International Resource Recovery, Inc. v. United States

60 Fed. Cl. 428, 2004 U.S. Claims LEXIS 92, 2004 WL 874809
United States Court of Federal Claims·Decided April 19, 2004·No. No. 04-154C·Published·Cited by 11 cases

Opinion

ORDER AND OPINION DENYING ADDITIONAL SUPPLEMENTATION OF THE ADMINISTRATIVE RECORD

WILLIAMS, Judge.

In this post-award bid protest, Plaintiff, an incumbent contractor who performed trash pick-up services, contends that the Army’s rejection of its proposal for failure to submit a mobilization plan was arbitrary and capricious because Plaintiff was already fully mobilized and the Army, as a matter of past practice, had not required mobilization plans from incumbents.

Following the Court’s denial of a preliminary injunction, Plaintiff seeks to supplement the Administrative Record (AR) for a second time to add materials which it claims should have been included or are necessary to clarify the record or the Court’s decision. Specifically, Plaintiff seeks to have Defendant produce a mobilization plan of another incumbent contractor, Horizon Waste, Inc., on [430]*430a prior procurement and the Army’s assessment of that plan to show that the Army had a past practice of waiving requirements for mobilization plans for incumbent contractors. Even if Plaintiff could establish that the Army had waived the mobilization plan requirement for Horizon, that single waiver in a different procurement would not remotely constitute a “past practice” which would obligate the Army to ignore solicitation requirements and again waive that requirement here. As such, the requested discovery and supplementation would be futile and a waste of the parties’ resources.

In addition, Plaintiff seeks to supplement the record with documents indicating that the Army knew that Plaintiff owned its vehicles and containers, information that was required to be included in an offeror’s mobilization plan and proposal, but which IRRI failed to include. Such a post hoc explanation of an offeror’s capabilities not reflected in an offer- or’s proposal is not a proper basis for supplementing an administrative record.

Background

By Order dated February 13, 2004, the Court granted Plaintiffs request to depose two contracting officers (CO) and Defendant’s alternative request to depose Plaintiffs principal, Mr. Henry Johnson. On February 20, 2004, Plaintiff sought a preliminary injunction, and the Court denied such relief, finding that Plaintiff had failed to comply with a mandatory requirement of the solicitation calling for a mobilization plan, and that the Army was not obligated to waive that requirement for incumbents. International Resource Recovery, Inc. v. United States, 60 Fed.Cl. 1 (2004). On March 29, 2004, Plaintiff advised the Court that it would file a motion for judgment on the Administrative Record and seek a permanent injunction.

Plaintiff now seeks to supplement the Administrative Record, with the following documents:

1. The formal mobilization plan, if any, submitted by another incumbent, Horizon Waste, Inc., in a prior procurement, and any contemporaneous assessment of that plan;
2. Documentation of an Assignment of Claims dealing with a Government-approved financing arrangement for Plaintiffs vehicles and containers; and
3. Affidavit of Mr. Henry Johnson, IRRI’s principal, explaining the use and ownership of IRRI’s equipment, as of yet unfiled.2

In taking the depositions the Court had authorized, neither party requested or produced Horizon’s plan.3

In its decision denying a preliminary injunction, the Court concluded:

The lone incident memorialized in a 2001 memorandum did not establish that the Army had a past practice of waiving the requirement for a mobilization plan. Rather, that memorandum and the contracting officer’s testimony suggested that the incumbent had submitted a mobilization plan at that time which was evaluated in that procurement. Mr. Johnson’s testimony to the contrary is hearsay and unsupported by any documentary evidence. Finally, IRRI’s reliance on this so called “past practice” was not reasonable in the face of a solicitation that clearly required a mobilization plan, particularly where the Army would not have all the information necessary to make an informed selection without such a plan.

International Resource Recovery, 60 Fed.Cl. at 7.

[431]*431 Discussion

The Court will permit a party to supplement the administrative record in limited circumstances in order to “preserve a meaningful judicial review.” Vantage Assocs., Inc. v. United States, 59 Fed. Cl. 1, 13 (2003) (quotations omitted) (citations omitted); International Resource Recovery, 60 Fed.Cl. at 5-6 (supplementation of the record allowed where there is “a genuine need to supplement that record arising from the particular circumstances of a case”); Gentex Corp. v. United States, 58 Fed.Cl. 634, 648 (2003). As this Court recognized in GraphicData, LLC v. United States, 37 Fed.Cl. 771, 780 (1997):

While a disappointed bidder does not have the right to have a federal court substitute its judgment for that of the administrative agency, the bidder does have the right to introduce appropriate evidence to allow the court to determine whether the agency action was ‘arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law.’

In the instant case, the Court has already permitted the parties to engage in discovery and supplement the record with depositions. In ruling on the motion for preliminary injunction, the Court has considered the record, as supplemented, along with the legal arguments on injunctive relief. As explained below, neither the requested additional discovery nor the proposed additional supplementation will assist the Court in assessing whether the agency’s action was arbitrary or capricious or in considering again whether injunctive relief is warranted.

First, Plaintiff seeks to have Defendant produce a mobilization plan of another incumbent contractor, Horizon Waste, Inc., on a prior procurement and the Army’s assessment of that plan to show that the Army had a past practice of waiving solicitation requirements for mobilization plans for incumbent contractors.4 As grounds for its request, Plaintiff asserts that “the record is vague, confusing and inconclusive on the core issue of the protest” and that these materials should have been part of the Administrative Record. Plaintiffs Motion to Supplement the Administrative Record at 1. This request ignores the Court’s conclusion, in ruling on Plaintiffs Motion for Preliminary Injunction, that this “lone incident ... did not establish that the Army had a past practice of waiving the requirement for a mobilization plan.” International Resource Recovery, 60 Fed.Cl. at 7-8. Further, the Court held that “IRRI’s reliance on this so called ‘past practice’ was not reasonable in the face of a solicitation that clearly required a mobilization plan, particularly where the Army would not have all the information necessary to make an informed selection without such a plan.” Id. Thus, the Court concluded, as a matter of law, that a single instance of waiving such a requirement did not rise to the level of a “past practice,” which would warrant a reasonable incumbent offeror to forgo submitting a mobilization plan contrary to the clear requirements of a solicitation.

Free access — add to your briefcase to read the full text and ask questions with AI

International Resource Recovery, Inc. v. United States, 60 Fed. Cl. 428, 2004 U.S. Claims LEXIS 92, 2004 WL 874809 (uscfc 2004).

60 Fed. Cl. 428 (International Resource Recovery, Inc. v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

AEY, Inc. v. United States
99 Fed. Cl. 300 (Federal Claims, 2011)
Al Andalus General Contracts Co. v. United States
86 Fed. Cl. 252 (Federal Claims, 2009)
FFTF Restoration Co. v. United States
86 Fed. Cl. 226 (Federal Claims, 2009)
DCMS-ISA, Inc. v. United States
84 Fed. Cl. 501 (Federal Claims, 2008)
Spectrum Sciences v. United States
84 Fed. Cl. 716 (Federal Claims, 2008)
Data Computer Corp. of America v. United States
80 Fed. Cl. 606 (Federal Claims, 2008)
North Star Alaska Housing Corp. v. United States
76 Fed. Cl. 158 (Federal Claims, 2007)
L.P. Consulting Group, Inc. v. United States
66 Fed. Cl. 238 (Federal Claims, 2005)
International Resource Recovery, Inc. v. United States
61 Fed. Cl. 38 (Federal Claims, 2004)