CHRISTOPHER MILLING v. BURNS AND MCDONNELL ENGINEERING COMPANY

CourtCourt of Appeals of Georgia
DecidedJuly 2, 2026
DocketA26A0450
StatusPublished

This text of CHRISTOPHER MILLING v. BURNS AND MCDONNELL ENGINEERING COMPANY (CHRISTOPHER MILLING v. BURNS AND MCDONNELL ENGINEERING COMPANY) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
CHRISTOPHER MILLING v. BURNS AND MCDONNELL ENGINEERING COMPANY, (Ga. Ct. App. 2026).

Opinion

THIRD DIVISION DILLARD, P. J., GOBEIL and PIPKIN, JJ.

NOTICE: Motions for reconsideration must be physically received in our clerk’s office within ten days of the date of decision to be deemed timely filed. https://www.gaappeals.gov/rules

July 2, 2026

In the Court of Appeals of Georgia A26A0450. MILLING v. BURNS AND MCDONNELL ENGINEERING COMPANY.

GOBEIL, Judge.

This appeal stems from a personal injury suit appellant Christopher Milling

filed against Burns & McDonnell Engineering Co. (“BME”) and a BME project

manager, Justin Kanitz (collectively referred to as the “defendants”). The trial court

granted the defendants’ motion for summary judgment, concluding that neither BME

nor Kanitz owed a legal duty to Milling, and Milling had failed to establish that BME’s

actions were the proximate cause of his injuries or that BME had superior knowledge

of the hazard that caused Milling’s injuries. Milling now appeals from the trial court’s

grant of summary judgment in favor of BME. For the reasons set forth more fully

below, we reverse. Summary judgment is proper where “the pleadings, depositions, answers to

interrogatories, and admissions on file, together with the affidavits, if any, show that

there is no genuine issue as to any material fact and that the moving party is entitled

to judgment as a matter of law[.]” OCGA § 9-11-56(c). We review the grant of a

motion for summary judgment de novo, “view[ing] the evidence, and all reasonable

inferences drawn therefrom, in the light most favorable to the nonmovant.” Cowart

v. Widener, 287 Ga. 622, 624(1)(a) (697 SE2d 779) (2010).

So viewed, the record shows that in 2021, Milling sustained severe injuries

while working as a lineman for nonparty Pike Electric (“Pike”). Nonparty Georgia

Power retained Pike to perform work related to the construction and integration of a

new electrical bay (“Bay 4”) at Old National substation. BME provided program

management services to Georgia Power in connection with its wide-ranging Grid

Investment Program, including managing the construction at the substation.

Specifically, in January 2020, BME entered into a Master Contract for Program

Management Services (the “MC”) with Southern Company (Georgia Power’s parent

company). The MC set out that “[e]ach Other contractor shall remain solely

responsible for ensuring the safety of its employees, subcontractors, and works.”

2 BME also agreed to “review the safety programs developed by each of the Other

Contractors for purposes of coordinating the safety programs with those of the Other

Contractors.” As part of its program management responsibilities, BME agreed to

“[m]anage[ ] the coordination of all [power] outage activity,” including developing

and directing outage planners on outage sequence and planning. The MC authorized

BME to perform work pursuant only to an executed authorization, and the parties

executed a service order regarding Program Management Services for the Grid

Investment Program (the “Service Order”).

BME compiled a Program Execution Plan (“PEP”) for the Grid Investment

Program that sets forth several relevant provisions. As to service authorizations, the

PEP described that BME’s program manager will review new project scopes and

prepare a recommendation to Georgia Power for the design-build (“DB”) contractor

assignments. With respect to outage planning and management, the PEP described

BME’s role as working with Georgia Power and DB contractors to address any

concerns before proceeding with a final outage sequence plan and ensure that the

plans are vetted. BME also was authorized to accompany construction teams to job

sites to inspect and plan outage work.

3 Pike entered into its own Master Contract with Southern Company for

“Design/Build Services for the Grid Investment Program” (the “Pike MC”). Pike’s

role in the project was the DB contractor to design and construct Bay 4 at the

substation. The Pike MC provided that Pike was “solely responsible for the safe

performance of all Work, [and Southern Company] is not responsible for the physical

condition or safety of a Work Site.”

BME prepared a “Final Scoping Report” (“FSR”) that identified the

equipment to be de-energized during the course of the Old National Substation

project. The outage management/reliability section of the FSR listed two days of

outages at three of the four bays. A November 2021 Outage Plan for the Old National

project indicated that three existing feeders at the substation would remain connected

to transmission metering potential transformers.

On the day of his injury, November 16, 2021, Milling was working to install and

align Bay 4 into the substation. Milling’s foreman, Greg Taylor, a Pike employee,

informed Milling that the area in which his crew would be working was de-energized.

While working near an energized feeder protruding from an existing bay (“Bay 3”),

4 Milling suffered severe injuries when his measuring equipment made contact with the

feeder.

Milling filed suit against the defendants, asserting in pertinent part that BME’s

conduct was the proximate cause of his injuries. Specifically, he alleged that the

defendants negligently approved and/or failed to detect deficiencies in an electrical

outage plan that left energized equipment too close to Pike’s active work zone. The

defendants filed motions for summary judgment, primarily on the grounds that they

did not owe a duty of care to Milling, and under the terms of the MC, BME was not

responsible for the safety of contractors’ workers.

Following a hearing, the trial court granted summary judgment to the

defendants, concluding that BME did not owe Milling a duty under either common

law or by virtue of its contract with Southern Company, as Milling was not a

third-party beneficiary under the MC. As to Kanitz, the court concluded that he was

not liable for Milling’s injuries because Milling failed to offer evidence to controvert

Kanitz’s testimony that Kanitz had no specific responsibilities related to the Old

National project.1 The trial court also found that Milling could not show proximate

1 Milling does not challenge the grant of summary judgment in favor of Kanitz, and he is not a party to the instant appeal. 5 cause because the defendants did not create, energize, or maintain the energized

feeder that injured Milling. According to the court, any failure by Pike to ensure a safe

work environment was not attributable to the defendants and broke any causal chain.

In addition, the trial court found that Milling had equal or superior knowledge of the

hazard based on his years of experience working as a lineman at other substations.

Finally, the trial court declined to consider post-incident “lessons learned” evidence,

finding that Milling failed to satisfy any of the exceptions to the rule that evidence of

subsequent remedial measures is generally inadmissible to prove negligence. This

appeal followed.

1. First, Milling argues that the trial court erred by concluding that BME did not

owe him a legal duty.

(a) Specifically, Milling contends that BME owed a duty of reasonable care to

other contractors working on the Old National substation

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Soucy v. Alexander
323 S.E.2d 662 (Court of Appeals of Georgia, 1984)
Baker v. HARCON, INC.
694 S.E.2d 673 (Court of Appeals of Georgia, 2010)
Doke v. Dover Elevator Co.
263 S.E.2d 209 (Court of Appeals of Georgia, 1979)
McKinney v. Regents of the University System
643 S.E.2d 736 (Court of Appeals of Georgia, 2007)
Coweta County v. Adams
473 S.E.2d 558 (Court of Appeals of Georgia, 1996)
Ragsdale Heating & Air Conditioning, Inc. v. Terrell
539 S.E.2d 199 (Court of Appeals of Georgia, 2000)
Cowart v. Widener
697 S.E.2d 779 (Supreme Court of Georgia, 2010)
MARK Et Al. v. AGERTER
775 S.E.2d 235 (Court of Appeals of Georgia, 2015)
Adcox Service Co. v. Adderhold
435 S.E.2d 262 (Court of Appeals of Georgia, 1993)
JOHNSON v. AVIS RENT a CAR SYSTEM, LLC (Two Cases)
858 S.E.2d 23 (Supreme Court of Georgia, 2021)

Cite This Page — Counsel Stack

Bluebook (online)
CHRISTOPHER MILLING v. BURNS AND MCDONNELL ENGINEERING COMPANY, Counsel Stack Legal Research, https://law.counselstack.com/opinion/christopher-milling-v-burns-and-mcdonnell-engineering-company-gactapp-2026.