Southwestern Electric Power Company v. Public Utility Commission of Texas

419 S.W.3d 414, 2011 WL 5299490, 2011 Tex. App. LEXIS 8848
CourtCourt of Appeals of Texas
DecidedNovember 4, 2011
Docket07-10-00108-CV
StatusPublished
Cited by4 cases

This text of 419 S.W.3d 414 (Southwestern Electric Power Company v. Public Utility Commission of Texas) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southwestern Electric Power Company v. Public Utility Commission of Texas, 419 S.W.3d 414, 2011 WL 5299490, 2011 Tex. App. LEXIS 8848 (Tex. Ct. App. 2011).

Opinion

OPINION

MACKEY K. HANCOCK, Justice.

Southwestern Electric Power Company (SWEPCO) and Texas Industrial Energy Consumers (TIEC) appeal from the trial court’s judgment affirming an order of the Public Utility Commission of Texas (the PUC) granting a certifícate of convenience and necessity (CCN) to SWEPCO. We will affirm.

Factual and Procedural History

The PUC Order

On August 12, 2008, the PUC entered an order with which nearly all concerned parties were dissatisfied. By a 2-1 vote, the PUC granted SWEPCO an amendment to its existing CCN permitting SWEPCO to build a coal-fired ultra-supercritical generating plant, referred to as the Turk plant, a few miles northeast of Texarkana, in Arkansas. The PUC granted the amendment subject to specified conditions and caps on the future recovery of yet-to-be-incurred costs.

The Turk plant is planned as a generation facility that will serve both SWEP-CO’s retail and wholesale customers in three states. Because SWEPCO intends to serve captive retail customers in Texas, it was required to seek a CCN from the PUC. See 16 Tex. Admin. Code § 25.101(b)(2) (2011) (Pub. Util. Comm’n of Tex., Certification Criteria). In this context, SWEPCO is a hybrid entity — an electric utility monopoly obligated to serve captive Texas ratepayers in certain areas of the state and a power generation company competing in the multistate wholesale market.

Litigation in the Trial Court

SWEPCO was displeased with the cost caps and, therefore, sought judicial review of their legality. TIEC sought judicial review contesting the PUC’s determination of the necessity of the Turk plant. The two cases were consolidated. In the trial court, SWEPCO unsuccessfully contested the PUC’s authority to impose the two caps at issue. Equally unsuccessful, TIEC argued that the PUC improperly considered SWEPCO’s wholesale load in determining the need for the Turk plant.

Just before the hearing in the trial court, SWEPCO filed a letter questioning whether its own issues relating to the cost caps were ripe for judicial review. SWEP-CO pointed out that any effect from the caps would be felt only if (1) the plant was built and used to serve retail customers, (2) its prudent costs exceeded the cap and/or yet-to-be-passed legislation resulted in carbon containment costs in excess of the cap, and (3) the then-current PUC in *417 some future rate case determined to follow the cost cap provisions. So, SWEPCO argued to the trial court, the issues might not be ripe and it might be asking the trial court to enter an unconstitutional advisory opinion.

The trial court suggested SWEPCO file a nonsuit in the case if it maintained that subject-matter jurisdiction was lacking. SWEPCO declined, and the trial court concluded that it did have subject-matter jurisdiction. The trial court affirmed the PUC order in all respects by judgment signed February 10, 2010. 1 This appeal followed and was originally filed in the Third Court of Appeals but, pursuant to the Texas Supreme Court’s docket equalization efforts, was transferred to this Court. See Tex. Gov’t Code Ann. § 73.001 (West 2005).

Appeal

SWEPCO’s appeal stems from its request for a CCN amendment from the PUC, required when a utility in a still-regulated portion of the State provides service to a captive retail customer base. The PUC granted SWEPCO’s CCN but did so with conditions the imposition of which, SWEPCO contends, was beyond the PUC’s authority. TIEC appeals the same order, contending that the PUC did not have the authority to enter the order based on consideration of SWEPCO’s wholesale load rather than solely on the capacity to serve captive retail, customers. The PUC maintains that it has broad regulatory authority, broad enough to authorize it to grant the CCN amendment and to do so with the particular restrictions, especially in light of the complex transition-to-full-deregulation climate and considering that SWEPCO is a hybrid entity serving captive retail customers and competing in the wholesale market.

With that said, we must consider the following issues: (1) whether the PUC had the authority to consider SWEPCO’s wholesale load in determining whether to grant the CCN and, if so, (2) whether the PUC had the authority to impose caps on what costs SWEPCO could recoup through rates applicable to captive Texas ratepayers. As a preliminary matter, though, we must decide (3) whether the issues concerning imposition of the cost caps are ripe for judicial review.

Ripeness

SWEPCO raises this issue, contending, as it did below, that the issue concerning the cost caps may not yet be ripe for review. 2 We address the issue of this Court’s subject-matter jurisdiction first because, if we do lack jurisdiction to review the matter, review of the cost caps issue *418 would be precluded. See Patterson v. Planned Parenthood of Houston & Se. Tex., Inc., 971 S.W.2d 439, 442 (Tex.1998); Garrett Operators, Inc. v. City of Houston, 360 S.W.3d 36, 41 (Tex.App.-Houston [1st Dist.] 2011, pet. filed).

SWEPCO contends that the contingencies built into the cost caps render the issues concerning the caps unripe. SWEPCO first points out that it has not sustained a concrete injury as a result of the cost caps. By its own admission, the construction cost estimates at the time of briefing was in excess by four percent of the caps, but, as it emphasized, those figures are simply estimates. Then, with respect to the cost caps relating to carbon dioxide emission control, SWEPCO contends that Congress has yet to pass federal legislation to govern this aspect of the plant’s operation and, therefore, no one can determine the costs of compliance or, consequently, whether the cost caps would negatively impact SWEPCO. SWEPCO relies on the doctrine of ripeness along with notions of judicial restraint to urge this Court to refrain from addressing the cost caps issue until such time that the negative impact of the cost caps, if any, are felt by SWEPCO.

Standard and Scope of Review

As an element of subject-matter jurisdiction, ripeness is reviewed de novo. See State v. Holland, 221 S.W.3d 639, 642 (Tex.2007). The Texas Supreme Court has directed that we review all available information, including intervening events after a lower court’s decision. 3 Perry v. Del Rio, 66 S.W.3d 239, 250 (Tex.2001).

Applicable Law: Ripeness and Finality

In the context of review of an agency order, the issues of ripeness and of finality of the agency order are very nearly inextricably intertwined in the cases addressing them.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
419 S.W.3d 414, 2011 WL 5299490, 2011 Tex. App. LEXIS 8848, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southwestern-electric-power-company-v-public-utility-commission-of-texas-texapp-2011.