Hammack v. Public Utility Com'n of Texas

131 S.W.3d 713, 2004 Tex. App. LEXIS 3396, 2004 WL 792193
CourtCourt of Appeals of Texas
DecidedApril 15, 2004
Docket03-02-00232-CV
StatusPublished
Cited by95 cases

This text of 131 S.W.3d 713 (Hammack v. Public Utility Com'n of Texas) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hammack v. Public Utility Com'n of Texas, 131 S.W.3d 713, 2004 Tex. App. LEXIS 3396, 2004 WL 792193 (Tex. Ct. App. 2004).

Opinion

OPINION

DAVID PURYEAR, Justice.

Our opinion and judgment issued on October 23, 2003 are withdrawn, and the following opinion is substituted.

Robert “Lee” Hammack and others (“appellants”) appeal from a district court judgment affirming an order of the Public Utility Commission of Texas (the “Commission”) granting a certifícate of convenience and necessity (“CCN”) to Central Power and Light Company (“Central Power”). 2 Before an electric utility may construct a transmission line, it must obtain a CCN from the Commission. See Tex. Util. Code Ann. § 37.056 (West 1998) (hereinafter “PURA”). The Commission referred Central Power’s application to the State Office of Administrative Hearings (“SOAH”). After conducting a contested-case hearing according to the Administrative Procedure Act (“APA”), the Administrative Law Judge (“ALJ”) issued a proposal for decision (“PFD”) recommending denial of Central Power’s application. See Tex. Gov’t Code Ann. §§ 2001.001-.902 (West 2000 & Supp.2003). The Commission declined to adopt the proposal for decision in its entirety and approved Central Power’s application for a CCN. The district court affirmed the Commission’s order. 3

*718 Appellants appeal by fourteen points of error, complaining that: (1) the Commission applied a new standard in finding a need for the line, inconsistent with the statutory requirements; (2) the finding of need for the line was not supported by substantial evidence; (3) the finding that the new service will lower costs to customers and improve service is not supported by substantial evidence; and (4) the Commission improperly approved the route for the line. In addition, appellants complain of various procedural irregularities in adopting the order. We will affirm the judgment of the district court, affirming the order of the Commission.

FACTUAL BACKGROUND

Many electric utilities in Texas have voluntarily interconnected their transmission systems, enhancing reliability and providing opportunities for utilities to purchase power from one another. This interconnected network of transmission lines forms a single grid within the state, known as the Electric Reliability Council of Texas (ER-COT). Although two other regional power grids serve parts of the state, ERCOT serves most of the state. 4

ERCOT is required to establish an Independent System Operator (ISO) charged with oversight of the transmission system in Texas. See PURA § 89.151 (West Supp.2003). One of the statutory directives is to “ensure the reliability and adequacy of the regional electrical network.” Id. § 39.151(a)(2). To accomplish this, ERCOT is given authority to enforce operating standards by establishment of policies, rules, guidelines, and procedures. Id. § 39.151(d), (h). To effectuate the legislative goal of adequate and reliable service, utilities are required to abide by the policies, rules, and procedures established by ERCOT. Id. § 39.151®. The ISO’s responsibilities include providing an annual report to the Commission identifying existing and potential transmission and distribution constraints, system needs, and recommendations for meeting those needs. See id. § 39.155(b) (West Supp.2003). 5

In 1996, Central Power expressed a concern regarding a shortage of power in the Rio Grande Valley. The line which is the subject of this case was proposed to ER-COT to increase the capacity of transmission into the Rio Grande Valley to meet a future-projected load. On October 1,1999, pursuant to the requirements of PURA section 39.155, the ISO sent a report to the Commission identifying, among other concerns, a constraint on the transfer capacity of power into South Texas as well as a constraint on transfer capacity from South to North.

On November 30, 1999, Central Power filed its application for a CCN to construct a 53-mile-long, high-voltage transmission line from Central Power’s Coleto Creek Power Plant in Goliad County to the Pawnee Substation in Karnes County. The Commission referred the case to SOAH to conduct a contested-case hearing. Numerous landowners, some of whom were plaintiffs below, intervened in the agency proceeding. In August 2000, the ALJ issued a PFD recommending denial of the application. The ALJ found, among other *719 things, that there was insufficient evidence demonstrating a public need for the proposed line. However, the PFD supported the route proposed by Central Power.

The Commission reviewed the evidence and in its final order found there was a public need for the line, that existing service was inadequate, and that granting the CCN would result in a probable improvement of service or lower costs to consumers. Appellants sought judicial review in district court, which affirmed the Commission’s order in March 2002. Appellants appeal from the judgment.

DISCUSSION

Statutory Requirements of Necessity

Before addressing appellants’ points of error, it is necessary first to set out the statutory provisions that govern the Commission’s issuance of certificates of convenience and necessity. Under section 37.051 of PURA, a public utility is forbidden to render service to the public, directly or indirectly, “unless the utility first obtains from the commission a certificate that states that the public convenience and necessity requires or will require the installation, operation, or extension of the service.” Id. § 37.051 (West Supp.2003). The Commission can grant a CCN pursuant to PURA section 37.056 as follows:

Section 37.056. Grant or Denial of Certificate
(a) The commission may approve an application and grant a certificate only if the commission finds that the certificate is necessary for the service, accommodation, convenience, or safety of the public.
(b) The commission may:
(1) grant the certificate as requested;
(2) grant the certificate for the construction of a portion of the requested system, facility, or extension or the partial exercise of the requested right or privilege; or
(3)refuse to grant the certificate.
(c)The commission shall grant each certificate on a nondiscriminatory basis after considering:
(1) the adequacy of existing service;
(2) the need for additional service;
(3) the effect of granting the certificate on the recipient of the certificate and any electric utility serving the proximate area; and
(4) other factors, such as:
(A) community values;
(B) recreational and park areas;

Free access — add to your briefcase to read the full text and ask questions with AI

Related

in the Interest of S.A.G., a Child
403 S.W.3d 907 (Court of Appeals of Texas, 2013)
Public Utility Commission v. Cities of Harlingen
311 S.W.3d 610 (Court of Appeals of Texas, 2010)
In Re Texas State Board of Public Accountancy
303 S.W.3d 892 (Court of Appeals of Texas, 2010)
Walker v. Texas Department of Family & Protective Services
312 S.W.3d 608 (Court of Appeals of Texas, 2009)
AEP Texas Central Co. v. Public Utility Commission of Texas
258 S.W.3d 272 (Court of Appeals of Texas, 2008)
Geeslin v. State Farm Lloyds
255 S.W.3d 786 (Court of Appeals of Texas, 2008)
State v. PUBLIC UTILITY COM'S OF TEXAS
246 S.W.3d 324 (Court of Appeals of Texas, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
131 S.W.3d 713, 2004 Tex. App. LEXIS 3396, 2004 WL 792193, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hammack-v-public-utility-comn-of-texas-texapp-2004.