Hammond v. Bechtel Inc.

606 P.2d 1269, 1980 Alas. LEXIS 516
CourtAlaska Supreme Court
DecidedFebruary 22, 1980
Docket3859
StatusPublished
Cited by30 cases

This text of 606 P.2d 1269 (Hammond v. Bechtel Inc.) is published on Counsel Stack Legal Research, covering Alaska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hammond v. Bechtel Inc., 606 P.2d 1269, 1980 Alas. LEXIS 516 (Ala. 1980).

Opinion

OPINION

Before RABINOWITZ, C. J., CONNOR, BOOCHEVER and BURKE, JJ., and DIMOND, Senior Justice.

RABINOWITZ, Chief Justice.

On July 12, 1974, Roy Hammond was injured when he stepped off a D-8 Caterpillar he had loaded onto a lowboy trailer and fell through a hole in the trailer. At the time of the accident, he was employed by General-Alaska-Stewart, a contractor engaged in the construction of the Happy Valley Camp on the Trans-Alaska Pipeline.

General-Alaska had a shop at Happy Valley for maintaining the equipment used in its construction activities. After the accident, Hammond had a conversation with a mechanic employed by General-Alaska at Happy Valley with regard to the condition of the lowboy trailer. Hammond’s deposition in this case, filed in the superior court, states that the General-Alaska mechanic told him that General-Alaska had been informed of the hole in the trailer and had been told to make the necessary repairs on *1271 several occasions. The deposition also states that the driver of the tractor used to pull the trailer told Hammond that “he had warned them five times to fix that [trailer] before someone got killed. . . . ” Hammond further stated that he had been given a similar account as to the contractor’s knowledge of the condition of the trailer by another mechanic who had been at the Happy Valley jobsite.

Bechtel was the Construction Management Contractor for the pipeline project. Bechtel’s contract with the Alyeska Pipeline Service Company, a consortium of several oil companies formed to build and manage the Trans-Alaska Pipeline, provided that for the purposes of the project Bechtel was to

[a]ct as ALYESKA’s representative during construction to administer Execution Contracts; monitor EXECUTION CONTRACTORS’ performance for quality, cost and schedule, ensuring appropriate and timely corrective actions where needed; and coordinate interfaces between these EXECUTION CONTRACTORS.

The contract further provided that Bechtel, in this representative capacity, was to have certain duties with respect to safety:

A. CMC [Bechtel] shall observe and abide by and require its subcontractors and the EXECUTION CONTRACTORS to observe and abide by all ALYESKA safety rules and all safety regulations and LAW, including but not limited to: State of Alaska General Safety Code, U.S. Department of Labor Safety and Health Regulations for Construction, and the Williams-Steiger Occupational Safety and Health Act of 1970, including any revisions of the foregoing that may hereinafter be applicable.
B. Said rules, laws, and regulations are designed as minimum requirements for CMC, and CMC shall take any additional precautions necessary or proper under the circumstances to prevent injury or death to persons and/or damages to property.

General-Alaska was an “execution contractor” in the terms of the pipeline contracts., 1 General-Alaska’s contract with Alyeska provided that it “is, and shall be deemed to be, an independent contractor and not the agent or employee of OWNERS or ALYESKA. Neither ALYESKA nor OWNERS shall have any authority to supervise the employees or representatives of [General-Alaska] and accomplishing WORK shall be under the supervision and control of [General-Alaska].” The contract provided that General-Alaska was to “furnish all supervision, consultation, construction services, labor, certain construction tools and equipment and other services as required for the proper field engineering and civil construction work,” and to “be responsible for safety related to and during the prosecution of WORK. . .” The contract further defined General-Alaska’s safety responsibilities in language similar to that used to define Bechtel’s duties in that regard as Construction Management Contractor, as quoted above.

On December 23, 1974, approximately five months after his accident, Hammond filed a tort action against Bechtel and Alyeska. He alleged that Bechtel had a contractual obligation to Alyeska to insure that defective equipment was not utilized on the pipeline, and claimed that he was a third-party beneficiary of this contract. He additionally alleged that, pursuant to the Alyeska/Bechtel contract, Bechtel was “in control of the project” and had “an express and absolute duty to provide adequate and proper safeguards.” Hammond asserted that Bechtel was acting as Alyeska’s agent and that, therefore, Alyeska was responsible for any breach of duty committed by Bechtel in this regard.

Defendants Bechtel and Alyeska subsequently moved for summary judgment. Their motion argued that Hammond’s employer General-Alaska was an independent *1272 contractor on the pipeline. Therefore, the motion asserted, neither Alyeska nor Bechtel had a duty to inspect or repair General-Alaska’s equipment, and neither was responsible for any negligence of General-Alaska with regard to equipment maintenance. With regard to Hammond’s claim that he was a third-party beneficiary of the contract between Bechtel and Alyeska, the motion asserted that Hammond was only an incidental and not an intended beneficiary of the contract, and thus lacked standing to file a suit based on any safety responsibilities assumed by Bechtel under that contract.

In support of this motion, Alyeska and Bechtel relied on the terms of the contracts between Alyeska and General-Alaska, summarized above. They also submitted an affidavit by V. S. Nielsen, Bechtel’s senior manager for the pipeline project, which stated in part:

4. Bechtel, as the Construction Management Contractor, did not have the authority to direct the method ánd manner of the work accomplished by the execution contractors.
5. Pursuant to Bechtel’s contract with Alyeska, Bechtel was not required to perform, and did not perform, maintenance on equipment used by the execution contractors. 2

Hammond’s argument in opposition to the motion for summary judgment included a list of genuine issues of material fact. The majority of these alleged issues were framed in terms of his claim that Bechtel had assumed the duty to inspect the equipment used in pipeline-related construction by Alaska-General and other “execution contractors,” and had the duty to ensure that General-Alaska not use dangerous or defective equipment, as well as the necessary control or power over General-Alaska’s operations to perform that duty. Hammond also argued that he had standing to sue Bechtel for breach of its safety responsibilities under its contract with Alyeska, since he was a member of the class of persons intended as beneficiaries of those provisions of the contract.

Hammond’s arguments relied on his deposition and affidavit filed with the superior court. The affidavit stated in part:

2. During the time I was employed by General-Alaska-Stewart there were constantly on the job safety inspectors employed by Bechtel and wearing Bechtel identification tags and caps whose responsibilities included inspection of equipment utilized by General-Alaska on the job.
3.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jason Earl Andrew Ness, Et Ano., V. Abb, Inc.
Court of Appeals of Washington, 2025
Cannon v. Fournier
57 So. 3d 875 (District Court of Appeal of Florida, 2011)
Hauptman v. WMC, INC.
224 P.3d 1175 (Court of Appeals of Kansas, 2010)
Mellon v. Shriners Hospitals for Children
22 Mass. L. Rptr. 544 (Massachusetts Superior Court, 2007)
Anderson v. PPCT Management Systems, Inc.
145 P.3d 503 (Alaska Supreme Court, 2006)
Powell v. Tanner
59 P.3d 246 (Alaska Supreme Court, 2002)
City of Seward v. Afognak Logging
31 P.3d 780 (Alaska Supreme Court, 2001)
Petranovich v. Matanuska Electric Ass'n
22 P.3d 451 (Alaska Supreme Court, 2001)
Plummer v. Bechtel Construction Co.
489 N.W.2d 66 (Michigan Supreme Court, 1992)
Madler v. McKenzie County
467 N.W.2d 709 (North Dakota Supreme Court, 1991)
Werdehausen v. Union Electric Co.
801 S.W.2d 358 (Missouri Court of Appeals, 1990)
Cuffe v. Sanders Construction Co.
748 P.2d 328 (Alaska Supreme Court, 1988)
Sievers v. McClure
746 P.2d 885 (Alaska Supreme Court, 1987)
Jackson v. Power
743 P.2d 1376 (Alaska Supreme Court, 1987)
Corsetti v. Stone Co.
483 N.E.2d 793 (Massachusetts Supreme Judicial Court, 1985)
Parker Drilling Co. v. O'NEILL
674 P.2d 770 (Alaska Supreme Court, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
606 P.2d 1269, 1980 Alas. LEXIS 516, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hammond-v-bechtel-inc-alaska-1980.