Public Utility Commission v. Cities of Harlingen

311 S.W.3d 610, 2010 WL 1173070
CourtCourt of Appeals of Texas
DecidedMay 27, 2010
Docket03-08-00793-CV
StatusPublished
Cited by24 cases

This text of 311 S.W.3d 610 (Public Utility Commission v. Cities of Harlingen) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Public Utility Commission v. Cities of Harlingen, 311 S.W.3d 610, 2010 WL 1173070 (Tex. Ct. App. 2010).

Opinions

OPINION

G. ALAN WALDROP, Justice.

This case involves an administrative appeal challenging an order of the Public Utility Commission of Texas approving the application of Electric Transmission Texas, LLC (ETT) for regulatory approval of (1) ETT’s formation transactions, (2) the transfer to ETT of certain transmission equipment held under another utility’s certificate of convenience and necessity (CCN), and (3) ETT’s initial rates. Prior to the administrative proceeding, ETT did not possess a CCN under which it could provide service to the public as an electric utility pursuant to the Public Utility Regulatory Act (PURA).1 Following the Commission’s order, ETT was approved to become an electric utility that provided only transmission-related services.

The district court found that the Commission exceeded its statutory authority by granting a CCN to ETT, and reversed the Commission’s order. The district court also found that the Commission erred by denying the municipalities that had intervened in the proceeding any of their expenses, and the court remanded the case to the Commission for a redetermination of the municipalities’ reasonable expenses pursuant to PURA section 33.023.

The Commission and ETT appeal the district court’s judgment. We hold that the Commission acted within its statutory authority in granting a CCN to ETT, and in approving the transfer to ETT of rights obtained under a CCN pursuant to PURA section 37.154 without requiring compliance with the provisions of section 37.056. We also hold that the Commission’s approval of the underlying formation transactions is supported by substantial evidence. However, we conclude that the Commission erred in determining that it was prohibited from granting the intervening municipalities reimbursement of their reasonable expenses. Consequently, we affirm the judgment of the district court as to its remand of the case for the Commission’s reconsideration of whether to reimburse the municipalities for their expenses, and we reverse the remainder of the judgment of the district court and render judgment that the Commission’s final order is otherwise affirmed.

Factual and Procedural Background

ETT filed an application with the Public Utility Commission in January 2007, seeking regulatory approvals needed to commence operations. ETT sought to become an electric utility whose activities would be limited to acquiring, constructing, owning, and operating transmission facilities within the state overseen by the Electric Reliability Council of Texas (ERCOT). Transmission for purposes of this proceeding involves transporting electricity over power lines at higher voltage. ETT would be owned in equal 50% shares by subsidiaries of American Electric Power Company, Inc. and MidAmerican Energy Holdings Company. American Electric Power’s investment was to include the transmission assets to be transferred, which had been constructed and were operated by its subsidiary AEP Texas Central Company [615]*615(TCC) under an existing CCN, and Mi-dAmerican was to contribute a comparable amount of cash to capitalize the venture. The facilities and related rights that would initially be transferred, subject to ETT’s application, were not yet in TCC’s rates.

ETT applied to the Commission for a CCN to provide service as an electric utility in Texas, see Tex. UtiLCode Ann. § 37.051(a) (West 2007), for approval of the transactions to form, capitalize, and structure ETT, see id. § 14.101 (West 2007), and for approval of ETT’s initial rates for transmission service, see id. § 36.001 (West 2007).2 Appellees — the Cities of Harlingen, McAllen, Mission, Port Lavaca, Rockport, and Victoria (the “Cities”), Texas Industrial Energy Consumers (TIEC), and the State of Texas— separately intervened in the proceeding, contesting portions of ETT’s application.

On December 21, 2007, the Commission on rehearing issued its final order on ETT’s application. The Commission found that the PURA contemplates the certification of a utility providing only transmission services. The Commission also found that, although ETT had originally requested a CCN in its application pursuant to PURA section 37.056, which governs the grant of a CCN, see id. § 37.056 (West 2007), it was more appropriate to apply PURA section 37.154, which governs the transfer of a CCN, see id. § 37.154 (West 2007). The Commission then granted ETT’s application for the transfer to ETT of TCC’s right to operate the initial facilities under the existing CCN in accordance with section 37.154, and approved ETT’s formation transactions as in the public interest taking into consideration the factors set out in PURA section 14.101. In addition, the Commission set ETT’s initial rates, granted ETT’s request for expense reimbursement, and denied the Cities’ request for reimbursement of their expenses incurred in connection with the proceeding.3

Appellees the Cities, TIEC, and the State separately sought review of the Commission’s order in district court, and the causes were consolidated by request of the parties. ETT intervened in the case in support of the Commission’s final order. Appellees challenged the transfer of the CCN by asserting that a utility which provides only transmission services and, therefore, which has no certificated service area cannot obtain a CCN under the PURA, that a utility without a preexisting CCN cannot receive by transfer rights obtained under another utility’s CCN unless the requirements of PURA section 37.056 are satisfied, and that approval of the transfer under section 37.154 despite the application’s citing only sections 37.051 and 37.056 was a violation of appellees’ right to due process and was outside of the Commission’s subject-matter jurisdiction. Ap-pellees also challenged the approval of ETT’s formation transactions, asserting that the Commission’s determination that the transactions satisfied PURA section 14.101 was not supported by substantial evidence. Lastly, the Cities challenged the Commission’s denial of their request for reimbursement of expenses.

On October 8, 2008, the district court issued its judgment in favor of appellees, reversing the Commission’s order. The judgment contains the following findings:

(1) the primary issues the Court considered in issuing this Order relate to [616]*616questions of statutory construction and procedural due process and are therefore reviewed de novo;
(2) the Public Utility Commission (“PUC”) exceeded its statutory authority by granting Electronic [sic] Transmission Texas, LLC (“ETT”) a certificate of convenience and necessity (“CCN”) pursuant to the Public Utility Regulatory Act, Tex. Utilities Code § 37.154 (“PURA”) instead of analyzing the request for a CCN pursuant to PURA §§ 37.051 and 37.056, the relevant statutes;
(3) the PUC violated the Plaintiffs’ due process rights when it granted ETT a CCN based on PURA § 37.154 when such basis was not pled or raised by the PUC or ETT until after the close of evidence below;
(4) the PUC exceeded its statutory authority and lacked subject matter jurisdiction by granting ETT a CCN based on PURA § 37.154 while accepting jurisdiction over the case based on different statutes, PURA §§ 37.051 and 37.056;
(5) the PUC exceeded its statutory authority in granting a CCN to ETT, a transmission-only utility without a service area; and further

Free access — add to your briefcase to read the full text and ask questions with AI

Related

NextEra v. D'Andrea
Fifth Circuit, 2022
NextEra v. Lake
48 F.4th 306 (Fifth Circuit, 2022)
RR Maloan Investments, Inc. v. New HGE, Inc.
428 S.W.3d 355 (Court of Appeals of Texas, 2014)
In re C.L.S.
403 S.W.3d 15 (Court of Appeals of Texas, 2012)
Slay v. Texas Commission on Environmental Quality
351 S.W.3d 532 (Court of Appeals of Texas, 2011)
Slay v. TEX. COM'N ON ENVIRONMENTAL QUALITY
351 S.W.3d 532 (Court of Appeals of Texas, 2011)
Romo v. Payne
334 S.W.3d 364 (Court of Appeals of Texas, 2011)
Public Utility Commission v. Cities of Harlingen
311 S.W.3d 610 (Court of Appeals of Texas, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
311 S.W.3d 610, 2010 WL 1173070, Counsel Stack Legal Research, https://law.counselstack.com/opinion/public-utility-commission-v-cities-of-harlingen-texapp-2010.