Nova Casualty Co. v. United States

72 Fed. Cl. 755, 2006 U.S. Claims LEXIS 298, 2006 WL 2846424
United States Court of Federal Claims·Decided October 5, 2006·No. No. 04-1665C·Published·Cited by 1 cases

Opinion

OPINION AND ORDER

LETTOW, Judge.

This surety case is before the court for decision on facts stipulated by the parties. The United States Coast Guard (“Coast Guard”) and Eagle Management Enterprises, Inc. (“Eagle”) entered into a contract for the renovation of the Coney Island Light Tower in Brooklyn, New York. As a condition of the contract, Eagle obtained from plaintiff, Nova Casualty Company (“Nova”), performance and payment bonds for the benefit of the United States as obligee. As a result of alleged defaults on the part of Eagle respecting performance of the work and payment of its subcontractors, both the performance and payment bonds were invoked against Nova.

In its Amended Complaint, Nova sought to contest Eagle’s obligations to the Coast Guard under the primary contract and to recover the contract balance the Coast Guard allegedly should have retained. The government moved to dismiss for lack of subject matter jurisdiction and for failure to state a claim under Rules 12(b)(1) and 12(b)(6) of the Rules of the Court of Federal Claims (“RCFC”). On January 12, 2006, this court issued an opinion and order granting in part and denying in part the government’s motions. Nova Cas. Co. v. United States, 69 Fed.Cl. 284, 292 (2006). Taking into account Nova’s failure to act under the performance bond to undertake the work Eagle allegedly had not properly completed, this court granted the government’s motion pursuant to RCFC 12(b)(1) to dismiss as beyond the court’s subject matter jurisdiction Nova’s contest of the contracting officer’s decision regarding Eagle’s default. Specifically, this court found that because Nova was not a “contractor” under the Contract Disputes Act, Pub.L. No. 95-563, 92 Stat. 2383 (1978) (codified at 41 U.S.C. §§ 601-613), its claim appealing the contracting officer’s final decision did not fall under the grant to this court in that Act of jurisdiction to hear certain contractually related claims. Nova Cas., 69 Fed.Cl. at 289-92. Respecting the payment bond, this court denied the government’s motions to dismiss Nova’s claim based on equitable subrogation arising under the bond, concluding that Nova had stated a valid claim under the Tucker Act, 28 U.S.C. § 1491(a)(1). Nova Cas., 69 Fed.Cl. at 292-94. Having paid all outstanding claims of subcontractors under its payment bond with Eagle, Nova could invoke the Tucker Act as a jurisdictional predicate for a suit against the government because Nova stood in the shoes of Eagle for that purpose. Id. at 293-94. Thus, the court had subject matter jurisdiction to consider the merits of Nova’s claim to the amount that allegedly “should have remained in the contract retainage had the government not improperly paid the contractor in July 2003.” Id. at 299.

Thereafter, the parties agreed to resolve disputed issues of fact by way of a stipulation and to submit cross-motions for judgment predicated upon the stipulation. See Order of Apr. 24, 2006. The parties filed their Joint Stipulation of Material Facts (“Stip.”) on May 19, 2006, and their cross-motions for judgment on June 30, 2006. Responses were filed by the government on July 28, 2006, and by Nova on July 31, 2006. The parties waived a hearing on the cross-motions and, in effect, the case has proceeded as a trial on stipulated facts.

For the reasons stated below, plaintiff’s motion for judgment on stipulated facts is granted and defendant’s motion for judgment on stipulated facts is denied.

FACTS

On September 6, 2001, the Coast Guard and Eagle entered into Contract No. DTCGG [758]*7581-01-C-3WK143, requiring Eagle to remove lead paint from, and to prepare and paint, all exterior and interior surfaces of the Coney Island Light Tower, and to make other minor repairs to the light tower’s exterior in exchange for payment of $138,000. Stip. ¶¶ 1, 2. As a condition of the contract and pursuant to the Miller Act, Pub.L. No. 74-321, § 1, 49 Stat. 793 (codified at 40 U.S.C. § 3131(b)) (formerly codified as 40 U.S.C. § 270a(a)), Eagle obtained performance and payment bonds, designated as Bonds No. 18271, from Nova in the amount of $138,000, each for the benefit of the United States as obligee. Stip. ¶ 3. In addition, under an earlier General Agreement of Indemnity, Eagle agreed, in the case of its breach or default under any contract for which Nova issued its bonds, to assign its rights under such a contract to Nova and to allow Nova to be “subrogated to all the rights and properties of [Eagle] in such contract.” Plaintiffs Opposition to Defendant’s Motion to Dismiss (“Pl.’s Opp.”) Ex. B (General Agreement of Indemnity (Dec. 27, 2000)).

Eagle commenced work on the light tower in September 2002, and based on invoices submitted in June, September, and November of 2002, the Coast Guard disbursed to Eagle three partial payments of $32,070, $28,500, and $37,450 for work performed under the contract. Stip. ¶¶ 10-14. On January 14, 2003, Mr. John O’Boyle, the Coast Guard Contracting Officer, advised Eagle that “the exterior painting work ha[d] been completed satisfactorily and [Eagle could] proceed with the removal of the scaffolding,” although “interior work and outside concrete work [wa]s still outstanding.” Stip. ¶ 18 (quoting Letter from John O’Boyle, Contracting Officer, Coast Guard, to Eagle (Jan. 14, 2003)).

Eagle had entered into two subcontracts with Metron Environmental Limited (“Me-tron”) and Harsco Corporation (“Harsco”) to perform work on the contract. Stip. ¶7. Late in 2002 and early in 2003, first Harsco and then Metron gave notice to the Coast Guard, Eagle, and Nova that Eagle had not paid those subcontractors for work they had completed on the project. Stip. ¶¶ 15, 20. In each instance, Eagle had applied for the pertinent progress amounts under the contract, certifying that “timely payments will be made from the proceeds of the payment covered by this certification in accordance with subcontracted agreements and the requirements of chapter 39 of Title 31, United States Code.” Stip. ¶¶ 9,11.

In response to Eagle’s invoice of June 9, 2003 requesting a fourth partial payment under the contract, Mr. O’Boyle forwarded to the Coast Guard Finance Center (“Finance Center”) a “Coast Guard Contract Payment Approval” form, approving a $25,303.50 payment to Eagle. Stip. ¶¶ 24, 26. Mr. O’Boyle noted on the form that the Coast Guard would retain $10,676.50 because of overbilling, incomplete work, and late performance. Stip. ¶ 26. Subsequently, during a site visit on June 20, 2003, Mr. O’Boyle noticed “blotches” on the exterior of the light tower, instead of a “solid white color,” and advised Eagle’s on-site representative of deficiencies in the painting. Stip. ¶27. Mr. O’Boyle notified Eagle in writing that he expected the contractor to “cure the[se] defects,” providing a copy of the letter to Nova. Stip. ¶ 28.

In a further letter dated June 27, 2003, Mr. O’Boyle advised Eagle that due to the defective painting, the Coast Guard would reduce its payment on the fourth invoice to $9,303.50. Stip. ¶ 29. That same day Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Nova Casualty Co. v. United States, 72 Fed. Cl. 755, 2006 U.S. Claims LEXIS 298, 2006 WL 2846424 (uscfc 2006).

72 Fed. Cl. 755 (Nova Casualty Co. v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related