Baker v. HARCON, INC.

694 S.E.2d 673, 303 Ga. App. 749, 2010 Fulton County D. Rep. 1461, 2010 Ga. App. LEXIS 334
CourtCourt of Appeals of Georgia
DecidedMarch 30, 2010
DocketA09A2398
StatusPublished
Cited by11 cases

This text of 694 S.E.2d 673 (Baker v. HARCON, INC.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Baker v. HARCON, INC., 694 S.E.2d 673, 303 Ga. App. 749, 2010 Fulton County D. Rep. 1461, 2010 Ga. App. LEXIS 334 (Ga. Ct. App. 2010).

Opinions

Bernes, Judge.

In this lawsuit, H. R. Baker I\i a construction supervisor, sued Harcon, Inc., a subcontractor working on the same construction project, after being injured on the construction site as a result of the alleged negligence of Harcon. The trial court granted summary judgment to Harcon after concluding that Baker failed to exercise ordinary care for his own safety and otherwise assumed the risk of his injury. We conclude that the alleged conduct of the parties raises genuine issues of material facts necessary for jury resolution, rendering this case inappropriate for summary adjudication; we therefore reverse.

Following the grant of a motion for summary judgment, we conduct a de novo review of the evidence. Creeden v. Fuentes, 296 Ga. App. 96 (673 SE2d 611) (2009). In so doing, we view the evidence and all reasonable conclusions and inferences drawn therefrom in the light most favorable to the nonmovant. Id. Summary judgment is proper only when no issue of material fact exists and the moving party is entitled to judgment as a matter of law. Id.; OCGA § 9-11-56 (c).

So construed, the evidence shows that in January 2006, Baker was working as an assistant construction supervisor for his employer, Foundation Contractors, Inc., a subcontractor on a large construction project known as the West Village Building Project. Harcon was also a subcontractor on the project. Both companies worked under the overall supervision of the general contractor, Hardin Construction Company, LLC. The project consisted of seven mixed-use buildings, numbered 1000 through 7000.

Foundation oversaw all concrete construction on the project. Harcon built and erected wooden “forms” into which Foundation poured the concrete. Once Foundation had poured concrete into the [750]*750forms, the concrete would then be given several days to cure. After the concrete had properly cured, Harcon would disassemble the forms and remove them from the workplace, leaving in place the remaining concrete structure.

The accident in question occurred during construction of the second level of Building 4000, a 10,000-square-foot concrete floor. To construct this floor, Harcon erected an elevated wooden deck to which temporary guardrails were attached.1 Harcon then surrounded the wooden deck with “edge forms.” Foundation employees showed Harcon areas in the concrete floor that were to be left open to accommodate such things as stairwells and trash chutes. Harcon then built additional wooden edge forms around the desired openings identified by Foundation so that holes would remain when Foundation poured the concrete floor. After the form assembly had been completed, Foundation poured the concrete onto the wooden deck.

Baker personally informed Harcon that Building 4000 was to have a trash chute, and showed Harcon its desired location. Building 4000 was at least the fifth building in the project on which Baker had worked, but the only one in which he worked that had a trash chute.2

After Foundation poured the concrete for the second level, Baker and his crew left Building 4000 to commence work on another building in the project. Approximately four to six days later, when the concrete on the second level of Building 4000 had cured, Harcon disassembled the wooden forms, and removed the wooden deck and guardrails. This disassembly included removal of a wooden sheet which underlay the area set out for the trash chute so that, for the first time, there was an opening in the floor.

After the disassembly occurred, Hardin, the general contractor, ordered Baker “to take a group of workers from any crew [he] could find” to return to the second floor platform and remove remaining debris in preparation for the framer’s arrival the following day. Baker, concerned about exposing his workers to the falling hazard, reluctantly agreed; he thereafter gathered several men from his own crew and a few Harcon workers to accompany him to the concrete platform. Baker implored the men to remain within ten feet from the edge of the platform and supplied them with rakes to reach items [751]*751that may be within that forbidden area, then accompanied them to ensure that they respected the perimeter and otherwise took adequate safety precautions.

As Baker walked the platform supervising the men, he and a second worker observed what they believed to be a pile of debris, consisting of several small pieces of wood on top of a larger piece of scrap plywood that contained cement smears and saw cuts. As the other worker picked up the smaller pieces of wood, Baker bent over to pick up the larger piece. Baker walked forward in an attempt to stand the wood upright but, due to the size of the plywood, he could not see the surface of the concrete platform below. As Baker stepped forward, he fell through the trash chute hole approximately 20 feet to the ground below, resulting in severe injuries which have caused him to be totally and permanently disabled.

Baker thereafter filed the instant lawsuit seeking compensatory and punitive damages against Harcon.3 Baker alleged that his injury resulted from Harcon’s negligent failure to adequately warn of and/or guard against the danger created by the hole that it exposed in the concrete platform.4 Harcon moved for summary judgment, contending that Baker failed to exercise ordinary care for his own safety and otherwise assumed the risk of his injury. The trial court granted Harcon’s motion and this appeal followed.

Baker contends that the trial court erred in granting summary judgment to Harcon. First, Baker argues that the trial court erroneously refused to consider certain statements that he made in an affidavit which the trial court deemed to be contradictory to testimony given during his deposition. See Prophecy Corp. v. Charles Rossignol, Inc., 256 Ga. 27, 28-30 (1) (343 SE2d 680) (1986). Second, Baker asserts that the trial court erred in concluding that he was precluded from recovering damages from Harcon because he failed to exercise ordinary care for his own safety and/or assumed the risk of his injury.

Pretermitting whether or not the trial court erred in excluding the affidavit testimony, we conclude that — even in the absence of that testimony — the record presents a jury question as to Harcon’s liability, rendering the trial court’s grant of summary judgment in favor of Harcon improper.

(a) Exercise of Ordinary Care. Unquestionably, a building subcontractor has a duty to exercise ordinary care not to cause injuries [752]*752to others engaged in work on the same premises. Doke v. Dover Elevator Co., 152 Ga. App. 434, 436 (263 SE2d 209) (1979).

Where severed persons are engaged in the same work, in which the negligent or unskillful performance of his part by one may cause danger to the others, in which each must necessarily depend for his safety upon the good faith, skill and prudence of each of the others in doing his part of the work, then it is the duty of each to the others engaged in the work to exercise the care and skill ordinarily employed by prudent men in similar circumstances.

(Citation and punctuation omitted.) Id. See OCGA § 51-1-6; Ragsdale Heating &c. v. Terrell, 245 Ga. App.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

DANIELLA MEJIA v. SK BATTERY AMERICA INC
Court of Appeals of Georgia, 2026
CITY OF SUWANEE v. LINDA PADGETT
Court of Appeals of Georgia, 2022
SIMON v. MURPHY Et Al.
829 S.E.2d 380 (Court of Appeals of Georgia, 2019)
King v. Georgia Department of Corrections.
820 S.E.2d 445 (Court of Appeals of Georgia, 2018)
Mike Smith v. Alda Jean Found
806 S.E.2d 287 (Court of Appeals of Georgia, 2017)
Benjamin Card v. Dublin Construction Company
788 S.E.2d 845 (Court of Appeals of Georgia, 2016)
SWOPE v. GREENBRIAR MALL LIMITED PARTNERSHIP Et Al.
765 S.E.2d 396 (Court of Appeals of Georgia, 2014)
Georgia Department of Corrections v. Couch
718 S.E.2d 875 (Court of Appeals of Georgia, 2011)
Orton v. MASQUERADE, INC.
716 S.E.2d 764 (Court of Appeals of Georgia, 2011)
Barnes v. Morganton Baptist Ass'n, Inc.
703 S.E.2d 359 (Court of Appeals of Georgia, 2010)
Ramcke v. Georgia Power Co.
703 S.E.2d 13 (Court of Appeals of Georgia, 2010)
Baker v. HARCON, INC.
694 S.E.2d 673 (Court of Appeals of Georgia, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
694 S.E.2d 673, 303 Ga. App. 749, 2010 Fulton County D. Rep. 1461, 2010 Ga. App. LEXIS 334, Counsel Stack Legal Research, https://law.counselstack.com/opinion/baker-v-harcon-inc-gactapp-2010.