IHI E&C International Corporation v. Robinson Mechanical Contractors, Inc.

CourtDistrict Court, N.D. Georgia
DecidedSeptember 30, 2022
Docket1:19-cv-04137
StatusUnknown

This text of IHI E&C International Corporation v. Robinson Mechanical Contractors, Inc. (IHI E&C International Corporation v. Robinson Mechanical Contractors, Inc.) is published on Counsel Stack Legal Research, covering District Court, N.D. Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
IHI E&C International Corporation v. Robinson Mechanical Contractors, Inc., (N.D. Ga. 2022).

Opinion

UNITED STATES DISTRICT COURT NORTHERN DISTRICT OF GEORGIA ATLANTA DIVISION

IHI E&C INTERNATIONAL CORPORATION et al., Plaintiffs, v. CIVIL ACTION NO. 1:19-cv-04137-JPB ROBINSON MECHANICAL

CONTRACTORS, INC., d/b/a

ROBINSON CONSTRUCTION COMPANY et al., Defendants. ORDER Before the Court are Defendant Fidelity and Deposit Company of Maryland’s (“Fidelity”) Motion for Partial Summary Judgment, ECF No. 163, and Plaintiff IHI E&C International Corporation’s (“IHI”) Cross Motion for Summary Judgment, ECF No. 179.1 Having fully considered the parties’ initial and post hearing briefs and their arguments at the hearing on the motions, the Court finds as follows:

1 Defendant Robinson Mechanical Contractors, Inc. supports Fidelity’s position and filed briefs in support of Fidelity’s motion and in opposition to IHI’s motion. For ease of reference and because Fidelity’s and Robinson’s arguments are similar, the Court will refer to Fidelity’s and Robinson’s arguments as Fidelity’s arguments. I. BACKGROUND In September 2019, IHI filed suit against Robinson Mechanical Contractors, Inc. (“Robinson”) and Fidelity alleging several causes of action in connection with a complex construction project in Elba Island, Georgia (the “Project”). Fidelity

now moves the Court for a ruling that a bond Fidelity issued to secure Robinson’s performance on its construction contract with IHI does not cover two other agreements between IHI and Robinson. IHI seeks the opposite judgment, i.e., that

the performance bond covers the construction contract as well as the two other agreements. The following relevant facts are not in dispute. Robinson entered into three separate written agreements with IHI that are the subject of IHI’s Complaint. Under the first agreement, which was signed on June

6, 2016, Robinson agreed to furnish certain pipes and rack modules for the Project at the price of $35,560,649.54 (“Purchase Order No. 1”). IHI did not require Robinson to furnish a performance bond for Purchase Order No. 1. Instead, IHI

required Robinson to provide an irrevocable letter of credit. That letter of credit has expired. Robinson and IHI entered into a second written agreement signed on February 2, 2017, pursuant to which Robinson agreed to furnish certain process

modules, piping, heat trace and pipe insulation for the Project at the price of $5,143,648 (“Purchase Order No. 2”). IHI similarly did not require Robinson to provide a performance bond for Purchase Order No. 2. IHI also did not require a letter of credit or any other security for Purchase Order No. 2. Robinson and IHI entered into a third agreement, which Robinson signed on

November 6, 2017, and IHI signed on November 14, 2017 (the “Construction Contract”). Under the Construction Contract, Robinson agreed to perform construction work at the Project site, including certain pipe rack and process

module installation, for the price of $24,007,045. During negotiations of the Construction Contract, IHI never mentioned that the Purchase Orders were related to the Construction Contract. However, the parties executed a change order for one of the Purchase Orders that removed certain work from the scope of the

Purchase Order and included it in the scope of the Construction Contract. IHI required Robinson to obtain payment and performance surety bonds for the Construction Contract, each in the sum of $24,007,045—the value of the

Construction Contract. Robinson obtained the bonds from Fidelity, in its capacity as surety. The performance bond, which was issued at a face value of $24,007,045 (the “Performance Bond”), extended coverage for only the “performance of the Construction Contract.” Specifically, Section 9 of the Performance Bond provides

that: The surety shall not be liable to [IHI] or others for obligations of [Robinson] that are unrelated to the Construction Contract, and the Balance of the Contract Price shall not be reduced or set off on account of any such unrelated obligations. Robinson’s president testified that in his thirty-four years of experience obtaining and providing surety bonds for construction contracts, all of the bonds he has obtained have covered only the contract identified in the bonds and were issued at the face value of the bonded contract price. In the construction industry, it is standard for payment and performance surety bonds to have the same penal sum as the bonded contract price. If the cost of the bonded work were significantly greater than the penal sum, the surety’s risk

would exceed the face value of the bond. For example, if a contract required work costing $24 million, the surety’s risk on a $24 million bond would be negligible after $24 million worth of work was completed properly. If, however, the contract

required work costing $64 million but the bond penal sum were only $24 million, the surety would still face full penal-sum risk long after the first $24 million in work was completed. For this reason, sureties expect and require that the estimated cost of the bonded work will be no more than the price of the bonded

contract (and the penal sum of the bond). It appears Robinson undertook work pursuant to the three agreements between 2016 and 2018. A significant portion of the work under the Purchase Orders was performed away from the Project site, and the stated scope of the Purchase Orders did not include work at the Project site. Conversely, almost all of the scope of work under the Construction Contract was to be performed at the Project site. This work included the installation of certain components Robinson

furnished under the Purchase Orders. Robinson departed the Project site before the completion of the Project, and IHI retained replacement subcontractors to complete Robinson’s work. IHI alleges

that it discovered and was required to pay for extensive repairs and correction of defects on the work Robinson completed. On July 24, 2019, IHI issued a demand to Robinson and Fidelity for payment in the amount of $31,180,565.

IHI contends that Robinson’s work under the Purchase Orders was incorporated into the Construction Contract and is therefore covered by the Performance Bond. IHI’s argument is based on an indemnity provision in section

30.3 of the Construction Contract (“Section 30.3”). Fidelity responds that the Purchase Orders are separate agreements that were not incorporated into the Construction Contract. Fidelity therefore concludes that the Performance Bond does not cover any work Robinson completed pursuant to the Purchase Orders.

Thus, the question presented to the Court is whether the Construction Contract and Performance Bond cover damages arising out of Robinson’s work under the Purchase Orders. II. DISCUSSION A. Legal Standard

“Summary judgment is appropriate when the record evidence, including depositions, sworn declarations, and other materials, shows that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of

law.” Feliciano v. City of Miami Beach, 707 F.3d 1244, 1247 (11th Cir. 2013) (quoting Fed. R. Civ. P. 56) (quotation marks omitted). A material fact is any fact that “is a legal element of the claim under the applicable substantive law which might affect the outcome of the case.” Allen v. Tyson Foods, Inc., 121 F.3d 642,

646 (11th Cir. 1997). A genuine dispute exists when “the evidence is such that a reasonable jury could return a verdict for the nonmoving party.” Anderson v. Liberty Lobby, Inc.,

Related

Allen v. Tyson Foods, Inc.
121 F.3d 642 (Eleventh Circuit, 1997)
Erie Railroad v. Tompkins
304 U.S. 64 (Supreme Court, 1938)
Byrd v. Blue Ridge Rural Electric Cooperative, Inc.
356 U.S. 525 (Supreme Court, 1958)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Janet Feliciano v. City of Miami Beach
707 F.3d 1244 (Eleventh Circuit, 2013)
Brogdon v. Pro Futures Bridge Capital Fund, L.P.
580 S.E.2d 303 (Court of Appeals of Georgia, 2003)
HERTZ EQUIPMENT RENTAL CORPORATION v. Evans
397 S.E.2d 692 (Supreme Court of Georgia, 1990)
Ainsworth v. Perreault
563 S.E.2d 135 (Court of Appeals of Georgia, 2002)
R. J. Griffin & Co. v. Continental Insurance
497 S.E.2d 586 (Court of Appeals of Georgia, 1998)
ESI Companies, Inc. v. Fulton County
609 S.E.2d 126 (Court of Appeals of Georgia, 2004)
General Steel, Inc. v. Delta Building Systems, Inc.
676 S.E.2d 451 (Court of Appeals of Georgia, 2009)
Puritan Mills, Inc. v. Pickering Construction Co.
262 S.E.2d 586 (Court of Appeals of Georgia, 1979)
Arnold v. INDCON, LP
466 S.E.2d 684 (Court of Appeals of Georgia, 1996)
Young v. Stump
669 S.E.2d 148 (Court of Appeals of Georgia, 2008)
Mullis v. Bibb County
669 S.E.2d 716 (Court of Appeals of Georgia, 2008)
Coleman v. ARRINGTON AUTO SALES & RENTALS
669 S.E.2d 414 (Court of Appeals of Georgia, 2008)
CS-Lakeview at Gwinnett, Inc. v. Simon Property Group, Inc.
642 S.E.2d 393 (Court of Appeals of Georgia, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
IHI E&C International Corporation v. Robinson Mechanical Contractors, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/ihi-ec-international-corporation-v-robinson-mechanical-contractors-inc-gand-2022.