McDevitt & Street Co. v. K-C Air Conditioning Service, Inc.

418 S.E.2d 87, 203 Ga. App. 640, 92 Fulton County D. Rep. 44, 1992 Ga. App. LEXIS 589
CourtCourt of Appeals of Georgia
DecidedMarch 18, 1992
DocketA91A1955
StatusPublished
Cited by23 cases

This text of 418 S.E.2d 87 (McDevitt & Street Co. v. K-C Air Conditioning Service, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McDevitt & Street Co. v. K-C Air Conditioning Service, Inc., 418 S.E.2d 87, 203 Ga. App. 640, 92 Fulton County D. Rep. 44, 1992 Ga. App. LEXIS 589 (Ga. Ct. App. 1992).

Opinion

Beasley, Judge.

Plaintiff McDevitt & Street Company sued defendants K-C Air Conditioning Service, Inc., and its surety, Employers Insurance of Wausau, to recover damages allegedly sustained as the result of the breach of a construction subcontract. Plaintiff appeals a judgment entered on a jury verdict in favor of defendants.

On February 26, 1985, plaintiff as general contractor and K-C as subcontractor entered into a written agreement (the subcontract) for the design, purchase and installation of a waste water riser system in an Embassy Suites Hotel. The agreement provided that “[t] he work shall be performed by subcontractor in a good and workmanlike manner strictly in accordance with the Contract Documents. . . .” It further contained a guarantee whereby “Subcontractor warrants and guarantees the Work to the full extent provided for in the Contract Documents. Without limiting the foregoing or any other liability or obligation with respect to the Work, Subcontractor shall, at its expense and by reason of its express warranty, make good any faulty, defective, or improper parts of the Work discovered within one year from the date of acceptance of the project by the Architect and Owner or within such longer period as may be provided in the Contract Documents.”

Specified as a “Contract Document” and specifically incorporated into the agreement, was an American Institute of Architects (AIA) contract A201, 1976 Edition as amended by Supplementary Conditions. In an article of that AIA contract pertaining to subcontractors, it was specified that “the Contractor shall require each Subcontractor, to the extent of the Work to be performed by the Subcontractor, to be bound to the Contractor by the terms of the Contract Documents, and to assume toward the Contractor all the obligations and responsibilities which the Contractor by these documents assumes toward the Owner and the Architect.” Pursuant to that AIA agreement, the Contractor warranted to the Owner that “[a] 11 Work will be of good quality, free from faults and defects and in conformance with the Con *641 tract Documents. All Work not conforming to these requirements . . . may be considered defective. . . . This warranty is not limited by the provisions of Paragraph 13.2.” Paragraph 13.2.2 related to “correction of work” and required that if within “one year after acceptance by Owner ... or within such longer period of time as may be prescribed by law . . . any of the Work is found to be defective or not in accordance with contract documents, the contractor shall correct it promptly after receipt of written notice to do so” unless Owner has “given a written acceptance of such condition. This obligation shall survive termination of the contract.”

The subcontract further required K-C as subcontractor to furnish “a performance bond ... in an amount equal to the [contract] Price [$1,564,500.] . . . with surety or sureties satisfactory to Contractor.” In compliance with that requirement, K-C posted a “subcontractor performance bond” with defendant Wausau. The bond was to remain in full force and effect, obligating Wausau as surety, until such time as “[K-C] shall well and truly perform all the undertakings . . . and conditions and agreements of [the] subcontract within the time provided therein . . . and during the life of any guaranty required under [the] subcontract, . . . and shall indemnify and save harmless [plaintiff] of . . . any loss, damage, and expense, including costs and attorney’s fees, which [plaintiff] may sustain by reason of failure to do so. . . .”

Embassy Suites opened for business in December of 1985. In early February of 1988, plaintiff received complaints about ten random leaks that were occurring in the plumbing risers in the hotel. On four or five different occasions ceiling tiles fell and raw sewage leaked from the guest rooms into the restaurant and meeting rooms below. On each occasion, a guest suite was out of service for three days. Such leaks were occurring randomly throughout the system with more frequency, at a rate of approximately one a week.

By letter dated February 4, 1988, Plaintiff provided both Subcontractor and Wausau with “formal notice of a claim against the . . . subcontract,” due to “mechanical connections [which] have failed throughout the building,” resulting in “damage caused by [ ] sewage flowing from the failed joints,” and requested that Wausau assign an adjustor to investigate before “we start the repairs to the mechanical system.” Wausau acknowledged receipt of plaintiff’s February 4 letter, and although it responded that it would investigate the problem with its principal, plaintiff received no confirmation that such an investigation had been conducted.

Plaintiff arranged a meeting on February 5 to review the problem with all those involved. Representatives of K-C were present, but Wausau declined to be represented. A decision was made to randomly open certain wall cavities to assess the problem. Upon doing so, it *642 became apparent that segments of pipe throughout the system had been improperly bonded. It was thought that the defect could potentially result in future leaks.

That information was presented at a second meeting which was held on February 8. It was agreed upon that a system-wide failure had occurred and a “decision was made to replace all the proset sleeves because no one was comfortable with the fact that [they] wouldn’t be back doing patch jobs again, again and again.”

Analysis of the couplings removed from the building revealed an adhesive failure due to contaminated cement that was used at the joints. This resulted in a system with a propensity to leak. Approximately 85-95 percent of the couplings examined were affected in that manner. K-C had installed at least 2,200 couplings of a similar nature in the hotel.

Although plaintiff offered K-C the opportunity to correct the problem, it declined. Plaintiff paid another subcontractor $151,986.97 to perform the repair.

Plaintiff informed Wausau that it would negotiate a settlement of the claim with Embassy Suites. It later sent K-C an itemized invoice reflecting payments totaling $338,594.57 it had expended for repairs and losses to the owner. Plaintiff sought reimbursement for those expenses from both K-C and Wausau under the performance bond. Both denied liability.

Plaintiff filed the present multi-count complaint seeking actual damages against K-C for negligence, breach of contract, breach of express and implied warranties, and expenses of litigation resulting from its alleged bad faith refusal to pay the claim. The complaint further alleged joint and several liability on the part of Wausau for K-C’s failure to perform. It sought actual damages, a 25 percent bad faith penalty and attorney fees from the surety.

1. Although plaintiff contends that it was entitled to a directed verdict in its favor as a matter of law, no such motion was presented below. It cannot now be made the basis for appellate review. See generally Fidelity &c. Ins. Co. v. Massey, 162 Ga. App. 249 (1) (291 SE2d 97) (1982). Appellant cites Denny v. D. J. D., Inc., 188 Ga. App. 431 (373 SE2d 383) (1988), as authority for its position, but in that case the plaintiff had raised the issue before the trial court in a motion for new trial, and it was the denial of that motion which was reviewable. There was no such motion in this case.

2.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Joe Rogers, Jr. v. Hylton B. Dupree
Court of Appeals of Georgia, 2017
Rogers v. Dupree
799 S.E.2d 1 (Court of Appeals of Georgia, 2017)
Rtt Associates, Inc. v. Georgia Department of Labor
775 S.E.2d 644 (Court of Appeals of Georgia, 2015)
Greene v. Bryant
626 S.E.2d 185 (Court of Appeals of Georgia, 2006)
Rental Equipment Group, LLC v. MACI, LLC
587 S.E.2d 364 (Court of Appeals of Georgia, 2003)
American Manufacturers v. Tison Hog
182 F.3d 1284 (Eleventh Circuit, 1999)
R. J. Griffin & Co. v. Continental Insurance
497 S.E.2d 586 (Court of Appeals of Georgia, 1998)
Dent v. Memorial Hospital of Adel, Inc.
490 S.E.2d 509 (Court of Appeals of Georgia, 1997)
Department of Transportation v. Dalton Paving & Construction, Inc.
489 S.E.2d 329 (Court of Appeals of Georgia, 1997)
Korte Construction Co. v. Deaconess Manor Ass'n
927 S.W.2d 395 (Missouri Court of Appeals, 1996)
Signsation, Inc. v. Harper
460 S.E.2d 854 (Court of Appeals of Georgia, 1995)
Armstrong Transfer & Storage Co., Inc. v. Mann Const., Inc.
458 S.E.2d 481 (Court of Appeals of Georgia, 1995)
First Union National Bank v. Davies-Elliott, Inc.
452 S.E.2d 132 (Court of Appeals of Georgia, 1994)
Food Lion, Inc. v. Johnson
448 S.E.2d 59 (Court of Appeals of Georgia, 1994)
Webster v. Brown
446 S.E.2d 522 (Court of Appeals of Georgia, 1994)
Blankenship v. West Georgia Plumbing Supply, Inc.
444 S.E.2d 596 (Court of Appeals of Georgia, 1994)
Blum v. Res Associates Ltd.
439 S.E.2d 712 (Court of Appeals of Georgia, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
418 S.E.2d 87, 203 Ga. App. 640, 92 Fulton County D. Rep. 44, 1992 Ga. App. LEXIS 589, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcdevitt-street-co-v-k-c-air-conditioning-service-inc-gactapp-1992.