Sam Houston Electric Cooperative, Inc. v. Public Utility Commission of Texas

733 S.W.2d 905, 1987 Tex. App. LEXIS 8057
CourtCourt of Appeals of Texas
DecidedMay 6, 1987
Docket14587
StatusPublished
Cited by26 cases

This text of 733 S.W.2d 905 (Sam Houston Electric Cooperative, Inc. v. Public Utility Commission of Texas) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sam Houston Electric Cooperative, Inc. v. Public Utility Commission of Texas, 733 S.W.2d 905, 1987 Tex. App. LEXIS 8057 (Tex. Ct. App. 1987).

Opinion

GAMMAGE, Justice.

Sam Houston Electric Cooperative, Inc. (“SHECO”) appeals the district court judgment affirming an order of the Public Utility Commission (“Commission”) which denied SHECO’s application for amendment of its certificate of convenience and necessity. We will reverse the judgment of the district court.

SHECO is a “public utility” as defined by the Public Utility Regulatory Act (“PURA”), Tex.Rev.Civ.Stat.Ann. art. 1446c, § 3(c) (Supp.1987). On October 7, 1981, SHECO filed an application to amend its certificate of convenience and necessity to allow construction of a transmission-line project composed of three elements: a 5.3-mile, 138-kilovolt electric transmission line (“TEMCO/Evergreen line”); an associated switching station (“TEMCO switching station”); and an associated distribution substation (“Evergreen substation”). The Commission set the application in Docket Number 4101. In October 1981, before the Commission had acted upon SHECO’s application, SHECO cleared a 100-foot right-of-way over which it planned to construct the TEMCO/Evergreen transmission line. The Commission approved the amendment of SHECO’s certificate to allow construction of the project on December 3, 1981.

Robert S. Baird, an owner of property over which SHECO proposed to construct its transmission line, filed a complaint against SHECO on January 25, 1982. Baird’s complaint, filed in Docket 4292, alleged that SHECO gave inadequate public notice of the application to amend its certificate. On March 11, 1982, the Commission voided the previously granted certificate amendment on three grounds: (1) SHECO failed to comply with the agency’s public notice requirements; (2) SHECO failed to obtain a certificate before construction of the proposed project; and (3) proper public notice is a jurisdictional requirement in certification cases.

SHECO filed a new certificate amendment application in Docket 4405 on March 26, 1982, and published proper notice of its *908 application. Several interested parties, including Baird, intervened to protest the application. After an evidentiary hearing on the merits, the examiner issued a report recommending the certificate be amended. The examiner determined that certification of the proposed transmission line project was necessary for the service, accommodation, convenience and safety of the public under PURA § 54(b). The examiner also concluded that certification of the proposed project would not have a negative impact on aesthetic values, environmental integrity, community values, recreational and park areas, or historical values under PURA § 54(c). The intervenors filed exceptions to the examiner’s report.

The Commission heard oral argument and on July 9, 1984, issued its final order. The Commission’s final order set aside the opinion portion of the examiner’s report and entered new findings of fact and conclusions of law supporting a denial of SHE-CO’s application. The Commission determined that SHECO failed to meet its statutory burden of proof under PURA § 54(c) and failed to prove the transmission line was needed. It also held that the proposed transmission line project necessarily encompassed the proposed TEMCO switching station and Evergreen substation and, therefore, a denial of certification for the line deprived SHECO of the legal authority to construct any portion of the project.

SHECO appealed to the district court which affirmed the Commission’s order on grounds that it was supported by substantial evidence and was based upon lawful Commission procedures. The district court also ruled that SHECO could not join a declaratory judgment action to its administrative appeal and refused to hear evidence relating to the declaratory judgment action.

SHECO brings six points of error, arguing first that the trial court erred in concluding the Commission did not exceed its statutory authority in prohibiting construction of the proposed transmission line project because the facilities sought to be constructed are statutorily exempt from certification.

PURA § 50 requires generally that public utilities obtain a certificate of convenience and necessity before rendering utility service to the public. Exceptions to the certification requirement are set out in PURA § 51:

Sec. 51. (a) A public utility is not required to secure a certificate of public convenience and necessity for:
# * * * * *
(2) an extension within or to territory already served by it or to be served by it under a certificate of public convenience and necessity; or
[[Image here]]
(b) Any extensions allowed by Subsection (a) of this section shall be limited to devices for interconnection of existing facilities or devices used solely for transmitting public utility services from existing facilities to customers of retail utility service.

SHECO urges that the proposed transmission line falls within the § 51(a)(2) exception to the certification requirement because it would be built within an area already served by SHECO under its certificate of convenience and necessity. We question but do not decide whether the proposed facilities qualify as an “extension” within the meaning of § 51(a). SHE-CO’s own engineer and expert witness testified as follows:

Q. Is this 138 KV line — or did you characterize it as a new line?
A. It’s the first segment of a planned transmission line that we would have west of Lake Livingston.
Q. It’s not an extension of any other 138 KV line owned by Sam Houston, is it?
A. No.
# # * * * *
A. It is not an extension of an existing Sam Houston [line].
Q. Is there any way in the fartherest [sic] stretch of your imagination that you *909 could characterize this 138 KV Temco to Evergreen transmission line as an extension right now? Not that it will be extended but as an extension right now of an existing Sam Houston line?
A. Not of a Sam Houston line.

Even if the proposed line qualifies as an extension, it must still meet the limits imposed by PURA § 51(b). SHECO argues there are two limitations in § 51(b): (1) “devices for interconnection of existing facilities”; or (2) “devices used solely for transmitting public utility services from existing facilities to customers of retail utility service.” The Commission, on the other hand, claims the phrase "used solely for transmitting public utility service from existing facilities to customers of retail utility service” qualifies the phrase “existing facilities or devices,” constituting only one limitation to § 51(a)’s non-certification exceptions. We need not resolve this question.

Even were we to accept the broader construction of § 51(b) urged by SHECO (again assuming arguendo that the proposed facilities qualify as an “extension” under § 51(a)), we still find the proposed facilities would not qualify as either “devices for interconnection of existing facilities” or “devices used solely for transmitting public utility services from existing facilities to customers of retail utility service.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

ENTERGY GULF STATES, INC. v. Traxler
320 S.W.3d 553 (Court of Appeals of Texas, 2010)
Texas Mutual Insurance Co. v. Vista Community Medical Center, LLP
275 S.W.3d 538 (Court of Appeals of Texas, 2009)
Hammack v. Public Utility Com'n of Texas
131 S.W.3d 713 (Court of Appeals of Texas, 2004)
City of Corpus Christi v. Public Utility Commission of Texas
51 S.W.3d 231 (Texas Supreme Court, 2001)
Nucor Steel v. PUB. UTILITY COM'N OF TEX.
26 S.W.3d 742 (Court of Appeals of Texas, 2000)
Quimby v. Texas Department of Transportation
10 S.W.3d 778 (Court of Appeals of Texas, 2000)
Texas Citrus Exchange v. Sharp
955 S.W.2d 164 (Court of Appeals of Texas, 1997)
Public Utility Commission v. Gulf States Utilities Co.
809 S.W.2d 201 (Texas Supreme Court, 1991)
Goeke v. Houston Lighting & Power Co.
797 S.W.2d 12 (Texas Supreme Court, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
733 S.W.2d 905, 1987 Tex. App. LEXIS 8057, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sam-houston-electric-cooperative-inc-v-public-utility-commission-of-texapp-1987.