in which CPS had an interest. The agreement between CPS and HL & P was executed on July 1, 1996, and resulted in CenterPoint as successor maintaining joint operations with CPS. The JOA provided for the joint operation of the two *395 utilities’ electrical generating systems in order to serve their combined load as a single service area. Under this joint dispatch arrangement, excess capacity from one utility could be used to serve the other utility’s customers.

At the end of each month, CPS and CenterPoint would calculate the net flow of energy from one utility to the other. Compensation for energy used was to have two separate components: the Production Cost Adjustment (“PCA”) and a benefit-sharing payment. The PCA was created to reimburse the party providing the energy for its costs of producing the electricity. The benefit-sharing payment allocated a pre-determined share of the benefits of joint operation between the parties.

Under the terms of the JOA, CPS and CenterPoint were required to calculate their individual cost of operating in the joint system and compare the joint system costs to the costs that would have occurred had the two parties operated separately, thus determining the savings arising from their joint operations. Joint system costs were calculated on the basis of a study designated “Study J”; stand-alone costs were calculated on the basis of “Study S.” 4 The JOA defined the total joint operation benefit as the difference between the parties’ actual costs under the joint operations and their stand-alone costs. Under this negotiated sharing arrangement, CPS would receive 90% of the calculated total benefit, while CenterPoint received 10%. The 90/10 allocation would continue until CPS received $150 million in benefit payments. CenterPoint would avoid the payment of $150 million in settlement payments if the JOA produced savings in that amount for CPS. 5 In January 2000, the parties modified the benefit split for short-term transactions from 90/10 to 50/50.

At the hearing, CenterPoint contended that the JOA provided it and CPS with fuel savings through the combined economic dispatch of all the generating units owned and operated by the two parties. Carla J.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
212 S.W.3d 389, 2006 Tex. App. LEXIS 4740, 2006 WL 1501263, Counsel Stack Legal Research, https://law.counselstack.com/opinion/centerpoint-energy-houston-electric-llc-v-public-utility-commission-texapp-2006.