Caddell Construction Co. v. United States

32 Cont. Cas. Fed. 73,206, 7 Cl. Ct. 236, 1985 U.S. Claims LEXIS 1074
CourtUnited States Court of Claims
DecidedJanuary 11, 1985
DocketNo. 7-85C
StatusPublished
Cited by20 cases

This text of 32 Cont. Cas. Fed. 73,206 (Caddell Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Caddell Construction Co. v. United States, 32 Cont. Cas. Fed. 73,206, 7 Cl. Ct. 236, 1985 U.S. Claims LEXIS 1074 (cc 1985).

Opinion

OPINION and ORDER

HARKINS, Judge:

On January 7, 1985, plaintiff filed a complaint seeking injunctive and declaratory relief related to a solicitation of the Department of the Navy for a contract to construct a submarine headquarters administrative building at Kings Bay, Georgia. On January 8, 1985, plaintiff filed its application for a preliminary injunction, and an order for a hearing was entered January 8, 1985. Pursuant to the order, a hearing was held on January 10, 1985, on plaintiff’s complaint and application for a preliminary injunction, plaintiff’s motion to advance and consolidate trial on the merits with preliminary injunction hearing, and defendant’s motion to dismiss. At the start of the hearing, Harry L. Griffin, Jr., verbally moved that Black-Bodenhamer, A Joint Venture, and low bidder on IFB No. N68248-85-B-5016, be permitted to intervene and participate in this proceeding. Mr. Griffin’s motion was allowed.

During the proceedings, plaintiff called one witness, John Caddell, and intervenor called one witness, Douglas M. Bodenhamer. Depositions taken in the District Court proceeding captioned Caddell Construction Co., Inc. v. John F. Lehman, Jr., et al., 599 F.Supp. 1542, District Court for the Southern District of Georgia, Brunswick Division, and exhibits proferred by the parties were admitted.

Pursuant to the January 8, 1985, order, plaintiff filed a brief in support of its application, and requested findings of fact, conclusions of law, and order. Defendant filed a supplement to its opposition to plaintiff’s request for injunctive relief, and an affidavit by James S. Beyer.

On consideration of the pleadings, affidavits, depositions, and the record of the January 10, 1985, proceeding, the following findings of fact and conclusions of law are made.

FINDINGS OF FACT

1. This case involves IFBs issued by the Officer in Charge of Construction TRIDENT (OICC TRIDENT), St. Marys, Georgia, a unit of the Naval Facilities Engineering Command (NAVFAC), for the construction of a combined Submarine Base Administrative Building and Communications Building (Admin Building). NAVFAC TRIDENT determined that only small business concerns would be eligible for award of the contract to construct the Admin Building.

2. On September 21, 1984, IFB No. N68248-82-B-2016 (IFB 2016) was issued for the construction of the Admin Building. Copies of the IFB were sent to more than 800 firms believed to be interested in bidding on the project; 249 companies requested and were sent copies of the IFB plans and specifications. The IFB provided that sealed bids would be publicly opened on November 1, 1984.

Paragraph 10 of the IFB, captioned “Award of Contract” provided:

(b) The Government may, when in its interest, reject any or all bids or waive any informality in the bids received.

On October 17, 1984, OICC TRIDENT issued two amendments to the IFB plans and specifications.

3. The bids were opened and publicly announced on November 1, 1984; two companies had submitted bids. Caddell Construction Co., Inc. (plaintiff) bid $8,310,000, and was the apparent low bidder. The other bid was $8,520,000, submitted by the Robert Gay Construction Company, Jacksonville, Florida (Gay). The Government estimate of $7,300,000 was announced at the bid opening. Plaintiff’s bid was 13.8% above the Government estimate and Gay’s bid was 16.7% above the Government estimate.

[239]*2394. The past procurement experience of OICC TRIDENT established that the advertisement of small business set aside contracts similar to that for the construction of the Admin Building generally resulted in the receipt of from 5 to 15 bids, many being in amounts well below the Government estimate.

5. On November 1, 1984, OICC TRIDENT directed the IFB be reviewed for errors and ambiguities. The review included inquiries to companies that had submitted bids on such projects in the past, and inquiries to some of the companies to which copies of the IFB had been sent.

6. On November 2, 1984, one day after bids on IFB 2016 were opened, an announcement advertising the re-solicitation of the Project was sent to the Commerce Business Daily (CBD), a publication of the Commerce Department, for inclusion in the November 8, 1984, issue of the CBD.

7. During this review of the IFB, OICC TRIDENT personnel discovered an error in the provision concerning liquidated damages for unexcused delays in completing the project. Pursuant to formulas contained in the NAVFAC Contracting Manual (P-68), the liquidated damages should have been set at approximately $1,600 per day. Due to an administrative error, Amendment, No. 0001 to the IFB stated the contractor’s anticipated liability for delay could be in excess of $11,000 per day, more than seven times the proper amount. Review of the IFB revealed other errors, omissions and ambiguities in the specification for the irrigation system, vault, borrow site, and the chilled water system. OICC TRIDENT concluded the IFB required items that were in excess of the Government’s needs (Contractor Quality Control (CQC) plan and installation of fire alarm system), not appropriate for purchase using military construction funds (telephone), or better deferred until a later date in order to insure compatibility with future construction plans (fiber-optics communication systems). OICC TRIDENT concluded the Government’s estimate for the project was reasonable.

8. The error in liquidated damages had a negative impact on the number of the bids and tended to inflate bid prices. Some concerns did not submit bids because of concern for the potential impact of the liquidated damages clause.

9. Because of the excessive bid prices and the errors in the IFB, OICC TRIDENT decided on November 6, 1984, to cancel IFB 2016 and readvertise a revised project. On November 15, 1984, OICC TRIDENT issued IFB No. N68248-85B-B-5016 (IFB 5016). IFB 5016 established a bid opening date of December 18, 1984.

10. The project as revised in IFB 5016 established three phases for the completion of the work: Phase I, the Communications Center; Phase II, the Administration Building proper; and Phase III, the site work. Liquidated damages were $600 per day for Phase I, $900 per day for Phase II, and $100 per day for Phase III. The maximum daily liquidated damages was limited to $1,600 per day.

IFB 5016 eliminated the fiber optics and telephone systems, clarified the location of the borrow pit, reduced the requirements for the contractor quality control program, and deleted the requirement to install the fire alarm system.

11. On November 7, 1984, OICC TRIDENT advised plaintiff by letter that all bids under IFB 2016 were being rejected and that “This action is being taken due to all bids received being substantially in excess of the Government estimate for this work.”

On November 26, 1984, OICC TRIDENT rejected plaintiff’s request for a meeting to review the Government’s estimate for IFB 2016. The letter states:

We are required to make a determination that the prices offered are reasonable prior to making an award. In addition to determining that the bid price was unreasonable based on a validated comparison with the government’s estimate, the Officer in Charge of Construction (OICC), TRIDENT discovered that some requirements were defectively specified, con[240]*240tract completion phasing was inappropriate and inaccurate liquidated damages were set forth.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Manson Constraction Co. v. United States
64 Fed. Cl. 746 (Federal Claims, 2005)
First Enterprise v. United States
61 Fed. Cl. 109 (Federal Claims, 2004)
Process Control Technologies v. United States
53 Fed. Cl. 71 (Federal Claims, 2002)
Griffy's Landscape Maintenance LLC v. United States
51 Fed. Cl. 667 (Federal Claims, 2001)
Brickwood Contractors, Inc. v. United States
49 Fed. Cl. 148 (Federal Claims, 2001)
Overstreet Electric Co. v. United States
47 Fed. Cl. 728 (Federal Claims, 2000)
California Marine Cleaning, Inc. v. United States
42 Cont. Cas. Fed. 77,398 (Federal Claims, 1998)
Aero Corp., S.A. v. United States
41 Cont. Cas. Fed. 77,144 (Federal Claims, 1997)
IMS Services, Inc. v. United States
40 Cont. Cas. Fed. 76,784 (Federal Claims, 1995)
Croman Corp. v. United States
39 Cont. Cas. Fed. 76,698 (Federal Claims, 1994)
Arthur Forman Enterprises, Inc. v. United States
37 Cont. Cas. Fed. 76,079 (Court of Claims, 1991)
Vanguard Security Inc. v. United States
20 Cl. Ct. 90 (Court of Claims, 1990)
Carothers Construction Inc. v. United States
35 Cont. Cas. Fed. 75,758 (Court of Claims, 1989)
John C. Grimberg Company, Inc. v. The United States
869 F.2d 1475 (Federal Circuit, 1989)
Honeywell, Inc. v. United States
35 Cont. Cas. Fed. 75,611 (Court of Claims, 1989)
Aviation Enterprises, Inc. v. United States
32 Cont. Cas. Fed. 73,403 (Court of Claims, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
32 Cont. Cas. Fed. 73,206, 7 Cl. Ct. 236, 1985 U.S. Claims LEXIS 1074, Counsel Stack Legal Research, https://law.counselstack.com/opinion/caddell-construction-co-v-united-states-cc-1985.