Georgia State Financing & Investment Commission v. XL Specialty Insurance Co.

694 S.E.2d 193, 303 Ga. App. 540, 2010 Fulton County D. Rep. 1337, 2010 Ga. App. LEXIS 380
CourtCourt of Appeals of Georgia
DecidedApril 7, 2010
DocketA10A0504, A10A0581
StatusPublished
Cited by4 cases

This text of 694 S.E.2d 193 (Georgia State Financing & Investment Commission v. XL Specialty Insurance Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Georgia State Financing & Investment Commission v. XL Specialty Insurance Co., 694 S.E.2d 193, 303 Ga. App. 540, 2010 Fulton County D. Rep. 1337, 2010 Ga. App. LEXIS 380 (Ga. Ct. App. 2010).

Opinion

BLACKBURN, Presiding Judge.

In this breach of construction contract action, owner Georgia State Financing & Investment Commission (“GSFIC”) appeals in Case No. A10A0504 the grant of summary judgment to the surety company that warranted the roof of the newly constructed buildings for five years (XL Specialty Insurance Company, hereinafter “XL”), arguing that the trial court erred in its interpretation of the XL bond. Specifically, GSFIC argues that XL’s bond on the roofs covered not only the five years after the architect was to issue its final certificate but also the time period before the issuance of that certificate. We agree with the trial court that the language of the bond meant that the bond covered the roofs only for the five years after the architect’s issuance of the final certificate, and we therefore affirm in Case No. A10A0504.

In Case No. A10A0581, Fireman’s Fund Insurance Company (“Fireman’s Fund”) appeals the grant of summary judgment to the subcontractor that installed the suspended ceilings in the buildings (Bonitz of Georgia, Inc., hereinafter “Bonitz”), arguing that some evidence showed that the installation was defective and negligently performed. We agree with Fireman’s Fund that some evidence showed that Bonitz negligently installed the ceilings in nonconfor-mance with contract specifications, and that therefore the trial court erred in granting summary judgment to Bonitz. Accordingly, we reverse in Case No. A10A0581. This moots Fireman’s Fund’s secondary argument that if Bonitz were properly granted summary judgment, Fireman’s Fund should have also been granted partial summary judgment on the claims against it involving Bonitz’s work.

Summary judgment is proper when there is no genuine issue of material fact and the movant is entitled to judgment as a matter of law. OCGA § 9-11-56 (c). A de novo standard of review applies to an appeal from a denial of summary judgment, and we view the evidence, and all reasonable conclusions and inferences drawn from it, in the light most favorable to the nonmovant. Matjoulis v. Integon Gen. Ins. Corp. 1

So viewed, the evidence shows that on August 2, 2000, a general contractor and GSFIC entered into a construction contract for the construction of several buildings for a state hospital for an amount *541 just over $16 million. Fireman’s Fund issued a performance bond on the project in favor of GSFIC in the same amount. Cf. OCGA § 13-10-40.

In an effort to close out the project, the general contractor, the architect, and GSFIC conducted a final inspection tour in early May 2003, and (as specified by the contract as part of the required close-out documents) the general contractor had XL execute on May 7, 2003 a GSFIC-prepared bond on the roofs and walls of the buildings “for a period of five years from the date of the execution of the final certificate of the architect.” However, the architect expressly refused to issue a final certificate of completion because neither the work had been fully completed nor had the contract been fully performed.

During the months and years thereafter, GSFIC determined that the general contractor had not constructed the buildings in conformance with the contract and further determined that there were numerous defects in the buildings including leaks in the roof. After terminating the general contractor and hiring other companies to remediate the defects, GSFIC in January 2007 sued the general contractor and the architect, then added Fireman’s Fund as a defendant (on its performance bond), and eventually added XL (on its roof bond). Bonitz and other subcontractors were added as third-party defendants on claims by Fireman’s Fund that they had negligently performed their work in breach of their subcontracts and were obligated to indemnify Fireman’s Fund for any resulting liability incurred by Fireman’s Fund. The general contractor asserted a similar cross-claim against Bonitz.

XL moved for summary judgment, arguing that its bond covered only the five years after the architect had executed its final certificate of completion, which execution GSFIC affirmatively conceded had never occurred. GSFIC opposed summary judgment, arguing that the bond also covered the time period between its execution on May 7, 2003 and the issuance of the architect’s final certificate. Interpreting the bond, the trial court granted summary judgment to XL, leading to GSFIC’s appeal in Case No. A10A0504.

Bonitz also moved for summary judgment on the third-party complaint and the cross-claim against it, arguing that no evidence showed that its work was defective or nonconforming. Although Fireman’s Fund opposed that motion, Fireman’s Fund in the alternative moved for partial summary judgment in its favor on any GSFIC claims against it arising from Bonitz’s work (should the court grant Bonitz summary judgment). Finding no evidence of defective work by Bonitz, the trial court granted Bonitz’s motion for summary judgment but denied Fireman’s Fund’s related motion for partial *542 summary judgment, leading to Fireman’s Fund’s appeal in Case No. A10A0518.

Case No. A10A0504

1. The central question in the appeal of the summary judgment granted to XL is the interpretation of its bond. Thus, we set forth some well-known principles of contract construction. First, the construction of a contract is a question of law for the court based on the intent of the parties as set forth in the contract, which construction we review de novo. Deep Six, Inc. v. Abernathy. 2 “The cardinal rule of construction is to ascertain the intention of the parties. If that intention is clear and it contravenes no rule of law and sufficient words are used to arrive at the intention, it shall be enforced irrespective of all technical or arbitrary rules of construction.” OCGA § 13-2-3. Thus, “when the terms of a written contract are clear and unambiguous, the court is to look to the contract alone to find the parties’ intent.” (Punctuation omitted.) Owners Ins. Co. v. Smith Mechanical Contractors 3 (quoting Park 'N Go of Ga. v. United States Fidelity &c. Co. 4 ). Only if the contract is ambiguous in some respect do we apply the rules of contract construction to resolve the ambiguity. Avion Systems v. Thompson. 5 See generally Gill v. B & R Intl. 6

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Eagle Jets, LLC. v. Atlanta Jet, Inc.
820 S.E.2d 197 (Court of Appeals of Georgia, 2018)
H & E Innovation, LLC v. Shinhan Bank America (Inc.)
808 S.E.2d 258 (Court of Appeals of Georgia, 2017)
Jessica Parm v. National Bank of California, N.A.
835 F.3d 1331 (Eleventh Circuit, 2016)
Olympus Media, LLC v. City of Dunwoody, Georgia
780 S.E.2d 108 (Court of Appeals of Georgia, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
694 S.E.2d 193, 303 Ga. App. 540, 2010 Fulton County D. Rep. 1337, 2010 Ga. App. LEXIS 380, Counsel Stack Legal Research, https://law.counselstack.com/opinion/georgia-state-financing-investment-commission-v-xl-specialty-insurance-gactapp-2010.