Oncor Electric Delivery Company LLC, and the Public Utility Commission of Texas v. Giovanni Homes Corporation

CourtCourt of Appeals of Texas
DecidedMay 30, 2025
Docket03-23-00322-CV
StatusPublished

This text of Oncor Electric Delivery Company LLC, and the Public Utility Commission of Texas v. Giovanni Homes Corporation (Oncor Electric Delivery Company LLC, and the Public Utility Commission of Texas v. Giovanni Homes Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Oncor Electric Delivery Company LLC, and the Public Utility Commission of Texas v. Giovanni Homes Corporation, (Tex. Ct. App. 2025).

Opinion

TEXAS COURT OF APPEALS, THIRD DISTRICT, AT AUSTIN

NO. 03-23-00322-CV

Oncor Electric Delivery Company LLC and the Public Utility Commission of Texas, Appellants

v.

Giovanni Homes Corporation, Appellee

FROM THE 419TH DISTRICT COURT OF TRAVIS COUNTY NO. D-1-GN-19-007049, THE HONORABLE CATHERINE MAUZY, JUDGE PRESIDING

M E M O RAN D U M O PI N I O N

Appellants Oncor Electric Delivery Company LLC and the Public Utility

Commission of Texas (PUC or Commission) challenge the trial court’s final judgment reversing

the PUC’s July 19, 2019 Order (“Final Order”), which resolved a complaint filed by appellee

Giovanni Homes Corporation against Oncor. The trial court concluded that the Final Order

“exceeds the Commission’s statutory authority and violates Giovanni Homes Corporation’s right

to a jury trial pursuant to Article I, Section 15 of the Texas Constitution.” In two issues, Oncor

and the Commission each argue that the trial court erred by (1) concluding that the Commission

exceeded its statutory authority because the Commission properly determined its jurisdiction over

Giovanni’s claims against Oncor and (2) concluding that the Final Order violates Giovanni’s

constitutional right to trial by jury. In their third issue, they argue that the trial court erred by

reversing the Final Order because the Final Order is supported by substantial evidence. For the reasons explained below, we reverse the trial court’s judgment, and we render judgment affirming

the Commission’s Final Order.

BACKGROUND 1

Factual background

Giovanni, a now-defunct custom homebuilder in the Tarrant County area, bought

platted but undeveloped lots in the Waterchase development in 2004 to develop them. Giovanni

contacted Oncor in early 2006 about providing electricity for three townhomes it had built on its

lots and for other planned residences. Oncor is a transmission-and-distribution utility (TDU)

regulated by the PUC; it serves the City of Fort Worth, among other Texas cities. 2 Oncor Elec.

Delivery Co. v. Chaparral Energy, LLC, 546 S.W.3d 133, 138 (Tex. 2018). As a TDU, Oncor’s

tariff governs its retail rates, services, and operations. Id. at 142 (“As a PUC-regulated utility,

Oncor is required to file a tariff with the PUC describing its rates, operations, and services.” (citing

Tex. Util. Code § 32.101(a))). “Once the PUC approves the tariff, Oncor must comply with [its]

requirements and apply its rates and provide its services uniformly to all of its retail customers.” 3 Id.

1 The facts in this background section include undisputed facts from the parties’ briefs (except where a dispute is noted) and unchallenged findings of fact from the Commission’s Final Order. 2 Oncor is the largest TDU in Texas and the sixth largest in the United States, serving over 7 million consumers in 401 cities and 91 counties. Oncor Elec. Delivery Co. v. Public Util. Comm’n of Tex., 507 S.W.3d 706, 709-10 (Tex. 2017). 3 The Commission requires all TDUs to use a “Pro-forma Retail Delivery Tariff” that it promulgates by rule. 16 Tex. Admin. Code § 25.214(c), (d) (pro-forma tariff) (Pub. Util. Comm’n, Terms and Conditions of Retail Delivery Serv. Provided by Investor Owned TDUs) (2015). “TDUs may add to or modify only Chapters 2 and 6 of this tariff, reflecting individual utility characteristics and rates, in accordance with commission rules and procedures to change a tariff . . . .” Id. § 25.214(c). For convenience, the Court cites to the current version of the

2 After Giovanni requested electric service to the three constructed townhomes,

Giovanni and Oncor discussed the additional service Giovanni would need for its planned

development of other residences. Oncor first issued a work authorization request on May 24, 2006,

to install electric-delivery facilities. As Giovanni continued to modify its proposed layout for the

residential lots, Oncor redesigned the facilities needed to serve those lots. In April 2007, Giovanni

began discussing with Oncor how Oncor could also serve a planned commercial building. In July

2007, Oncor determined that a new single-phase distribution line would need to be constructed to

serve Giovanni’s lots.

In addition, after Giovanni discovered an underground line on its property on

April 27, 2007, it requested the relocation of the underground three-phase line and a pad-mounted

three-phase transformer that Oncor had placed outside the platted utility easement years before

Giovanni had purchased the lots. 4 Because the relocation involved moving the line and

transformer to neighboring property, additional easements were necessary, and Giovanni agreed to

obtain them. After Giovanni provided Oncor with the final executed easement in December 2007,

Oncor completed, approved, and packaged the relocation design from January to March 2008.

In March 2008, when Oncor was about a week away from completing the planned

relocation of the three-phase line and transformer, a representative of the neighboring property

Administrative Code where there has been no relevant substantive change since the events that led to Giovanni’s suit. The versions of Oncor’s tariff relevant to Giovanni’s breach-of-contract claim are the 2003 and 2006 versions, which, respectively, were in effect when Giovanni requested the Out-of- Easement Facilities’ relocation and the Single-Phase Line’s installation described later in this background section. The tariffs were introduced into evidence at the administrative hearing. For simplicity, we refer to them as “Oncor’s tariff” unless it is necessary to distinguish them. 4 No one disputes that the line was located outside of the platted utility easement at the direction of a previous owner or that it supplied electricity to two neighboring properties. 3 owner informed Oncor that the property owner’s signature on the easement for his parking lot was

forged and raised other concerns about locating the transformer in the parking lot. As a result,

Oncor stopped its construction work on the relocation of the three-phase line and transformer. The

delay also affected Oncor’s construction work on the single-phase line, which was to be routed

onto the same property owner’s property. An April 2008 major storm then affected the availability

of Oncor’s crews to work on the single-phase line. In May 2008, the neighboring property owner

objected to the line running through trees on his property, which required Oncor to do a limited

redesign of the single-phase line.

Oncor finished installing the single-phase line on June 26, 2008, and the line was

available to serve the three constructed townhomes and Giovanni’s other lots. Due to the delay

from the necessity of working with the neighboring property owners on the relocation and delays

from major storms, including two hurricanes, in Oncor’s service area in the period between April

2008 through September 2008, and the accompanying backlog of non-safety-related work, Oncor

did not complete the relocation of the three-phase line and transformer until February 2009.

Trial in Tarrant County District Court

In September 2008, Giovanni sued Oncor in Tarrant County District Court, alleging

claims arising from the parties’ interactions in 2007 and 2008.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

J.M. Davidson, Inc. v. Webster
128 S.W.3d 223 (Texas Supreme Court, 2003)
Entergy Gulf States, Inc. v. Summers
282 S.W.3d 433 (Texas Supreme Court, 2009)
Reliant Energy, Inc. v. Public Utility Commission
153 S.W.3d 174 (Court of Appeals of Texas, 2004)
City of El Paso v. Public Utility Commission
883 S.W.2d 179 (Texas Supreme Court, 1994)
Subaru of America, Inc. v. David McDavid Nissan, Inc.
84 S.W.3d 212 (Texas Supreme Court, 2002)
Cincinnati Life Insurance Co. v. Cates
927 S.W.2d 623 (Texas Supreme Court, 1996)
Nucor Steel v. PUBLIC UTILITY COM'N OF TEX.
168 S.W.3d 260 (Court of Appeals of Texas, 2005)
Southwestern Electric Power Co. v. Grant
73 S.W.3d 211 (Texas Supreme Court, 2002)
Public Utility Commission v. Cities of Harlingen
311 S.W.3d 610 (Court of Appeals of Texas, 2010)
In Re Entergy Corp.
142 S.W.3d 316 (Texas Supreme Court, 2004)
in the Interest of M.G.N. and A.C.N., Minor Children
441 S.W.3d 246 (Texas Supreme Court, 2014)
Oncor Electric Delivery Company LLC v. Giovanni Homes Corporation
438 S.W.3d 644 (Court of Appeals of Texas, 2014)
TIC Energy & Chemical, Inc. v. Martin
498 S.W.3d 68 (Texas Supreme Court, 2016)
Oncor Elec. Delivery Co. v. Chaparral Energy, LLC
546 S.W.3d 133 (Texas Supreme Court, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
Oncor Electric Delivery Company LLC, and the Public Utility Commission of Texas v. Giovanni Homes Corporation, Counsel Stack Legal Research, https://law.counselstack.com/opinion/oncor-electric-delivery-company-llc-and-the-public-utility-commission-of-texapp-2025.