McKinney v. Regents of the University System

643 S.E.2d 736, 284 Ga. App. 250
CourtCourt of Appeals of Georgia
DecidedFebruary 8, 2007
DocketA06A2439
StatusPublished
Cited by3 cases

This text of 643 S.E.2d 736 (McKinney v. Regents of the University System) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McKinney v. Regents of the University System, 643 S.E.2d 736, 284 Ga. App. 250 (Ga. Ct. App. 2007).

Opinion

Ruffin, Judge.

David M. McKinney, an employee of LF Pipeline, was seriously injured when the jackhammer he was operating struck an electrical line. He brought a negligence action against the Regents of the University System of Georgia (“Board of Regents”), Turner Construction Company and E. R. Mitchell Construction, Inc. d/b/a Turner Mitchell Joint Venture (“Turner/Mitchell”), and Mark Henderson, Incorporated (“Henderson”). The trial court granted the defendants’ motion for summary judgment and McKinney appeals. We affirm, for reasons that follow.

“ ‘Summary judgment is proper where there is no genuine issue of material fact and the movant is entitled to judgment as a matter of law.’ 1 A defendant is entitled to summary judgment if he can demonstrate “an absence of evidence on at least one essential element of the plaintiffs case.” 2 Ade novo standard of review applies to a grant of summary judgment, and we view the evidence in a light most favorable to the nonmovant. 3

Viewed favorably to McKinney, the evidence shows that on May 6, 1996, the Board of Regents entered into a construction management agreement with Turner/Mitchell for the construction of a parking deck and student center on the Georgia State University campus. On January 8, 1997, Turner/Mitchell and Henderson entered into a subcontract wherein Henderson agreed to provide the electrical work for the project. Henderson installed an electrical conduit encased in concrete more than four feet underground.

*251 Atlanta Gas Light arranged for LF Pipeline to lay the pipe for the gas line at the construction site. Fred Kirby was Henderson’s electrical superintendent for the project. Kirby testified that, on the day of the incident, he met with three men from LF Pipeline, including McKinney and another person he believed to be the job foreman for LF Pipeline. 4 Kirby showed the men the precise location of the electrical conduit and explained that it was encased in concrete. 5 He did not know that the men intended to use a jackhammer until after the incident.

Ricky Jackson, the LF Pipeline supervisor for the project, recalls meeting with McKinney, two other men, and a man that Jackson believed was the superintendent for the water company or the plumbing contractor. According to Jackson, the superintendent told them that the power cables were encased in concrete and ran from the transformer box to the building. Jackson recalls that although McKinney was present during the conversation with the superintendent regarding the utility lines, McKinney “[was not] listening.” However, Jackson also stated that he specifically told McKinney that there were power lines encased in concrete in the area in which McKinney dug.

During his deposition, McKinney testified that he walked around the job site with his crew, Ricky Jackson, and a superintendent. 6 The superintendent told them that there were power lines running from the road to the transformer box. McKinney stated that no one told him that there were electrical lines — encased in concrete or otherwise — running from the transformer to the building and that if he had known that there were electrical lines in that area, he would not have dug until the lines had been located.

McKinney and his crew decided to use the jackhammer to get through the concrete footing wall. McKinney recalls that the superintendent responded, “okay,” when McKinney told him that he intended to “[use] the jackhammer to get up under the wall.” Approximately five minutes after he began operating the jackhammer, it hit an electrical line, and McKinney sustained an electric shock, resulting in second and third degree burns below McKinney’s waist, on his hands, and on one elbow. 7

*252 McKinney filed suit against the defendants, alleging that they negligently failed to mark the location of the underground power lines, to notify him of the existence of the lines, and to keep the worksite safe. The defendants moved for summary judgment on several grounds, including that they owed no duty to McKinney to warn of the electrical lines, that McKinney caused his own injury by changing the nature of the premises, and that any duty of the defendants to warn of the buried electrical lines was discharged by LF Pipeline’s knowledge of the hazard. Following oral argument, the trial court granted summary judgment to the defendants, essentially concluding that they were not liable to McKinney because his supervisor had been adequately notified about the location of the buried electrical duct bank.

1. McKinney contends that the trial court erred in granting summary judgment. We disagree. Negligence requires a showing that the defendants owed a duty to plaintiff that they then breached, causing plaintiff harm. 8 Pretermitting whether the defendants owed any duty to McKinney or whether McKinney changed the condition of the premises, rendering it unsafe, any duty imposed upon the defendants was discharged by virtue of Jackson’s knowledge of the existence and location of the electrical conduit. 9

In Douberly, 10 a logger sustained serious electrical burns when a tree he felled struck a power line. He sought recovery against the landowner, alleging that the owner breached its duty to warn him of the existence of the power line.* 11 Because there was unrefuted evidence that the logger’s employer was informed of the location and existence of the power line, including the employer’s admission that he had actual knowledge, we affirmed the trial court’s grant of summary judgment to the landowner. 12 Thus, “[tjhere [was] no question as to the adequacy of the warning. Full knowledge by the independent contractor of the dangers should and will be held to discharge the landowner’s alternative duty to warn the employees.” 13

Here, McKinney’s supervisor, Jackson, specifically admits that he was informed of the existence and location of the power line. Thus, assuming that the defendants owed McKinney a duty to warn of the buried electrical conduit, such duty was discharged once LF Pipeline *253 had actual knowledge of the power lines. 14 And, although there are different accounts regarding who informed Jackson, such discrepancy does not alter the fact that Jackson had actual knowledge of the hazard. The source of the warning is immaterial, as the sole issue is whether LF Pipeline had knowledge of the electrical lines. 15

Free access — add to your briefcase to read the full text and ask questions with AI

Related

LAW Et Al. v. CHEMTALL, INC.
802 S.E.2d 408 (Court of Appeals of Georgia, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
643 S.E.2d 736, 284 Ga. App. 250, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mckinney-v-regents-of-the-university-system-gactapp-2007.