Florida Power & Light Company v. Westinghouse Electric Corporation

826 F.2d 239, 1987 U.S. App. LEXIS 10874
CourtCourt of Appeals for the Fourth Circuit
DecidedAugust 12, 1987
Docket85-1089
StatusPublished
Cited by25 cases

This text of 826 F.2d 239 (Florida Power & Light Company v. Westinghouse Electric Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Florida Power & Light Company v. Westinghouse Electric Corporation, 826 F.2d 239, 1987 U.S. App. LEXIS 10874 (4th Cir. 1987).

Opinion

DONALD RUSSELL, Circuit Judge:

This litigation had its beginning over two decades ago, though actual litigation has been in progress only a little over a decade. During this period the development of a program of peaceful use of nuclear power as authorized by Congress, begun with such enthusiasm, has since experienced a chequered career, marked by many changes in official policy and subjected to increasing regulatory and judicial constraints. All of these circumstances have contributed to the complexities and difficulties of the present litigation. In its court life of a little over a decade this litigation has generated thousands of pages of trial and discovery testimony and has produced for the record innumerable exhibits, some of an extremely technical nature. Highly expert engineering and scientific testimony and records have been developed. The result has been three separate district court decisions, spread over about four years, which have not been consistent. It is our task on this appeal to resolve the issues that have arisen in the litigation over the last decade in these contradictory decisions.

I.

The subject of the action is a contract between the appellee, Florida Power & Light Company (Florida), and the appellant, Westinghouse Electric Corporation (Westinghouse). This contract had its source in the early 60’s when Florida determined to give careful consideration to the construction of a nuclear power plant or plants at Turkey Point, in the State of Florida. Florida’s interest in such a development was prompted by the high cost to it of transporting coal or oil necessary for firing its electric generating plants. Nuclear power was thought likely to provide Florida with a less expensive alternative to coal or oil for its power generation. Florida invited three concerns experienced in providing nuclear power plants to submit detailed proposals for the plant it was considering. These concerns were the defendant Westinghouse, the General Electric Corporation, and Babcock & Wilcox. Only Westinghouse and General Electric Corporation, however, responded to Florida’s invitation with complete proposals. The proposals of the two were carefully compared and evaluated by Florida over a considerable period of time. Florida finally settled on Westinghouse as its supplier, selecting the latter’s pressurized water reactor (PWR) as the favored facility. Florida, in announcing the signing of the contract of purchase with Westinghouse, said the facility selected had “been operating successfully for several years in commercial generating stations” both in this country and abroad.

After Westinghouse and its PWR facility had been chosen by Florida, the parties engaged in the drafting of a definitive purchase contract. The contract negotiations proceeded over a number of months. In the course, drafts were exchanged between the parties. The district court found that, while Westinghouse was supposedly more expert in the field of nuclear energy, Florida was more expert in the drafting of agreements and that it had demonstrated this superior expertise by “out-negotiating” Westinghouse in negotiating the ultimate purchase contract. Whether Westinghouse was “out-negotiated” or not is, however, irrelevant in this context since *241 the contract was freely and voluntarily executed by the parties. Under the contract executed Westinghouse, in consideration of Florida’s agreements, obligated itself (1) to supply Florida with a Westinghouse PWR-type nuclear power installation, (2) to furnish at a fixed price the uranium to be required for the first ten years of the plant’s operations, and (3) to grant Florida an option to exercise one of three options for the disposal of the spent fuel discharged by the plant’s reactors for the first ten years of the plant’s operations. One of the options (Option A) contemplated disposal of the spent fuel by Florida; the other two, with some minor variations, (Options B and C) provided for disposal by Westinghouse. Florida was required to exercise its option on or before “initial criticality” (i.e., before the plant became operational).

Initial criticality, namely when the plants became operational, (the contract had been expanded after initial execution of the contract to include the furnishing of a second plant) was reached in October of 1972 for the first plant and in June, 1973 for the second. The two plants have been successfully operated since completion with considerable savings to Florida and its customers in energy costs. While there was a dispute between the parties with respect to that part of the contract which imposed on Westinghouse the obligation to furnish uranium at a fixed price for the first ten years of the plants’ operations, this controversy has been settled between the parties and is not an issue on this appeal. The only part of the contract involved in this appeal is that section dealing with the disposal of spent fuel. In October, 1972, Florida formally elected to require Westinghouse to dispose of the spent fuel discharged by the plants’ reactors under Option C of the contract. It had, though, earlier in 1970 informally [and in 1972 formally] informed Westinghouse that it was electing to require Westinghouse to do this.

Option C is set forth in Section 27(a)(2) of the contract. It is:

Section 27. Scope

(a) Westinghouse will:
(2) Remove the irradiated fuel from the Plant site and dispose of it as Westinghouse sees fit;

Earlier in 1969, Westinghouse had, with the knowledge of Florida and on the assumption it might be required by Florida to dispose of the spent fuel at the plant, begun discussions with Allied General Nuclear Services (AGNS) which had a construction permit from the Atomic Energy Commission (AEC) to construct a reprocessing plant at Barnwell, South Carolina, 1 for the purpose of securing reprocessing of the Turkey Point spent fuel at AGNS’s reprocessing plant then under construction as a means of disposing of the Turkey Point spent fuel. By April, 1970, these negotiations resulted in a letter of intent between Westinghouse and AGNS for the reprocessing of such spent fuel at the Barnwell plant “subject to the negotiation of a mutually acceptable agreement.” The parties arrived at an unsigned agreement in 1974. AGNS, however, refused to sign the agreement. As summarized in a Westinghouse memorandum, AGNS

“claimed that its contracts, including a letter of intent agreement with W[estinghouse] were no longer valid and must be renegotiated. AGNS claim[ed] that changing government regulations [had] increased its costs several times. They *242 are currently seeking government aid in several areas to assure their ability to run the facility. W[estinghouse] and AGNS have discussed several proposals since AGNS refused to sign the original contract in 1974. These proposals have been open ended on the cost to W[estinghouse] while maintaining a degree of profit for AGNS. W[estinghouse] continues to maintain its position that these proposals are not consistent — with the letter of intent and draft agreement agreed on by the parties.”

AGNS itself stated its reasons for refusing to execute the agreement in a formal letter to Westinghouse dated March 28, 1974:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Averett v. Hardy
W.D. Kentucky, 2023
Ko v. Messer
E.D. New York, 2021
Begay v. United States
188 F. Supp. 3d 1047 (D. New Mexico, 2016)
Dairyland Power Cooperative v. United States
90 Fed. Cl. 615 (Federal Claims, 2009)
Wisconsin Electric Power Co. v. United States
90 Fed. Cl. 714 (Federal Claims, 2009)
Ner Tamid Congregation of N. Town v. Krivoruchko
638 F. Supp. 2d 913 (N.D. Illinois, 2009)
Southern Nuclear Operating Co. v. United States
77 Fed. Cl. 396 (Federal Claims, 2007)
Yankee Atomic Electric Co. v. United States
73 Fed. Cl. 249 (Federal Claims, 2006)
South Carolina ex rel. Campbell v. O'Leary
64 F.3d 892 (Fourth Circuit, 1995)
Phoenix Mutual Life Insurance v. Adams
828 F. Supp. 379 (D. South Carolina, 1993)
Transdulles Center, Inc. v. USX Corp.
976 F.2d 219 (Fourth Circuit, 1992)
G.C. Murphy Co. v. M. Goldfarb-My Florist Inc.
11 Pa. D. & C.4th 614 (Alleghany County Court of Common Pleas, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
826 F.2d 239, 1987 U.S. App. LEXIS 10874, Counsel Stack Legal Research, https://law.counselstack.com/opinion/florida-power-light-company-v-westinghouse-electric-corporation-ca4-1987.