Commonwealth Edison Co. v. Allied-General Nuclear Services

731 F. Supp. 850
CourtDistrict Court, N.D. Illinois
DecidedMarch 6, 1990
Docket79 C 2866
StatusPublished
Cited by20 cases

This text of 731 F. Supp. 850 (Commonwealth Edison Co. v. Allied-General Nuclear Services) is published on Counsel Stack Legal Research, covering District Court, N.D. Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Commonwealth Edison Co. v. Allied-General Nuclear Services, 731 F. Supp. 850 (N.D. Ill. 1990).

Opinion

OPINION AND ORDER

POSNER, Circuit Judge (sitting by designation).

Ten years ago, Commonwealth Edison filed this suit for breach of contract against Allied-General Nuclear Services (AGNS), a partnership of companies, and against the partners themselves. A diversity suit governed (pursuant to the choice of law provision in the contract) by New York law, it had bounced from judge to judge over the years until it fell into my lap when I volunteered to assist the Northern District of Illinois in clearing its growing backlog of civil jury cases. On October 19, 1989, I issued an order resolving a number of open questions. Before me now are a number of other motions, three of which— motions for partial summary judgment— are both fundamental in defining the scope of the trial (which will begin on March 19, 1990) and of sufficient general interest to warrant a published opinion.

The complexity of the issues and the importance of this decision to the scope of the lawsuit persuaded me that it would be prudent to solicit the parties' views before making the decision final, so on January 30 I issued a proposed opinion and directed the parties to submit by February 9 briefs setting forth any disagreements they might have with the findings and conclusions in it. I stated that any objection not made in the briefs would be deemed waived. The briefs have been submitted and the matter is now ripe for decision. It should go without saying that this opinion supersedes the proposed one, from which it differs, indeed, in important respects.

A complex, high-stakes case between two large law firms often develops a life of its own. That has happened here. In their relentless pursuit of the “facts,” the parties have lost sight of the central legal issues. I am convinced that there is only one, minor, triable issue of liability; the trial will be confined for the most part to limited issues of damages.

Some background will be necessary to make these conclusions understandable. Commonwealth Edison owns and operates nuclear power plants. In these plants, fuel manufactured from uranium undergoes fission, producing heat that makes steam to drive turbines that generate electricity. Eventually the fuel becomes depleted of fissionable material and must be discharged from the reactor and replaced by new fuel. The spent fuel contains, however, some uranium, which can be extracted and used to manufacture new fuel. The beauty of reprocessing spent nuclear fuel is that it not only reclaims what would otherwise be a waste product but also helps solve the vexing problem of how to dispose of spent nuclear fuel safely. The spent fuel is highly radioactive and no one has come up with a method for permanently storing it that is proof against contamination of the soil or water in which it is stored. As a result, most such fuel remains on site at the nuclear power plant, stored in pools of water to await the ever-receding day when a permanent home for it will be found, and taking up more and more room as the operation of the plant throws off a growing accumulation of spent fuel.

All is not rosy, however, with the idea of reprocessing nuclear fuel. Reprocessing produces plutonium as a byproduct, and plutonium is the key component of nuclear weapons. Some people fear that widespread commercial reprocessing would promote nuclear proliferation and in particular make it easier for terrorists to obtain the components for assembling nuclear weapons. Westinghouse Electric Corp. v. United States, 598 F.2d 759, 762 n. 4 (3d Cir.1979).

*853 In 1971 Edison issued a request for bids to supply it with reprocessing services for spent nuclear fuel. AGNS, a partnership formed to build a large commercial nuclear reprocessing plant in Barnwell, South Carolina, responded to the request. In 1974— at the height of interest in nuclear power following the run-up in oil prices after the Arab-Israeli war in October 1973, and against a background of governmental efforts to encourage reprocessing, Allied-General Nuclear Services, Inc. v. United States, 12 Cl.Ct. 372, 388-90 (1987), aff'd in part, rev’d in part, 839 F.2d 1572 (Fed.Cir.1988)—the parties signed the contract that is the subject of this suit. The contract requires AGNS to reprocess at Edison’s request any spent fuel discharged by designated nuclear power plants of Edison through 1979 and to deliver the reprocessed fuel to Edison.

A potential hitch evident to the parties at the time of the negotiations was that although the Nuclear Regulatory Commission had issued a construction permit for the Barnwell plant, and the plant was fairly close to completion, the Commission had not yet issued an operating license and until AGNS had that it could not lawfully reprocess nuclear fuel. Edison was concerned that AGNS might drag its feet in obtaining a license until it had signed up enough other electrical utilities to be able to operate Barnwell at full capacity. Section 16 of the contract, the Facility Contingency Plan, was intended to respond to this concern. Section 16.1(a) provides that “subject to paragraph (b) below, this Agreement shall be construed as [AGNS’s] unequivocal commitment to (1) be ready to process fuel or (2) to have such fuel processed by others by not earlier than one hundred twenty (120) days after any discharge [i.e., removal of spent fuel from the reactor core] and by not later than (i) twelve (12) months after the discharge hereunder or (ii) December, 1975, whichever is later.” Paragraph (b) provides, so far as relevant here, that if Edison makes its demand under (a) “on or before a date which, except for reasons of force majeure (provided, however, with regard to commencement of commercial operation, failure to obtain an operating license shall not be deemed a force majeure reason), is prior to the commencement of commercial operation of [the Barnwell] Plant,” then AGNS shall be required to deliver “fissile material equivalent to that which would have been recovered from the fuel” discharged by Edison if Barnwell had reprocessed it. In other words, if the plant was not in operation when AGNS was required by paragraph (a) to accept Edison’s spent fuel for reprocessing, AGNS would have to provide equivalent fuel unless the plant was not in operation for force majeure reasons other than AGNS’s “failure to obtain an operating license” for the Barnwell plant. A mere failure to obtain an operating license would not excuse AGNS’s failure to perform even if AGNS had sought a license diligently. But it is equally important to note, in view of Edison’s reiterated observation that nothing ever occurred to make the supplying of equivalent fissile material impossible, that when and if AGNS was prevented by causes that do count as force majeure from placing Barnwell into commercial operation, it was excused from supplying equivalent fissile material whether or not it would have been possible or practicable to supply it.

The operating license has never been issued. In 1975 the Nuclear Regulatory Commission delayed the issuance of any operating licenses for nuclear fuel reprocessing plants pending hearings to determine the environmental impact of such reprocessing. Mixed Oxide Fuel, 40 Fed. Reg. 53056, corrected, 40 Fed.Reg. 59497 (1975). The Commission decided in the same order to grant interim operating licenses, 40 Fed.Reg. at 53061, but this decision was reversed in National Resources Defense Council, Inc. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Private Jet Servs. Grp. v. Tauck, Inc.
2024 N.H. 20 (Supreme Court of New Hampshire, 2024)
55 Oak Street LLC v. RDR Enterprises, Inc.
2022 ME 28 (Supreme Judicial Court of Maine, 2022)
Hitz Restaurant Group
N.D. Illinois, 2020
Ner Tamid Congregation of N. Town v. Krivoruchko
638 F. Supp. 2d 913 (N.D. Illinois, 2009)
Pillsbury Co., Inc. v. Wells Dairy, Inc.
752 N.W.2d 430 (Supreme Court of Iowa, 2008)
City of Starkville v. 4-COUNTY ELECTRIC POWER ASSN.
819 So. 2d 1216 (Mississippi Supreme Court, 2002)
Watson Laboratories, Inc. v. Rhone-Poulenc Rorer, Inc.
178 F. Supp. 2d 1099 (C.D. California, 2001)
Horwitz-Matthews, Incorporated v. City of Chicago
78 F.3d 1248 (Seventh Circuit, 1996)
New York v. United States
942 F.2d 114 (Second Circuit, 1991)
State of New York v. United States
942 F.2d 114 (Second Circuit, 1991)
Babcock & Wilcox Co. v. Allied-General Nuclear Services
161 A.D.2d 350 (Appellate Division of the Supreme Court of New York, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
731 F. Supp. 850, Counsel Stack Legal Research, https://law.counselstack.com/opinion/commonwealth-edison-co-v-allied-general-nuclear-services-ilnd-1990.