Monesson v. Champion International Corp., Del-Mar Division

546 S.W.2d 631, 1976 Tex. App. LEXIS 3396
CourtCourt of Appeals of Texas
DecidedDecember 2, 1976
Docket971
StatusPublished
Cited by15 cases

This text of 546 S.W.2d 631 (Monesson v. Champion International Corp., Del-Mar Division) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Monesson v. Champion International Corp., Del-Mar Division, 546 S.W.2d 631, 1976 Tex. App. LEXIS 3396 (Tex. Ct. App. 1976).

Opinion

McKAY, Justice.

This is a contract case. Suit was instituted by appellee, Champion International Corporation, Del-Mar Division (Del-Mar), against Ronald J. Monesson (Monesson) for failure to pay for cabinets manufactured, sold and delivered under a contract to Monesson for a housing project known as “Chimney Hill Townhomes”. Monesson answered and filed a counterclaim alleging that Del-Mar breached a contract between the parties by failing and refusing to deliver cabinets for all 420 units in the project at the agreed price and thereby caused him to suffer damages in excess of those claimed by Del-Mar. Del-Mar’s first amended petition, upon which it went to trial, pled in the alternative, in quantum meruit, and attached exhibits of the contract in question alleging that Monesson had agreed in writing to pay attorney’s fee. A stipulation was entered into by the parties that judgment should be rendered in favor of Del-Mar for $18,167.09 for cabinets delivered but not paid for, together with attorney’s fee of $2,500.00 in the event the court determined Del-Mar was entitled to attorney’s fee. Trial was then had on Monesson’s counterclaim before a jury, and a verdict was returned favorable to Monesson. The trial court granted Del-Mar’s motion for judgment non obstante veredicto and rendered judgment for Del-Mar in accord with the stipulations, which included the attorney’s fee. Monesson brings this appeal on three points.

In 1971 Monesson, a real estate builder and developer, decided to construct a townhouse project in North Dallas. The plan contemplated a four-phase development eventually resulting in the construction of a total of 420 townhouses. Monesson began accepting bids from various materialmen. Lestingi, a sales representative of Del-Mar, submitted to Monesson a written bid or proposal dated April 6, 1972, on a printed form. The proposal referred to the project and offered to supply various styles of cabinets at certain set prices, although no specific quantity was mentioned other than the reference to the “420 UNIT TOWNHOUSE PROJECT — CHIMNEY HILL”. The proposal also had the term “Prices are subject to change without notice.” Del-Mar being the successful bidder, Monesson and Del-Mar’s sales representative, Joe Lestingi, both signed the proposal offered by Del-Mar, the result of which is the agreement which is the subject of dispute in this case. 1 Subsequently on January B, 1978, Monesson was requested to and did sign a proposal essentially identical to the one he had previously signed, because as the testimony showed, Lestingi wanted to confirm the previous agreement for phases 3 and 4. The January 3, 1973, instrument, on the same form, had the language “420 UNIT TOWNHOUSE PROJECT — CHIMNEY HILL — PHASE 3 & 4,” and in the subject to acceptance blank had “30” days. On January 18, 1973, another proposal on the same form was signed by Monesson and Larry Walls for Del-Mar which was designated “Addendum to Bid Dated January 3, 1973; 420 Unit Townhouse Project — Phase 3 & 4,” which added another model cabinet.

*634 [[Image here]]

Del-Mar had Lestingi to request Mones-son to accept a three per cent (3%) increase in price, but Monesson refused. Del-Mar continued providing cabinets until late in 1973, when, after Lestingi had left the employ of Del-Mar, another of its sales representatives asked Monesson to “renegotiate” the contract by accepting approximately a thirty-three per cent (33%) price increase. Monesson refused the price increase; and on January 1, 1974, Del-Mar stopped shipping cabinets to Monesson. Monesson *635 wrote Del-Mar on January 11, 1974, demanding that it honor the terms of the contract. Del-Mar replied by letter dated March 1, 1974, informing Monesson that it considered his failure to accept the price increase to be a breach of contract. This was followed by another letter to Monesson, dated March 7, 1974, from Del-Mar’s New York counsel, Stephen Brown, stating that Monesson was guilty of breach of contract and if Monesson obtained his cabinets elsewhere “We intend to include in our claim all losses suffered by Del-Mar” as a result of Monesson’s failure to perform under the contract. Del-Mar’s refusal to supply the remaining cabinets to Monesson at the contract price resulted in Monesson’s making a contract with another cabinet supplier for the remaining units, at a cost of approximately $63,000 more than the price agreed to by Del-Mar.

Monesson testified that prior to the 3% price increase request Del-Mar, through its chief executive officer Fisher, refused to give Monesson a requested three per cent (3%) advertising allowance on the ground that the contract fixed the prices to be charged for the entire development. Monesson also testified that Del-Mar had supplied cabinets to him for several previously built projects, and that the same contract form was used on each of them and that Del-Mar had never asked for a price increase on any other project. He testified that Del-Mar made him a proposal through their representative, Lestingi, and that he accepted it by signing it as he had all the others, and that it was his intention that the agreement was for the entire 420 units at fixed prices. Monesson further testified that the language “Prices subject to change without notice” was intended to apply so long as it was a proposal, but after he accepted the proposal it meant “We had a firm contract and I was entitled to rely upon those prices throughout the development and Del-Mar was entitled to rely upon my purchasing from them at those prices.”

Lestingi, Del-Mar’s sales representative, testified that it was his intention that the contract prices were fixed for the entire 420 units from time of Monesson’s acceptance, and that Del-Mar’s prices were based on the fact that Del-Mar bid on the entire 420 units, and that it was Del-Mar’s intention to give Monesson a commitment to supply the 420 units at the fixed prices set out in the contract. Also introduced was evidence of custom and practice in the building industry to the effect that offers to sell are made by proposals or bids, and that once a proposal is accepted by both parties, it is binding on both as to quantity and the prices become fixed.

Del-Mar objected to the testimony of Monesson and Lestingi on the ground that such evidence was a violation of the parol evidence rule and was an attempt to vary the terms of a written contract. The jury found in Special Issue Number One that the contract was for cabinets for all of the 420 townhouses; and in Special Issue Number Two, that the prices were fixed, according to the proposal, for the whole term of the contract. 2 The trial court granted judgment notwithstanding the verdict on the *636 basis that the findings had no support in the evidence and did so apparently for the reason that they were based on inadmissible parol evidence, contravening the unambiguous terms of a written contract, or that the parties had no contract at all. Appellant’s first two points attack this action of the trial court.

A trial court “may render judgment non obstante veredicto if a directed verdict would have been proper. . . . ” Rule 301, T.R.C.P. To sustain the action of the trial court in granting a motion non obstante veredicto it must be determined that there is no evidence upon which the jury could have made the findings relied upon, Douglass v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lincoln Farm, L.L.C. v. Oppliger
2013 OK 85 (Supreme Court of Oklahoma, 2013)
Robert Veshone Monroe v. State
Court of Appeals of Texas, 2008
GTE Southwest, Inc. v. Public Utility Commission
102 S.W.3d 282 (Court of Appeals of Texas, 2003)
Allen v. Wachtendorf
962 S.W.2d 279 (Court of Appeals of Texas, 1998)
C & C Partners v. Sun Exploration & Production Co.
783 S.W.2d 707 (Court of Appeals of Texas, 1989)
Summit Bank v. the Creative Cook
730 S.W.2d 343 (Court of Appeals of Texas, 1987)
Eans v. Grocer Supply Co., Inc.
580 S.W.2d 17 (Court of Appeals of Texas, 1979)
Thompson v. Preston State Bank
575 S.W.2d 312 (Court of Appeals of Texas, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
546 S.W.2d 631, 1976 Tex. App. LEXIS 3396, Counsel Stack Legal Research, https://law.counselstack.com/opinion/monesson-v-champion-international-corp-del-mar-division-texapp-1976.