Commercial Casualty Insurance v. Maritime Trade Center Builders

572 S.E.2d 319, 257 Ga. App. 779
CourtCourt of Appeals of Georgia
DecidedSeptember 24, 2002
DocketA02A1100, A02A1101
StatusPublished

This text of 572 S.E.2d 319 (Commercial Casualty Insurance v. Maritime Trade Center Builders) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Commercial Casualty Insurance v. Maritime Trade Center Builders, 572 S.E.2d 319, 257 Ga. App. 779 (Ga. Ct. App. 2002).

Opinion

Barnes, Judge.

These cases arise from a performance bond in a subcontractor’s construction contract. The surety, Commercial Casualty Insurance Company (“CCIC”), contends on appeal that the general contractor, Maritime Trade Center Builders (“MTCB”), failed to give sufficient notice to trigger liability under the bond. In a cross-appeal, MTCB contends that the trial court awarded it insufficient damages after a bench trial. For the reasons that follow, we affirm.

MTCB served as the project manager and trade contractor for the Georgia Maritime and International Trade Center construction, built on Hutchinson Island in Chatham County. MTCB entered into a subcontract for $288,356 with IL Construction Company (“IL”) for certain concrete work. Pursuant to the terms of the subcontract, IL obtained a performance bond for $288,356 with CCIC on March 11, 1998.

Relations between MTCB and IL deteriorated, and eventually, in May 1999, IL sued MTCB for money it claimed was due under the subcontract. MTCB answered, denied liability, and counterclaimed against IL for breach of contract, bad faith, and stubborn litigiousness. MTCB also counterclaimed against CCIC, contending the *780 surety was jointly and severally liable under the performance bond. CCIC answered the counterclaim, denying liability and raising as a defense MTCB’s “failure to fulfill conditions precedent to the viable assertions of their claims,” among other things.

Discovery disputes ensued. The trial court ordered IL to supplement some of its answers to MTCB’s interrogatories within a certain time frame. IL failed to do so and filed a dismissal without prejudice, to which MTCB objected. The trial court sustained the objection and held that MTCB’s counterclaim remained pending. The court then granted MTCB’s motion for sanctions against IL for failing to supplement its interrogatory responses as ordered and declared IL to be in default on MTCB’s counterclaims for breach of contract and stubborn litigiousness. After the parties filed additional pleadings, the trial court awarded MTCB attorney fees and expenses of $13,319.59 for prosecuting .the motions to compel and for sanctions.

Both MTCB and CCIC subsequently moved for summary judgment on MTCB’s claim against the surety under IL’s performance bond. After a hearing on contract damages and attorney fees, the trial court denied CCIC’s motion for summary judgment on the issue of coverage under the performance bond, granted MTCB’s motion for summary judgment, and awarded $196,302 to MTCB against IL and CCIC, jointly and severally.

Case No. A02A1100

1. CCIC contends on appeal that it was not liable on the performance bond because MTCB failed to give proper notice of IL’s default, as required by the terms of the bond. MTCB contends that it gave proper notice pursuant to the bond’s terms, and that it was also entitled to recover under the terms of its subcontract with IL, which was incorporated into the bond by reference. The performance bond itself details certain actions MTCB (the Owner) must take to declare IL (the Contractor) in default and thus trigger the surety’s obligations under the bond.

3 If there is no Owner Default, the Surety’s obligation under this Bond shall arise after: 3.1 The Owner has notified the Contractor and the Surety . . . that the Owner is considering declaring a Contractor default and has requested and attempted to arrange a conference with the Contractor and the Surety to be held not later than fifteen days after receipt of such notice to discuss methods of performing the Construction Contract. If the Owner, the Contractor and the Surety agree, the Contractor shall be allowed a reasonable time to perform the Construction Contract, but such an *781 agreement shall not waive the Owner’s right, if any, subsequently to declare a Contractor Default; and 3.2 The Owner has declared a Contractor Default and formally terminated the Contractor’s right to complete the contract. Such Contractor Default shall not be declared earlier than twenty days after the Contractor and the Surety have received notice as provided in Subparagraph 3.1; and 3.3 The Owner has agreed to pay the Balance of the Contract Price to the Surety in accordance with the terms of the Construction Contract or to a contractor selected to perform the Construction Contract in accordance with the terms of the contract with the owner.

The bond also incorporates by reference the contract between MTCB and IL. Article 13 of that contract specifies the actions and remedies available to MTCB if IL fails to perform properly or promptly under the contract, or fails to pay its materialmen. Those remedies include supplementing IL’s work with labor, materials, and equipment after 48 hours notice to IL, and taking charge of IL’s work on the project. 48 hours after giving the subcontractor written notice it was in default. Subsection E of Article 13 addresses the surety’s role if MTCB exercises any remedies under the article, providing:

The remedies provided the Trade Contractor in this Article 13 . . . shall be cumulative, and not exclusive, of all other remedies which the Trade Contractor may have for breach of this Agreement by the Subcontractor, or as a result of the Subcontractor’s failure to perform any of the covenants of this Agreement. All losses, damages, and expenses, including attorneys’ fees incurred in the prosecution or defense of any action, arbitration or suit, trial or appeal, enforcement of any judgment, bankruptcy or insolvency proceeding, or any subsequent proceeding or appeal from any order or judgment entered therein, incurred by or resulting to the Trade Contractor on the above account, shall be borne by and charged against the Subcontractor and shall be damages for breach of this Agreement. Trade Contractor may recover same from the Surety issuing the bonds referenced in Article 16 hereof, and both the Subcontractor and its Surety agree to pay Trade Contractor for such losses, damages, expenses and attorneys’ fees. ...

(Emphasis supplied.)

MTCB sent four documents to CCIC regarding IL’s poor performance. Its project engineer returned a form to CCIC on September 3, *782 1998, reporting on IL’s contract progress. On the form, the engineer noted that the anticipated date of contract completion was October 25,1998, that IL was not paying labor and material bills, and that its work was not progressing satisfactorily. Under "Remarks,” MTCB’s engineer wrote: “MTCB is paying vendors with joint checks now. MTCB is now supplementing field personnel, to run IL Construction crews. IL Construction is so far behind schedule MTCB has added crews to complete job. MTCB had IL Construction’s field superintendent removed from job. Work has been unacceptable.”

MTCB returned another form to CCIC on November 24, 1998, again noting that IL was not paying labor and material bills, and that its work was not progressing satisfactorily, but also indicating that there is no anticipated date of completion because MTCB had to “do a reduction of scope.” Under “Remarks,” the project engineer noted:

Contractor not paying bills. Had vendors coming in and requesting joint checks. Field personnel checks bouncing at bank. Could not meet payroll. Job has been behind schedule.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tucker Materials (Georgia), Inc. v. Devito Contracting & Supply, Inc.
535 S.E.2d 858 (Court of Appeals of Georgia, 2000)
Anchor Sign Company of Georgia, Inc. v. Itt Terryphone Corporation
227 S.E.2d 492 (Court of Appeals of Georgia, 1976)
R. J. Griffin & Co. v. Continental Insurance
497 S.E.2d 586 (Court of Appeals of Georgia, 1998)
Greene County v. North Shore Resort at Lake Oconee, LLC
517 S.E.2d 553 (Court of Appeals of Georgia, 1999)
McArthor v. McGilvray
57 S.E. 1058 (Court of Appeals of Georgia, 1907)

Cite This Page — Counsel Stack

Bluebook (online)
572 S.E.2d 319, 257 Ga. App. 779, Counsel Stack Legal Research, https://law.counselstack.com/opinion/commercial-casualty-insurance-v-maritime-trade-center-builders-gactapp-2002.