R. J. Griffin & Co. v. Continental Insurance

497 S.E.2d 586, 230 Ga. App. 822, 98 Fulton County D. Rep. 830, 1998 Ga. App. LEXIS 219
CourtCourt of Appeals of Georgia
DecidedFebruary 12, 1998
DocketA97A1765
StatusPublished
Cited by7 cases

This text of 497 S.E.2d 586 (R. J. Griffin & Co. v. Continental Insurance) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
R. J. Griffin & Co. v. Continental Insurance, 497 S.E.2d 586, 230 Ga. App. 822, 98 Fulton County D. Rep. 830, 1998 Ga. App. LEXIS 219 (Ga. Ct. App. 1998).

Opinion

Smith, Judge.

This is an appeal of the grant of summary judgment in favor of the surety on a construction performance bond and the corresponding denial of summary judgment for the general contractor obligee. We must decide whether a subcontractor’s refusal to return funds belonging to the general contractor is covered by the subcontractor’s performance bond issued in favor of the general contractor. Under the plain language of the subcontract and the bond, as well as the final waiver and release executed by the surety, we conclude that the subcontractor’s wrongful retention of funds is a breach of the subcontract and covered under the terms of the bond. The trial court therefore erred in granting summary judgment to the surety and in denying summary judgment to the obligee.

The facts underlying this litigation are not in dispute. 1 R. J. Griffin & Company was the general contractor on a hospital project in Tampa, Florida. Griffin hired Doyle Electric Services, Inc. as a subcontractor, and the terms of the subcontract required Doyle to furnish a performance bond. Doyle obtained a performance bond *823 from Continental Insurance Company. At the end of the project, Doyle and Continental both executed a separate final waiver and release of claims.

Doyle performed not only the contract work but a significant amount of additional work on change orders, including the installation of a generator. Doyle was paid twice for the generator work as the result of a clerical error and refused to return the overpayment. While the trial court agreed that Doyle had an equitable obligation to return the double payment, it concluded that Continental’s performance bond did not cover Doyle’s refusal to return the money. The trial court therefore denied summary judgment to Griffin while granting summary judgment to Continental. From this ruling Griffin appeals.

In determining the scope of coverage of the performance bond at issue here, we must follow the applicable rules of construction. In contrast to the general rule that policies of insurance are construed strictly against the insurer, the obligation of a surety is construed strictly in the surety’s favor. Arnold v. Indcon, L.P., 219 Ga. App. 813 (1) (466 SE2d 684) (1996); Johns v. Leaseway of Ga., 166 Ga. App. 472 (304 SE2d 555) (1983). But it is also true that no construction of a surety’s bond is “required or even permissible when the language employed by the parties in the contract is plain, unambiguous and capable of only one reasonable interpretation.” (Citation and punctuation omitted.) Id. at 472-473.

Turning to the surety bond itself, we note that the parties to the bond are Griffin (obligee), Doyle (principal) and Continental (surety). The bond obligates the surety “to perform fully and complete the work mentioned and described in said subcontract and any and all modifications thereof pursuant to and in accordance with the undertakings, covenants, terms, conditions and agreements thereof, if the principal fails ... to so perform fully and complete said work.” The question presented is whether the obligation to “perform fully” includes the obligation to cure all breaches of the subcontract, not just the physical completion of the work. Under the plain language of the bond, we find that it does. The surety’s contract is not limited to physical “work” — the contract obligates it to “perform fully” as well as “complete the work ... in accordance with the undertakings, covenants, terms, conditions and agreements.”

This is in accord with our decision in McDevitt & Street Co. v. K-C Air Conditioning Svc., 203 Ga. App. 640 (418 SE2d 87) (1992). In that case, Employers Insurance of Wausau issued a performance bond for a plumbing subcontractor. Wausau attempted to escape liability on the ground that the subcontractor had completed the work on the project, although that work later proved defective outside the period of the warranty provided by the subcontract. This Court *824 rejected a limitation of the surety’s liability to mere completion of the physical work, observing: “ ‘Sureties . . . are jointly and severally liable with their principal unless the contract provides otherwise.’ OCGA § 10-7-1. Since Wausau’s obligation under the bond remained in full force and effect until K-C’s obligations under the subcontract were terminated, and there was evidence that K-C did not ‘well and truly perform’ within the statute of limitation, the trial court erred in directing a verdict in Wausau’s favor.” Id. at 645 (6).

Here, Continental’s suretyship contract binds it to complete the work in accordance with the subcontract, and the subcontract itself provides that “subcontractor’s guarantors, surety, or sureties agree to be bound to contractor with respect to such remedies notwithstanding any provision of the bonds provided.”

Under the subcontract, Doyle agreed “to perform and furnish, all labor, supervision, services, material, equipment, tools, scaffolds, transportation and all other things necessary to complete the work described in Exhibit ‘A,’ in accordance with the following standard terms and conditions.” Among those terms and conditions, Doyle agreed to hold in trust for its subcontractors, suppliers, and material-men all payments made by Griffin, to reimburse Griffin for back-charges, and to protect Griffin from possible consequences of any other breach or default. Finally, Doyle agreed that if it should “fail in the performance or the observance of any of the covenants, conditions or other terms of this subcontract, then . . . contractor shall . . . have the right to exercise any one or more of” certain enumerated remedies. Griffin’s remedies under the subcontract were “cumulative and shall be in addition to every remedy given hereunder or under the prime contract documents, or now or hereafter existing at law or in equity.”

The trial court found that Doyle wrongfully retained the funds and had an obligation to return them. Continental has not appealed that finding, and it was not enumerated as error in this appeal by Griffin. See generally Patterson v. Professional Resources, 242 Ga. 459, 462 (249 SE2d 248) (1978). Doyle has therefore breached its obligations under the subcontract, and Continental by the language of its surety bond has agreed to perform fully Doyle’s obligations if Doyle fails to do so.

B & B Elec. Supply Co. v. H. J. Russell Constr. Co., 166 Ga. App. 499 (304 SE2d 544) (1983), a case involving a public works bond under OCGA § 36-82-100 et seq., is inapposite here. In B & B, a subcontractor on an Atlanta Housing Authority project failed to pay one of its suppliers. Because the subcontractor had failed to obtain a payment bond as required under the subcontract, the supplier made a claim for payment under a performance bond issued to AHA, the owner of the project. After noting special requirements for a bond in *825

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re: Estate Of: Jacqueline Gladstone
798 S.E.2d 660 (Court of Appeals of Georgia, 2017)
Community Magazine, LLC v. Color Xpress
Court of Appeals of Georgia, 2014
Commercial Casualty Insurance v. Maritime Trade Center Builders
572 S.E.2d 319 (Court of Appeals of Georgia, 2002)
Tucker Materials (Georgia), Inc. v. Devito Contracting & Supply, Inc.
535 S.E.2d 858 (Court of Appeals of Georgia, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
497 S.E.2d 586, 230 Ga. App. 822, 98 Fulton County D. Rep. 830, 1998 Ga. App. LEXIS 219, Counsel Stack Legal Research, https://law.counselstack.com/opinion/r-j-griffin-co-v-continental-insurance-gactapp-1998.