Cities for Fair Utility Rates v. Public Utility Commission

924 S.W.2d 933, 39 Tex. Sup. Ct. J. 840, 1996 Tex. LEXIS 88, 1996 WL 354774
CourtTexas Supreme Court
DecidedJune 28, 1996
Docket94-1237
StatusPublished
Cited by39 cases

This text of 924 S.W.2d 933 (Cities for Fair Utility Rates v. Public Utility Commission) is published on Counsel Stack Legal Research, covering Texas Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cities for Fair Utility Rates v. Public Utility Commission, 924 S.W.2d 933, 39 Tex. Sup. Ct. J. 840, 1996 Tex. LEXIS 88, 1996 WL 354774 (Tex. 1996).

Opinion

HECHT, Justice,

delivered the opinion for a unanimous Court.

The principal question in this appeal from an order of the Public Utility Commission is whether an electric utility’s costs of construction work in progress, CWIP, including an allowance for funds used during construction, AFUDC, can be included in its rate base as plant held for future use, PHFU, when construction has halted but the project remains viable. We agree with the PUC, the district court, and the court of appeals, that the answer is yes.

*935 I

We begin by looking at those aspects of utility ratemaking that form the legal setting for the present controversy, including accounting conventions for CWIP, AFUDC and PHFU. Utility ratemaking in Texas is governed by the Public Utility Regulatory Act of 1995, or PURA, Tex.Rev.Civ.Stat.Ann. art. 1446c-0 (Vernon Supp.1996), a nonsubstan-tive recodification of the Public Utility Regulatory Act, Act of June 2, 1975, 64th Leg., R.S., eh. 721, 1975 Tex.Gen.Laws 2327 (formerly at Tex.Rev.Civ.Stat.Ann. art. 1446c (Vernon Supp.1995)), to which we refer as “the 1975 Act”. PURA, 74th Leg., R.S., ch. 9, § 3, 1995 Tex.Gen.Laws 31, 87. As there is no difference between PURA and the 1975 Act that affects this case, we refer to PURA whenever possible. The accounting conventions at issue are part of the uniform system of accounts prescribed by the Federal Energy Regulatory Commission, 18 C.F.R. pt. 101 (1995), which the PUC requires electric utilities to use, 16 Tex.Admin.Code § 23.12(a)(2)(B) (West Supp.1995), under its statutory authority, PURA § 1.201(c).

Fundamentally, a public utility’s rates must be “just and reasonable”. PURA § 2.202. As a general rule,

[i]n fixing the rates of a public utility, the regulatory authority shall fix its overall revenues at a level which will permit such utility a reasonable opportunity to earn a reasonable return on its invested capital used and useful in rendering service to the public over and above its reasonable and necessary operating expenses.

PURA § 2.203(a). Restated, the rule is that a utility’s rates must be set so as to produce revenues equal to the sum of two amounts. One is the utility’s “reasonable and necessary operating expenses”, including taxes and depreciation. The other is “a reasonable return on its invested capital used and useful in rendering service to the public”. That capital is the utility’s rate base. Thus, a utility is entitled to rates sufficient to repay its expenses, without a return'or profit on those expenses, and to provide a return on the invested capital included in its rate base, without repaying that investment.

A utility’s cost of constructing a facility for use in providing service is ordinarily not an operating expense; obviously, until the facility is completed, there is nothing to operate. Rather, the cost of constructing a new facility, like the purchase price of an existing facility, is an investment of capital in an asset to be used in the future. As such, it must be included in a utility’s rate base, but not until the facility has become “used and useful in rendering service to the public”. “Used and useful” refers to “such property as has been acquired ... in good faith and held for use in the reasonably near future in order to enable [a utility] to supply and furnish adequate and uninterrupted ... service.” Lone Star Gas Co. v. State, 137 Tex. 279, 153 S.W.2d 681, 698 (1941).

Historically, a facility under construction has not been considered used or useful in providing service until it actually becomes operational. Chaeles F. Phillips, JR., The Regulation of Public Utilities 354-355 (3d ed. 1993); Richakd J. Pierce, Jr. & Ernest Gellhorn, Regulated Industries 112 (3d ed. 1994). In this view, construction costs are not included in rate base until construction is complete. Meanwhile, they are accrued in an account for construction work in progress, or CWIP, for short. See 18 C.F.R. pt. 101, at 284 (Account 107).

The cost of the capital used to pay construction costs is also part of the investment in the facility. 1 A.J.G. Priest, PRINCIPLES of Public Utility Regulation, 178-180 (1969). Recognizing this, uniform accounting rules adopted by the Federal Power Commission in 1937 and followed in most states allowed a utility to include in its cost accounting an amount for “interest during construction”. Phillips, supra, at 354. In 1971 the FPC substituted the phrase “allowance for funds used during construction”, or AFUDC, for interest, but the basic idea remained the same. Id. AFUDC is now part of FERC’s uniform accounting system. 18 C.F.R. pt. 101, at 269. While construction is continuing, AFUDC accrues on CWIP. AFUDC does not represent a transfer of funds; it is simply an entry in a utility’s books to indicate the cost of capital used during construction. When construction is complete and the facili *936 ty operational, both CWIP and AFUDC are transferred to the utility’s rate base, and the utility begins to earn a return on its investment' in both. Phillips, supra, at 354; PiERCE & Gellhorn, supra, at 113.

Although this method of accounting — accumulating CWIP and AFUDC and then transferring them to the rate base — should allow a utility a fair return on its investment in a new project, actual payment of that return does not begin until after construction is completed. Thus, in essence, a utility advances the cost of construction until the work is done, and only then begins to profit from its investment. “[Cjonsumer groups universally contend that [this accounting] procedure results in a correct match of costs and benefits between present and future customers” of a utility. Phillips, supra, at 354. In other words, present customers should not pay rates for benefits only future customers will realize.

However, if costs of capital and construction are high, and construction periods are lengthy, the funds “advanced” — actually expended by a utility — can be so large over so long a time that they cause the utility serious cash flow problems. Expenditures may become enormous before any return at all is realized. That is precisely what began to happen in the late 1960s. See generally Lawrence S. Pomerantz & James E. Suel-flow, Allowance for Funds Used During Construction 1-7 (1975) (detailing the financial positions of major gas and electric utilities in light of large construction projects during the 1960s and early 1970s). To accommodate a utility’s real financial difficulties, and still preserve an accounting procedure historically viewed as fair to present and future utility customers, regulators began to allow CWIP to be included in the rate base before completion of construction, but only when it was necessary for the financial integrity of the utility. Phillips, supra, at 354-355; Pierce & Gellhorn, supra, at 115— 116. To the extent the utility is financially able to bear accrual of construction costs, deferring inclusion in rate base until construction is completed is fairest to present and future ratepayers. When the burden is too great, however, present customers must share in the prudent provision of service for the future.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pioneer Natural Resources USA, Inc. v. Public Utility Commission
303 S.W.3d 363 (Court of Appeals of Texas, 2009)
CenterPoint Energy Houston Electric, LLC v. Public Utility Commission
212 S.W.3d 389 (Court of Appeals of Texas, 2006)
Reliant Energy, Inc. v. Public Utility Commission
153 S.W.3d 174 (Court of Appeals of Texas, 2004)
Entergy Gulf States, Inc. v. Public Utility Commission of Texas
112 S.W.3d 208 (Court of Appeals of Texas, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
924 S.W.2d 933, 39 Tex. Sup. Ct. J. 840, 1996 Tex. LEXIS 88, 1996 WL 354774, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cities-for-fair-utility-rates-v-public-utility-commission-tex-1996.