This text of 258 S.W.3d 272 (AEP Texas Central Co. v. Public Utility Commission of Texas) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
AEP Texas Central Co. v. Public Utility Commission of Texas, 258 S.W.3d 272, 2008 WL 2544895 (Tex. Ct. App. 2008).

Opinions

OPINION

PER CURIAM.

We withdraw the opinion, concurring and dissenting opinion, concurring opinion and judgment issued May 23, 2008, and substitute the following in their place. We overrule the appellants’ motion for rehearing.1

This appeal arises from the final order of the Public Utility Commission in the true-up proceeding to finalize “stranded costs” and other true-up balances for the AEP Texas Central Company and CPL Retail Energy, L.P. (collectively “TCC”) as a result of the legislative mandate to bring [276]*276competition to the retail energy market in Texas. The district court affirmed the Commission’s final order in most respects, but reversed on three issues. This Court affirms the district court’s judgment in part, reverses in part, and remands this cause to the Commission for further proceedings consistent with the Court’s opinions.

Justice Patterson filed a concurring and dissenting opinion, joined by Justices Pur-year and Pemberton in part. Justice Pem-berton filed a concurring opinion, joined by Justice Puryear.

For the reasons expressed in Justice Patterson’s opinion, the Court affirms the district court’s judgment, except that the Court reverses the district court’s judgment that: (1) the Commission erred in excluding the testimony and expert report of Ross A. Sollosy; (2) the Commission erred in using the interest rate specified in PUC Rule 25.263(Z )(3); (3) the Commission properly refused to consider the potential normalization violation resulting from its treatment of the amounts held in TCC’s federal tax accounts for Accumulated Deferred Investment Tax Credits (AD-ITC) and Excess Deferred Federal Income Tax (EDFIT); and (4) the Commission properly accounted for the excess mitigation credits and interest paid by TCC.

For the reasons expressed in Justice Pemberton’s opinion, the Court affirms the district court’s judgment that section 39.252(d) of the Public Utility Regulatory Act precludes the Commission from adjusting the net book value of TCC’s generation assets where the Commission has found that TCC has disposed of those assets in a bona fide third-party transaction under a competitive offering as required in section 39.262(h). Accordingly, the Court does not reach the question of whether the Commission’s adjustments to the net book values of TCC’s share in the South Texas Nuclear Project and the Coleto Creek Coal Plant for “commercial unreasonableness” were supported by substantial evidence. The Court also affirms the district court’s judgment affirming the Commission’s refusal to make book-value adjustments based on the failure to employ bridge power sales agreements.

Justice Patterson dissents from the majority’s conclusion that section 39.252(d) precludes the Commission’s adjustments to the net book value of TCC’s generation assets for “commercial unreasonableness” related to TCC’s sales of the South Texas Nuclear Project and the Coleto Creek Coal Plant to the extent TCC’s commercially unreasonable behavior benefitted the utility and was not captured in the market valuation of TCC’s generation assets.

Concurring and Dissenting Opinion by Justice PATTERSON, joined in part by Justices PURYEAR and PEMBERTON.

Concurring Opinion by Justice PEMBERTON, joined by Justice PURYEAR.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
258 S.W.3d 272, 2008 WL 2544895, Counsel Stack Legal Research, https://law.counselstack.com/opinion/aep-texas-central-co-v-public-utility-commission-of-texas-texapp-2008.