Oncor Electric Delivery Company LLC v. Giovanni Homes Corporation

438 S.W.3d 644, 2014 WL 1320943, 2014 Tex. App. LEXIS 3596
CourtCourt of Appeals of Texas
DecidedApril 3, 2014
Docket02-11-00237-CV
StatusPublished
Cited by7 cases

This text of 438 S.W.3d 644 (Oncor Electric Delivery Company LLC v. Giovanni Homes Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Oncor Electric Delivery Company LLC v. Giovanni Homes Corporation, 438 S.W.3d 644, 2014 WL 1320943, 2014 Tex. App. LEXIS 3596 (Tex. Ct. App. 2014).

Opinion

OPINION

BOB McCOY, Justice.

I. Introduction

In three issues, appellant Oncor Electric Delivery Company LLC appeals the trial court’s judgment on the jury verdict for appellee Giovanni Homes Corporation on Giovanni Homes’s breach-of-contract claim and award of attorneys’ fees and argues that Giovanni Homes’s trespass claim cannot serve as an alternative basis for judgment against it. In a single issue in its cross-appeal, Giovanni Homes appeals the trial court’s judgment notwithstanding the verdict (JNOV) in favor of Oncor on the jury’s award of interest payments on construction loans to Giovanni Homes.

Having encountered a jurisdictional defect in the case, 1 we do not reach the merits of these issues. We reverse the trial court’s judgment and remand this case to the trial court with instructions to abate the case to allow Giovanni Homes a reasonable opportunity to cure the jurisdictional defect if possible. See Am. Motorists Ins. Co. v. Fodge, 63 S.W.3d 801, 805 (Tex.2001) (stating that the court may abate proceedings to allow a reasonable opportunity to cure a jurisdictional impediment if the impediment is one that can be cured).

II. Factual and Procedural Background

Giovanni Homes had to work with On-cor 2 to obtain electricity for some parcels *646 of real property that it was developing in Fort Worth. Giovanni Homes wanted to secure a new single-phase electrical line to serve the development; after discovering a three-phase electrical line on its property on April 27, 2007, it also wanted to relocate that line and transformer box from its property. 3 The single-phase line was not installed until June 2008, and the three-phase line was not relocated until February 2009. Ultimately, the parties went to trial in December 2010 on Giovanni Homes’s claims arising from the parties’ interactions in 2007 and 2008. 4

Giovanni Homes’s breach-of-contract theory was based primarily on Plaintiffs Exhibit 80, a July 23, 2007 letter from Richard Hildebrand, an Oncor employee, to a Giovanni Homes secretary, which states,

Oncor Electric Delivery intends to reroute the existing underground primary cable currently installed through the lot in question into a new easement along the private drive to be provided by Giovanni Homes. The relocation will reconnect the existing service necessary to provide service to the existing customers along with serving the new proposed development.

Vincent Piras, Giovanni Homes’s owner, testified that in exchange for the lines’ installation and relocation, Giovanni Homes was to obtain the easements across neighboring properties for Oncor and that he had obtained all of those easements and delivered them to Oncor by December 6, 2007.

The trial court submitted Question No. 1 to the jury:

Did Giovanni Homes and Oncor agree on July 23, 2007 that:
a. Oncor would relocate the three-phase underground primary cable from the Residential Lots and the Commercial Lot to a new easement?
b. Oncor would supply electrical power via single-phase line to the Townhome Lots, Residential Lots, and Commercial Lot?
In deciding whether the parties reached an agreement, you may consider what they said and did in light of the surrounding circumstances, including any earlier course of dealing. You may not consider the parties’ unexpressed thoughts or intentions.
Answer “Yes” or “No” for each:
a. Relocate the three-phase line:
b. Supply electrical power via single-phase line:

The jury unanimously answered “Yes” to both l.a. and l.b. and concluded in a 10-2 vote that Oncor had breached the agreement by failing to timely comply with it. The jury also unanimously concluded that Oncor had trespassed on Giovanni Homes’s commercial lot, through which the three-phase line ran.

The jury awarded to Giovanni Homes over a million dollars in damages on the contract claim, including $189,611 for construction loan interest payments, and attorneys’ fees. It awarded to Giovanni *647 Homes $60,000 in damages on the trespass claim. Giovanni Homes elected to recover under its breach-of-contract theory, and Oncor sought a JNOV.

The trial court entered judgment in favor of Giovanni Homes except for recovery of the construction loan interest payments and awarded to Giovanni Homes $949,061 under its breach-of-contract theory, as well as prejudgment and postjudgment interest, attorneys’ fees, and costs; it denied Oncor’s JNOV motion except as to the construction loan interest payments. This appeal and cross-appeal followed.

III. Jurisdiction

In the initial briefing in this case, Oncor argued, among other things, that its tariff (the Tariff), which Giovanni Homes offered into evidence and which the trial court admitted, required Giovanni Homes to provide easements to Oncor and that those easements therefore could not be consideration to support the alleged agreement between the parties. Oncor further argued that the law “forbade Oncor from changing or ignoring the terms of the Tariff.”

Upon examining the Tariff and the utilities code, we discovered a potential jurisdictional issue requiring supplemental briefing and requested that each party file a brief to (1) address whether the Public Utility Commission of Texas (the PUC) 5 had exclusive jurisdiction over Giovanni Homes’s breach-of-contract claim and (2) explain the role of the Tariff and the filed-rate doctrine in light of the 1999 deregulation amendments to the Public Utility Regulatory Act. See City of Allen v. Pub. Util. Comm’n of Tex., 161 S.W.3d 195, 199 (Tex.App.-Austin 2005, no pet.) (stating that the question of jurisdiction is fundamental and can be raised at any time in the trial of a case or on appeal).

In its supplemental briefing, Oncor argued that the breach-of-contract claim directly related to Oncor’s provision of “Delivery Services” covered by the Tariff and that the PURA placed exclusive original jurisdiction over issues covered by the Tariff in the pertinent regulatory authorities, while Giovanni Homes countered that the contract was “a private, non-administrative, non-regulatory agreement that does not fall within the PURA’s stated purpose for enactment.” 6 Giovanni Homes contends that the Tariff does not govern its claims and so does not trigger the PURA’s exclusive jurisdiction provisions. We therefore review the PURA and the Tariff to determine whether Giovanni Homes’s contract claim falls within their purview.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
438 S.W.3d 644, 2014 WL 1320943, 2014 Tex. App. LEXIS 3596, Counsel Stack Legal Research, https://law.counselstack.com/opinion/oncor-electric-delivery-company-llc-v-giovanni-homes-corporation-texapp-2014.