OPINION

JAN P. PATTERSON, Justice.

In this appeal, we must decide whether the Public Utility Commission has jurisdiction under the Public Utilities Regulatory Act (PURA) to review certain ordinances *197 that a city claims to have enacted based on its police power. The City of Allen and a coalition of cities 1 appeal from a district court judgment partially dismissing the Cities’ appeal and partially affirming the Commission’s summary decision that invalidated four municipal ordinances because of their conflict with Oncor Electric Delivery Company’s 2 tariffs, PURA, and the Commission’s rules. For the reasons discussed below, we affirm the district court’s order.

BACKGROUND

In 1999, the legislature began dismantling Texas’s electric utility regulation. 3 The legislature revised PURA to allow determination of retail electric rates by competition. See City of Corpus Christi v. Public Util Comm’n, 51 S.W.3d 231, 235 (Tex.2001). Oncor is a transmission and distribution company created as part of TXU Electric Company’s unbundling 4 during the electricity deregulation process. Because electric transmission and distribution has not phased into the competitive market, the Commission continues to govern Oncor, including analysis and approval of Oncor’s tariff. See Tex. Util.Code Ann. § 39.201 (West Supp.2004-05); 16 Tex. Admin. Code § 25.214(c) (2004) (Public Util. Comm’n, Terms and Conditions of Retail Delivery Service Provided by Investor Owned Transmission and Distribution Utilities). Oncor is certificated to distribute electric service in Allen, Texas.

Allen is a home rule city under the Texas Constitution’s home rule amendment. Tex. Const. art. XI, § 5 (amended 1912). The home rule amendment altered the longstanding practice of having special charters individually granted and amended by the legislature for the State’s larger cities. City of San Antonio v. City of Boerne, 111 S.W.3d 22, 26 & n. 5 (Tex.2003). Cities adopting a home rule charter have the full power of self government and look to the legislature only for limitations on their power. Id. Beginning in 2000, Allen enacted “zoning development standards” in its land development code that required utilities to: (1) place certain electric distribution 5 lines underground, (2) screen electric meters and other electric distribution facilities from view, and (3) substitute metal or concrete distribution line poles for wooden poles—all at the *198 utility’s expense. 6 After enacting these ordinances, Allen denied two of Oncor’s construction permits for failure to comply with the electrical undergrounding specifications.

Oncor challenged the ordinances in an appeal to the Commission. The Commission’s preliminary order stated that the Commission had jurisdiction to consider Oncor’s appeal, and that Allen exceeded its authority when it passed the ordinances in question. The Commission referred the matter to the State Office of Administrative Hearings (SOAH), 7 to analyze the applicability of an analogous decision concerning the Commission’s jurisdiction to review municipal ordinances that required undergrounding utility lines and screening facilities. See Tex. Pub. Util. Comm’n, Application of Texas Utilities Electric Company to Obtain a CCN for the Trophy Club-Coppell-Euless 138 kV Transmission Line; Appeals of Brazos Electric Power Cooperative, Inc., Tri-County Electric Cooperative, Inc. and Texas Utilities Electric Company of an Ordinance of the Town of Westlake, Texas; Appeals of Texas Utilities Electric Company and Brazos Electric Power Cooperative, Inc. of an Ordinance of the Town of Trophy Club, Texas, Docket Nos. 6117, 6170-72; 1986 WL 383404, at *1-2, 1986 Tex. P.U.C. LEXIS 292, at *5.

While the case was before SOAH, the Commission’s staff moved for summary decision, arguing that there were not any issues of material fact to be resolved at the evidentiary hearing. In her proposal for decision, the administrative law judge recommended that the Commission issue a summary decision for Oncor and invalidate the ordinances as a matter of law, because the ordinances violated PURA and impaired the public interest by requiring that Oncor install non-standard facilities at its own expense.

After the administrative law judge released the proposal for decision — but before the Commission issued its order— Allen repealed the portions of the ordinances that required undergrounding lines and wooden pole replacement. 8 Applying exceptions to the mootness doctrine, 9 the Commission invalidated the sections of Allen’s ordinances that required under-grounding, wooden pole replacement, and screening of facilities, to the extent that they imposed the expense of installing non-standard electric distribution facilities on Oncor, in violation of its tariff, PURA, and Commission rules.

On administrative appeal, the district court ruled that it lacked jurisdiction to consider the Cities’moot challenge to the *199 Commission order invalidating the under-grounding and pole replacement provisions of the ordinances. The court partially dismissed the Cities’ appeal and ruled that the remainder of the Cities’ challenges lacked merit. 10

In a single point of error, the Cities challenge the Commission’s appellate jurisdiction over the ordinances in Allen’s land development code. They contend that Allen’s ordinances were not promulgated to regulate Oncor, but to protect the health, safety, and welfare of Allen’s citizens, that is, as an exercise of police power. The Cities ask this Court to “vacate the Commission order and reverse the district court’s order as to its finding of Commission jurisdiction.”

ANALYSIS

Motion to Dismiss

The Utilities and the Commission moved to dismiss this appeal, asserting that we cannot reach the question of the Commission’s jurisdiction over the under-grounding and pole replacement provisions in the ordinances without addressing the district court’s refusal to rule on them, and that the Cities waived this point of error due to inadequate briefing.

However, the question of jurisdiction is fundamental and can be raised at any time in the trial of a case or on appeal. Public Util. Comm’n v. J.M. Huber Corp.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Richardson v. Oncor Elec. Delivery Co.
539 S.W.3d 252 (Texas Supreme Court, 2018)
King v. Deutsche Bank National Trust Co.
472 S.W.3d 848 (Court of Appeals of Texas, 2015)
Entergy Corp. v. Jenkins
469 S.W.3d 330 (Court of Appeals of Texas, 2015)
Oncor Electric Delivery Company LLC v. Giovanni Homes Corporation
438 S.W.3d 644 (Court of Appeals of Texas, 2014)
Dallas Area Rapid Transit v. Oncor Electric Delivery Co.
331 S.W.3d 91 (Court of Appeals of Texas, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
161 S.W.3d 195, 2005 Tex. App. LEXIS 1990, 2005 WL 607697, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-allen-v-public-utility-commission-texapp-2005.