Public Utility Commission of Texas and Southwestern Electric Power Company v. Texas Industrial Energy Consumers

Texas Supreme Court·Decided March 26, 2021·No. 18-1061·Published

Opinion

IN THE SUPREME COURT OF TEXAS ════════════

NO. 18-1061

════════════

PUBLIC UTILITY COMMISSION OF TEXAS AND SOUTHWESTERN ELECTRIC POWER COMPANY, PETITIONERS,

v.

TEXAS INDUSTRIAL ENERGY CONSUMERS, ET AL., RESPONDENTS ════════════════════════════════════════════════════ ON PETITION FOR REVIEW FROM THE COURT OF APPEALS FOR THE THIRD DISTRICT OF TEXAS ════════════════════════════════════════════════════

Argued December 3, 2020

JUSTICE BLAND delivered the opinion of the Court.

JUSTICE HUDDLE did not participate in the decision.

Forecasting the future supply of electric power in Texas and consumer demand for it is challenging given the variables on both sides of the equation. Once a forecast is made, and the approved construction of a new power plant well underway, a decision whether to abandon construction based on new forecasting is even more difficult. This case concerns the standard for evaluating a utility’s decision to complete an approved project and the degree courts must defer to the Public Utility Commission, which is charged with making that evaluation. 1

1 The Public Utility Commission (Commission) is a state regulatory agency established and governed by the Public Utility Regulatory Act. TEX. UTIL. CODE §§ 11.00–66.016. The Act “establish[es] a comprehensive and adequate regulatory system for public utilities to assure rates, operations, and services that are just and reasonable to the consumers and to the utilities.” Id. § 11.002(a).

The Commission determined that the Southwestern Electric Power Company’s decision to complete construction of a power plant was “one of a select range of options” that a reasonable utility manager could have chosen. Because SWEPCO had not maintained records reflecting a continuous reassessment of its decision to build the plant, it bore the burden before the Commission of establishing that its decision was a prudent one through after-the-fact justifications. Having concluded that SWEPCO met this burden, the Commission allowed SWEPCO to include the plant’s construction costs in its utility rates.

The Respondents here 2 challenged the Commission’s ruling in state district court. They argued that the Commission’s decision to allow part of the construction costs was arbitrary and lacked evidence to support it because SWEPCO did not provide an outside expert’s assessment of the decision to continue construction. Rejecting that contention, the trial court upheld the Commission’s decision in all respects.

The court of appeals reversed, concluding that the Commission had set a standard that required evidence of “independent, retrospective analyses” of the project. 3 Because SWEPCO did not produce independent expert testimony, the court held, the Commission had no basis for its decision. 4 The Commission and SWEPCO, the Petitioners here, contend that the Commission properly applied its standard for assessing SWEPCO’s decision to complete construction of the plant. They further contend that substantial evidence supports the Commission’s conclusions. The

2 The Respondents in this Court are Texas Industrial Energy Consumers, the Office of Public Utility Counsel, and Cities Advocating Reasonable Deregulation. The Office of Public Utility Counsel is a state agency that “represents the interests of residential and small commercial consumers.” Id. § 13.001. It may intervene as a matter of right in a judicial proceeding that involves an administrative agency action in which it is authorized to appear. Id. § 13.003(a)(4). Cities Advocating Reasonable Deregulation is a municipal coalition whose members have jurisdiction over SWEPCO’s rates and services within their respective city limits. See id. § 33.001(a).

3 608 S.W.3d 817, 827–29 (Tex. App.—Austin 2018).

4 Id. at 827–28.

parties also present an issue that the court of appeals did not reach: whether the Commission erred in permitting SWEPCO to include financing costs 5 that exceeded the project’s initial cap on capital costs in its rate base. 6 We hold that the Commission properly applied its standard in evaluating SWEPCO’s decision to complete construction and substantial evidence supports the Commission’s decision. Though outside expert analysis is evidence that the Commission may consider, it does not replace the standard of review the Commission used in this case: whether a reasonably prudent utility manager could have decided to complete construction under the circumstances. The Commission applied the standard it set forth in concluding that completing construction was a prudent decision. Relying mainly on the absence of “independent, retrospective analyses,” the court of appeals erred in rejecting the evidence that supports the Commission’s findings. Accordingly, we reverse the judgment of the court of appeals. We remand the case to that court for it to consider in the first instance whether the Commission arbitrarily permitted SWEPCO to further adjust the rate base to include capital financing costs.

5 The financing costs at issue are known as the “allowance for funds used during construction” or AFUDC.

AFUDC refers to the “carrying costs” used to finance a long-term construction project. See Cities for Fair Util. Rates v. Pub. Util. Comm’n of Tex., 924 S.W.2d 933, 935 (Tex. 1996) (explaining that AFUDC “is simply an entry in a utility’s books to indicate the cost of capital used during construction”).

6 608 S.W.3d at 829 n.14 (“[W]e need not address any challenges to the Commission’s determination that the cap on costs . . . did not include AFUDC.”). “The rate base, sometimes referred to as invested capital, includes as a major component the original cost of plant, property, and equipment, less accumulated depreciation, used and useful in rendering service to the public.” 16 TEX. ADMIN. CODE § 25.231(c)(2). We have explained:

[A] utility’s rates must be set so as to produce revenues equal to the sum of two amounts. One is the utility’s “reasonable and necessary operating expenses”, including taxes and depreciation. The other is “a reasonable return on its invested capital used and useful in rendering service to the public”.

That capital is the utility’s rate base. Thus, a utility is entitled to rates sufficient to repay its expenses, without a return or profit on those expenses, and to provide a return on the invested capital included in its rate base, without repaying that investment.

Cities for Fair Util. Rates, 924 S.W.2d at 935.

I

SWEPCO is a fully integrated electric utility that provides service to retail and wholesale customers in Texas, Arkansas, and Louisiana. Within its Texas service area along the northeastern Texas border and the eastern side of the Texas Panhandle, SWEPCO must provide electric power to anyone who requests it. It must also maintain sufficient capacity to meet its ratepayers’ power needs.

The Commission regulates SWEPCO’s business, including construction of new power plants, and it sets the rates that SWEPCO may charge its Texas customers. 7 The Commission must ensure that SWEPCO’s rates are “just and reasonable.” 8 Those rates must also allow SWEPCO “a reasonable opportunity to earn a reasonable return” on its invested capital. 9 In 2005, SWEPCO identified a need for more “long-term baseload capacity and energy resources” to serve its Texas customers. SWEPCO asked the Commission to approve the construction of three new power plants. The Commission authorized construction of two gas-fired plants, issuing certificates of convenience and necessity for their construction. The Commission later approved the third plant, the John W. Turk, Jr. Plant, 10 a coal-fired power plant located in

Free access — add to your briefcase to read the full text and ask questions with AI

Public Utility Commission of Texas and Southwestern Electric Power Company v. Texas Industrial Energy Consumers, (Tex. 2021).

Public Utility Commission of Texas and Southwestern Electric Power Company v. Texas Industrial Energy Consumers (Public Utility Commission of Texas and Southwestern Electric Power Company v. Texas Industrial Energy Consumers) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Duquesne Light Co. v. Barasch
488 U.S. 299 (Supreme Court, 1989)
Texas-New Mexico Power Co. v. Texas Industrial Energy Consumers
806 S.W.2d 230 (Texas Supreme Court, 1991)
State v. Public Utility Com'n of Texas
883 S.W.2d 190 (Texas Supreme Court, 1994)
City of El Paso v. Public Utility Commission
883 S.W.2d 179 (Texas Supreme Court, 1994)
Railroad Commission v. Torch Operating Co.
912 S.W.2d 790 (Texas Supreme Court, 1995)
Public Utility Commission v. AT & T Communications of Southwest
777 S.W.2d 363 (Texas Supreme Court, 1989)
AEP Texas North Co. v. Public Utility Commission
297 S.W.3d 435 (Court of Appeals of Texas, 2009)
Cities for Fair Utility Rates v. Public Utility Commission
924 S.W.2d 933 (Texas Supreme Court, 1996)
Gulf States Utilities Co. v. Public Utility Commission
841 S.W.2d 459 (Court of Appeals of Texas, 1992)