Lamb County Electric Cooperative, Inc. v. Public Utility Commission

269 S.W.3d 260, 2008 Tex. App. LEXIS 8381, 2008 WL 4823179
CourtCourt of Appeals of Texas
DecidedNovember 7, 2008
Docket03-04-00593-CV
StatusPublished
Cited by3 cases

This text of 269 S.W.3d 260 (Lamb County Electric Cooperative, Inc. v. Public Utility Commission) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lamb County Electric Cooperative, Inc. v. Public Utility Commission, 269 S.W.3d 260, 2008 Tex. App. LEXIS 8381, 2008 WL 4823179 (Tex. Ct. App. 2008).

Opinions

OPINION

DAVID PURYEAR, Justice.

Lamb County Electric Cooperative (the “Cooperative”) asserted to the Public Utility Commission (the “Commission”) that Southwestern Public Service Company (“Southwestern”) had exceeded the scope of its certificates of convenience and necessity and was improperly providing electricity to customers inside the Cooperative’s service area. The Commission referred the matter to the State Office of Administrative Hearings for a contested-case hearing before an administrative law judge. The judge concluded that the service Southwestern was providing was consistent with its certificates. The Commission adopted the judge’s proposal in its final order. The Cooperative appealed the order of the Commission, and the district court affirmed the Commission’s order. The Cooperative appeals the district court’s judgment, and we will affirm the judgment of the district court.

BACKGROUND

This appeal has a complex and lengthy procedural history originating in the 1970s. To facilitate the discussion of the issues raised in this appeal, we will provide a brief summary of the procedural history of this case and of various changes that occurred in the energy market in the 1970s.

Prior to 1975, utilities were allowed to choose the areas and customers that they wanted to provide service to, which meant that more than one utility might be providing service to the same general area.1 However, the manner in which a utility’s customers were selected was significantly altered as a result of the passage of the Public Utility Regulatory Act and the formation of the Commission in 1975. See Act of June 2, 1975, 64th Leg., R.S., ch. 721, 1975 Tex. Gen. Laws 2327, 2327-52 (current version at Tex. Util.Code Ann. §§ 11.001-64.158 (West 2007 & Supp. 2008)). The Act created a new regulatory scheme for public utilities, under which the Commission began licensing utilities to serve power to a particular area. See Lamb County Elec. Coop. v. Public Util. Comm’n of Tex., No. 03-00-00113-CV, [265]*2652001 WL 28142, at *1, 2001 Tex.App. LEXIS 173, at *2 (Tex.App.-Austin Jan.ll, 2001, no pet.) (not designated for publication). In other words, generally speaking, a single utility was given the authority to provide all of the electricity to customers located inside a specific geographical region. This region was called a service area.

To become a designated provider, utilities were required to apply for and obtain a certificate of convenience and necessity from the Commission. Id.; see also Tex. Util.Code Ann. § 37.051 (West 2007) (requiring utility to obtain permit before directly or indirectly providing service to public).2 That meant that electricity providers that desired to continue providing service to an area they had been serving had to apply to the Commission for a certificate.

To make approving the applications and establishing the service areas more efficient, the Commission consolidated the cases so that applications for neighboring service areas were considered in the same docket. Because a utility might request a service area that was too large to consider in one docket, it was possible that a utility might be a party to more than one docket. During the dockets, the boundaries for the neighboring service areas were established, and the boundaries were often reflected in certification maps submitted by utilities. Once the service areas were established, utilities were prohibited from interfering with the operations of another utility by providing service within that util-tty’s service area. See Tex. Util.Code Ann. § 37.156 (West 2007) (fisting actions Commission may take if utility interferes with operations of another utility).

As discussed previously, prior to the passage of the Act, it was not uncommon for more than one utility to provide service to the same general area. Because the Commission was effectively dividing the State into distinct service areas, it was possible that the boundaries established by the Commission might effectively prohibit a utility from continuing to provide service to some of its previous customers if the Commission placed those customers inside another utility’s service area. This would effectively strand a utility’s power fines within the service area of another utility and deprive the stranded utility of any economic benefit from having installed the power fines.

To ameliorate this potentially inequitable result, the legislature and the Commission established several remedies. For example, the legislature enacted section 37.155 of the utilities code, which allowed utilities to enter into agreements specifying the areas and customers to be served by each utility. Id. § 37.155 (West 2007); see also Public Utils. Bd. v. Cent. Power & Light Co., 587 S.W.2d 782, 784 (Tex.Civ.App.-Corpus Christi 1979, writ ref'd n.r.e.) (describing how after passage of Act, Commission required utilities to enter into negotiations regarding their service areas under regulation). Further, section 37.155 provided that those types of agreements are “valid and enforceable” and “shall be [266]*266incorporated into the appropriate areas of certification” as long as the Commission approves the agreements. Tex. UtiLCode Ann. § 87.155. In other words, rather than limiting their service areas to distinct regions, the utilities were allowed to negotiate their own arrangements regarding the areas and customers that each utility could serve. If the utilities were able to reach agreements and if the Commission approved the agreements, the agreements established the service areas for the utilities.

The Commission also provided an additional remedy when it promulgated the corridor rule. See Commission Rule 052.02.05.056(b)(6)(B) (1976) (current version at 16 Tex. Admin. Code § 25.101(e)(1)-(3) (2008)). The corridor rule specifically applied to situations in which the boundaries created in the certification dockets stranded a utility’s preexisting distribution line inside another utility’s newly designated service area. Essentially, the rule allowed a utility to continue providing limited service through the stranded line. Id. Under the rule, a utility was given a certification for a 400-foot wide corridor (200 feet on either side of the line) within which the stranded utility was allowed to provide service to customers inside another utility’s service area. Id. The authorization given under the rule essentially constituted a type of dual certification allowing a particular service area to be served by more than one utility. The rule automatically applied to all certification dockets unless the Commission provided otherwise.3

Prior to the passage of the Act, it was common for investor-owned utilities to only provide service to the more population-dense portions of a county, while electric cooperatives, which were owned by the customers that they served, provided electricity to the areas of a county, generally the rural regions, that were less economically appealing to the investor-owned utilities.

The dichotomy in service slowly eroded over time, and investor-owned utilities began providing service to more rural regions.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
269 S.W.3d 260, 2008 Tex. App. LEXIS 8381, 2008 WL 4823179, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lamb-county-electric-cooperative-inc-v-public-utility-commission-texapp-2008.