GTE Southwest, Incorporated D/B/A Verizon Southwest/MCI Communications Corporation and MCI WorldCom Communications, Inc. v. Public Utility Commission of Texas MCI Communications Corporation And MCI WorldCom Communications, Inc./GTE Southwest Incorporated D/B/A Verizon Southwest, Inc.

Court of Appeals of Texas·Decided March 20, 2003·No. 03-02-00405-CV·Published

Opinion

TEXAS COURT OF APPEALS, THIRD DISTRICT, AT AUSTIN



NO. 03-02-00405-CV

GTE Southwest, Incorporated d/b/a Verizon Southwest/MCI Communications Corporation and MCI WorldCom Communications, Inc., Appellants



v.



Public Utility Commission of Texas; MCI Communications Corporation; and MCI WorldCom Communications, Inc./GTE Southwest, Incorporated d/b/a

Verizon Southwest, Inc., Appellees



FROM THE DISTRICT COURT OF TRAVIS COUNTY, 200TH JUDICIAL DISTRICT

NO. GN1-00159, HONORABLE SUZANNE COVINGTON, JUDGE PRESIDING

O P I N I O N


GTE Southwest Incorporated d/b/a Verizon Southwest ("Verizon") sought judicial review of a final order issued by the Public Utility Commission of Texas (the "Commission") that interpreted and enforced an interconnection agreement. MCI Communications Corporation and MCI WorldCom Communications, Inc. ("WorldCom") intervened in the suit to defend the order and to request the district court to award interest accruing from the date of the order. The district court affirmed the order, but awarded interest only from the date of its judgment. In two issues, Verizon asks this Court to reverse the district court's judgment because: (1) the Commission lacked jurisdiction to enter the order; and (2) even if the Commission had jurisdiction, it erred as a matter of law in interpreting the agreement. WorldCom brings a cross-appeal complaining of the district court's refusal to award WorldCom interest from the date of the Commission's order. We will affirm the judgment of the district court in all respects.



BACKGROUND

This case concerns an interconnection agreement between Verizon, an incumbent local telephone exchange company, and WorldCom, a new entrant in the local exchange telecommunications market. (1) The interconnection of networks between telecommunications carriers makes it possible for customers of different carriers to call one another. Thus, interconnection agreements are crucial for new entrants to compete in the local telephone market. Both federal and state laws have been enacted to promote competition in local telephone markets and to require interconnection and procedures for negotiating and enforcing such agreements. See Federal Telecommunications Act (FTA) of 1996, 47 U.S.C.A. §§ 251-252 (West 2001); Public Utility Regulatory Act (PURA), Tex. Util. Code Ann. §§ 60.121-.128 (West 1998).

In September 1996, Verizon and WorldCom entered into an interim interconnection agreement. The interim agreement contemplated a permanent agreement, which had not been completed by the time this dispute arose. Although the parties failed to seek the Commission's approval of their interim agreement, and thereby did not comply with federal procedures set forth in section 252(e) of the FTA, they operated under the agreement for three years. See 47 U.S.C.A. § 252(e). (2) But when a dispute over terms of the agreement arose, this failure to seek Commission approval became problematic.

In May 1999, WorldCom filed its first complaint with the Commission in Docket No. 20870, alleging that Verizon had breached the interim agreement by failing to comply with reciprocal compensation provisions for terminating local traffic. Reciprocal compensation arrangements establish the terms by which local exchange carriers ("LECs") compensate each other for the use of the other's networks. See 47 U.S.C.A. § 251(b)(5), (c)(1) (West 2001). When an LEC's customer places a local call to a customer of another LEC, the LEC whose customer initiated the call compensates the receiving LEC for transporting and "terminating" the call through its network. Id. WorldCom complained that Verizon refused to compensate for the termination of Verizon's customers' calls to Internet Service Providers ("ISPs") that are WorldCom customers. The Commission dismissed the complaint without prejudice, ruling that it lacked jurisdiction to consider a dispute arising under an agreement that it had not approved. See Tex. Pub. Util. Comm'n, Arbitration Award (Dismissing Complaint), Docket No. 20870 (June 18, 1999).

In July 1999, WorldCom initiated a second proceeding in Docket No. 21088, seeking the Commission's approval of the interconnection agreement after the fact, presumably so the Commission could then assert its jurisdiction to resolve the parties' contractual dispute. Verizon refused to join the application for approval, taking the position that the agreement was no longer in the public interest. Verizon asked the Commission to dismiss WorldCom's application, insisting that Verizon's joinder was necessary before the Commission could approve the agreement. The administrative law judge certified the following question to the Commission: Can the Commission approve an agreement, even if a signatory party does not support its approval?

The Commission considered the unique circumstances of the dispute: an agreement that was supported by both parties when it was signed; an agreement that was intended to govern the parties' dealings for an interim period until a final agreement was reached, but that had in fact been in effect for three years; and the parties' inadvertent failure to seek the Commission's approval for the agreement because it "fell between the proverbial cracks." Tex. Pub. Util. Comm'n, Order on Certified Issue, Docket No. 21088 (Oct. 28, 1999) (citing Affidavit of Joseph A. Lazzara, the Verizon consultant responsible for negotiating the interim agreement in the summer of 1996). The Commission declined to answer the certified question but reversed its earlier decision that it lacked jurisdiction to settle this dispute. Referring to the unique facts outlined above, the Commission found that although the parties had failed to comply with the FTA's requirement that the Commission approve the interim agreement, the Commission nevertheless had jurisdiction to resolve the dispute under state law because PURA does not require the Commission's prior approval of an agreement to vest the Commission with authority to review it. See Tex. Pub. Util. Comm'n, Order on Certified Issue, Docket No. 21088 (Oct. 28, 1999). Having determined that it could assert its jurisdiction under state law without first approving the agreement, the Commission then dismissed as moot WorldCom's application for approval of the interim agreement. See Tex. Pub. Util. Comm'n, Order, Docket No. 21088 (Jan. 13, 2000).

Verizon sought judicial review of the Commission's action, and the trial court affirmed its order. This Court reviewed that judgment in GTE Southwest, Inc. v. Public Utility Commission, 37 S.W.3d 546 (Tex. App.--Austin 2001, no pet.). The contractual dispute, including the issue of the Commission's authority to hear the dispute under state law, was not before us in that cause. Rather, we limited our review to the dismissal of WorldCom's application for approval of the interim agreement. Id.

Free access — add to your briefcase to read the full text and ask questions with AI

GTE Southwest, Incorporated D/B/A Verizon Southwest/MCI Communications Corporation and MCI WorldCom Communications, Inc. v. Public Utility Commission of Texas MCI Communications Corporation And MCI WorldCom Communications, Inc./GTE Southwest Incorporated D/B/A Verizon Southwest, Inc., (Tex. Ct. App. 2003).

GTE Southwest, Incorporated D/B/A Verizon Southwest/MCI Communications Corporation and MCI WorldCom Communications, Inc. v. Public Utility Commission of Texas MCI Communications Corporation And MCI WorldCom Communications, Inc./GTE Southwest Incorporated D/B/A Verizon Southwest, Inc. (GTE Southwest, Incorporated D/B/A Verizon Southwest/MCI Communications Corporation and MCI WorldCom Communications, Inc. v. Public Utility Commission of Texas MCI Communications Corporation And MCI WorldCom Communications, Inc./GTE Southwest Incorporated D/B/A Verizon Southwest, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Nucor Steel v. PUB. UTILITY COM'N OF TEX.
26 S.W.3d 742 (Court of Appeals of Texas, 2000)
Coker v. Coker
650 S.W.2d 391 (Texas Supreme Court, 1983)
KMI Continental Offshore Production Co. v. ACF Petroleum Co.
746 S.W.2d 238 (Court of Appeals of Texas, 1988)
Intratex Gas Co. v. Puckett
886 S.W.2d 274 (Court of Appeals of Texas, 1994)
Robertson County v. Wymola
17 S.W.3d 334 (Court of Appeals of Texas, 2000)
Monesson v. Champion International Corp., Del-Mar Division
546 S.W.2d 631 (Court of Appeals of Texas, 1976)
Cardwell v. Sicola-Cardwell
978 S.W.2d 722 (Court of Appeals of Texas, 1998)
Southwestern Bell Telephone Co. v. Public Utility Commission of Texas
79 S.W.3d 226 (Court of Appeals of Texas, 2002)
Friendswood Development Co. v. McDade + Co.
926 S.W.2d 280 (Texas Supreme Court, 1996)
Atwood v. Rodman
355 S.W.2d 206 (Court of Appeals of Texas, 1962)
Verizon Maryland Inc. v. RCN Telecom Services, Inc.
248 F. Supp. 2d 468 (D. Maryland, 2003)
Nabisco, Inc. v. Rylander
992 S.W.2d 678 (Court of Appeals of Texas, 1999)
Texas Citrus Exchange v. Sharp
955 S.W.2d 164 (Court of Appeals of Texas, 1997)
GTE Southwest Incorporated v. Public Utility Commission of Texas
37 S.W.3d 546 (Court of Appeals of Texas, 2001)