United States for the Use and Benefit of Jay Worch Electric, LLC v. Atlantic Specialty Insurance Company

CourtDistrict Court, D. Maryland
DecidedMay 21, 2024
Docket8:22-cv-02420
StatusUnknown

This text of United States for the Use and Benefit of Jay Worch Electric, LLC v. Atlantic Specialty Insurance Company (United States for the Use and Benefit of Jay Worch Electric, LLC v. Atlantic Specialty Insurance Company) is published on Counsel Stack Legal Research, covering District Court, D. Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States for the Use and Benefit of Jay Worch Electric, LLC v. Atlantic Specialty Insurance Company, (D. Md. 2024).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF MARYLAND

UNITED STATES OF AMERICA FOR * THE USE AND BENEFIT OF JAY WORCH * ELECTRIC, LLC d/b/a JWE, LLC, * * Plaintiff, * * Civil Action No. 8:22-cv-02420-PX * v. * * ATLANTIC SPECIALTY INSURANCE * COMPANY, et al., * * Defendants. * *** MEMORANDUM OPINION Pending before the Court in this contract dispute is the motion for summary judgment filed by Plaintiff United States of America for the Use and Benefit of Jay Worch Electric, LLC d/b/a JWE, LLC (“JWE”). ECF No. 26. No hearing is necessary. D. Md. Loc. R. 105.6. For the following reasons, the motion is granted in part and deferred in part. I. Background Unless otherwise noted, the following facts are undisputed and construed most favorably to Defendants Pontiac Drywall Systems, Inc. d/b/a PDSI Contractors (“PDSI” or the “contractor”) and Atlantic Specialty Insurance Company (“ASIC” or the “surety”) as the non- moving parties. This case arises out of a government contract awarded to PDSI to install lighting at a parking lot on the Naval Air Station in Patuxent River, Maryland. See ECF No. 26-1 at 2; ECF No. 27 at 2. On September 29, 2021, in connection with the project, ASIC issued a payment bond identifying PDSI as the principal contractor.1 See id.

1 PDSI secured ASIC as a surety pursuant to its obligations under the Miller Act, which requires government contractors to post a surety bond “for the protection of all persons supplying labor and material in carrying out the work provided for in the contract.” 40 U.S.C. § 3131(b)(2). On October 15, 2021, JWE and PDSI entered into a written Subcontract Agreement (the “Subcontract”), in which JWE, as subcontractor, would perform $159,259 of electrical work on the project. See ECF No. 11-1 at 7. Under the Subcontract, PDSI and JWE agreed that “progress payments will be made to [JWE] on a monthly basis for [JWE’s] Work performed through the

preceding month.” ECF No. 11-1 at 10. As a condition precedent for payment, the Subcontract required that JWE submit a “draft copy of pay requests” to PDSI “no later than Monday noon of the 3rd week for each month.” Id. at 5. Upon review and approval of such payment requests, JWE was also required to submit “a signed Partial Conditional Waiver and Release . . . [and] a duly executed Sworn Statement” as a condition of payment. Id. at 11. Last, the Subcontract conditioned payment to JWE on the Navy’s payment to PDSI for the work performed. Id. at 23 (payment “will be issued within 7 business days” from PDSI being paid for the work as the prime contractor). Notably, the Subcontract did not address the how PDSI would make payment to JWE. That is, the Subcontract was silent on to whom the payment would be directed and on the relative

responsibility for payment if PDSI’s efforts to pay were thwarted, whether by error, inadvertence, or third-party interference. See ECF No. 11-1 at 8–18. On May 23, 2022, JWE invoiced PDSI for work performed. See ECF No. 28-7 at 3–4. JWE President, Jay Worch (“Worch”), emailed PDSI the invoice for this payment, using his correct email address, which ends in “.com.” See id.; ECF No. 26-2 ¶ 7. The next day at 2:30 p.m., PDSI Project Manager, Laith Sadik (“Sadik”), responded by email to the .com address. See ECF No. 28-8 at 3. Sadik confirmed that PDSI would pay JWE $58,850 of the invoiced amount and explained why. See id. Some 50 minutes later, Sadik received an email from an address identical to Worch’s, except that this address ended in “.net” instead of “.com.” See ECF No. 27-2 at 4. This .net email also included the same signature block for Worch with the same title and contact numbers as in the .com email. Compare id. at 4– 5, with ECF No. 28-7 at 4. The email from the .net addressee represented to Sadik that because JWE’s primary bank account “is under review,” all payments had to be made “directly into [its] Corporate account via

ACH only.” ECF No. 27-2 at 4. The .net addressee also urged that payment be made “tomorrow.” Id. Six hours later, at 9:16 p.m., Sadik responded to the .net email, explaining that because the Navy must still approve payment, PDSI would not be able to pay JWE “tomorrow” as requested. Id. On May 31, 2022, Sadik received another email from the .net addressee that asked if payment would be made within the week, and that it would “forward our updated ACH bank details” to PDSI. ECF No. 27-2 at 2. It is unclear from the record whether Sadik responded to this email. See id. But about a week later, on June 8, 2022 at 2:06 p.m., Worch, using the .com email, sent PDSI a revised invoice for $58,850. See ECF No. 28-9. At the same time, the .net addressee also sent a revised invoice identical to that which Worch had submitted. See ECF No.

11-8 at 7–8. PDSI however, has no record of receiving the revised invoice from the .com email; it received only the one from the .net email. See ECF No. 27-1 ¶ 19. Approximately three hours later, Sadik responded by emailing Worch at his .com address a waiver and sworn statement that had to be completed prior to payment. See ECF No. 28-6 at 3. Worch, in response, emailed signed versions of the documents to Sadik along with directions to send the “check” for payment to JWE’s address in Lexington Park, Maryland. See ECF No. 28-4 at 2; ECF No. 28-3 ¶ 5. Around the same time, PDSI payroll accountant, Melinda Transou (“Transou”), received an email from the .net addressee, pressing her for payment on the invoice via wire transfer. See ECF No. 11-8 at 3–7. When Transou resisted, the .net addressee snapped “I told you several times, we can’t receive check [sic] but since you insist, Can you mail out the check to my partner’s address? Let me know so I can send the name to be written on check [sic] and address.” Id. at 4.

Ultimately the .net addressee acceded to payment by check. The .net addressee provided payment directions to include that the check be made payable to “Yvens Carlo Vante” and mailed to a Bridgeport, Connecticut address. See ECF No. 11-8 at 3. In response, Transou asked for the .net addressee to sign the same waiver and sworn statement that Worch had signed for Sadik the day before. Id. at 2. The next day, the .net addressee emailed the identical notarized waiver and sworn statement that Jay Worch had previously supplied. Compare id. at 9–11, with ECF No. 28-4 at 3–5. PDSI, in turn, mailed the check for $58,850 to Vante at the Bridgeport, Connecticut address. See ECF No. 11-9 at 2. No evidence suggests that Vante or the Bridgeport, Connecticut address is affiliated with JWE. Predictably, JWE never received payment. See ECF No. 26-2 ¶ 5. However, the $58,850

funds cut to Vante were deposited in an account at JP Morgan Chase (“Chase Bank”). See ECF No. 25 at 2. Although not altogether clear from the record, the bank appears to have frozen the assets in connection with an investigation into the fraudulent activities behind the .net addressee. See id. To the Court’s knowledge, the funds remain with Chase Bank. See id. On September 22, 2022, JWE filed suit against PDSI for breach of contract and against Defendants for a companion Miller Act claim. ECF No. 1 ¶¶ 8–21. The parties have since resolved all issues save for whether PDSI breached the Subcontract in failing to pay JWE the $58,850, and ASIC’s companion liability under the Miller Act as a surety. See ECF No. 27-1 ¶ 2. JWE now seeks summary judgment in its favor on both claims, arguing that no genuine issue of disputed fact exists as to PDSI’s breach in its failure to pay for $58,850 worth of work performed. See ECF No. 26. II. Standard of Review Summary judgment is appropriate when the Court, viewing the evidence in the light most

favorable to the non-moving party, finds no genuine disputed issue of material fact, entitling the movant to judgment as a matter of law.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States Ex Rel. Sherman v. Carter Constr. Co.
353 U.S. 210 (Supreme Court, 1957)
Emmett v. Johnson
532 F.3d 291 (Fourth Circuit, 2008)
Panitz v. Panitz
799 A.2d 452 (Court of Special Appeals of Maryland, 2002)
Taylor v. NationsBank, N.A.
776 A.2d 645 (Court of Appeals of Maryland, 2001)
Sy-Lene of Washington, Inc. v. Starwood Urban Retail II, LLC
829 A.2d 540 (Court of Appeals of Maryland, 2003)
Peters v. Jenney
327 F.3d 307 (Fourth Circuit, 2003)
Bouchat v. Baltimore Ravens Football Club, Inc.
346 F.3d 514 (Fourth Circuit, 2003)
Williams v. Giant Food Inc.
370 F.3d 423 (Fourth Circuit, 2004)
World of Boxing LLC v. King
56 F. Supp. 3d 507 (S.D. New York, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
United States for the Use and Benefit of Jay Worch Electric, LLC v. Atlantic Specialty Insurance Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-for-the-use-and-benefit-of-jay-worch-electric-llc-v-mdd-2024.