Carothers Construction Inc. v. United States

35 Cont. Cas. Fed. 75,758, 18 Cl. Ct. 745, 1989 U.S. Claims LEXIS 255, 1989 WL 143515
CourtUnited States Court of Claims
DecidedNovember 29, 1989
DocketNo. 564-89C
StatusPublished
Cited by4 cases

This text of 35 Cont. Cas. Fed. 75,758 (Carothers Construction Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Carothers Construction Inc. v. United States, 35 Cont. Cas. Fed. 75,758, 18 Cl. Ct. 745, 1989 U.S. Claims LEXIS 255, 1989 WL 143515 (cc 1989).

Opinion

OPINION

FUTEY, Judge.

This pre-award contract action is before the court on defendant’s motion for summary judgment and plaintiff’s cross-motion for injunctive and declaratory relief. This action originally came before the court on plaintiff’s motion filed on October 18, 1989, requesting that the Department of the Navy be enjoined from awarding a contract to Barron Construction Company to construct an Aviation Support Equipment Training Facility at the Naval Air Station in Millington, Tennessee. Before the contracting officer decided whether Barron’s bid was responsive, plaintiff filed a protest with the General Accounting Office which alleged that Barron’s bid was untimely submitted and therefore non-responsive. The General Accounting Office issued a recommendation which concluded that the bid was responsive and the Navy announced that it will adopt the General Accounting Office’s recommendation. Plaintiff asserts, inter alia, that Barron’s bid was not timely submitted and a determination to the contrary violates Federal procurement practices and the government’s obligation to consider Carothers Construction Inc.’s bid fairly and honestly. For the reasons stated hereinafter, defendant’s motion for summary judgment, which requests denial of plaintiff’s claim for a permanent injunction of the award of the subject contract to Barron, is granted and plaintiff’s cross-motion for injunctive and declaratory relief is denied and its complaint is dismissed.

Factual Background

On February 27, 1989, the Southern Division of the Naval Facilities Engineering Command (Navy) issued a solicitation, No. N62467-84-B-0153 (solicitation) for sub[747]*747mission of sealed bids on the construction of an Aviation Support Equipment Training Facility at the Naval Air Station Memphis in Millington, Tennessee. Subsequently, several amendments to the solicitation changed the date and place of the bid opening, which was finally set for 2:00 p.m. on June 1, 1989, in Building S-236, room 116, Naval Air Station, Memphis, Tennessee.

The events at issue occurred in room 116 and principally involve three individuals: Dolores Quinton (Quinton), the bid opening officer for the solicitation, Luke Thoele (Thoele), a contracts specialist, and Allen Townsend (Townsend), a representative of Barron Construction Company (Barron), a contractor which bid on the solicitation. Sometime before 2:00 p.m. on June 1, 1989, Townsend submitted a bid on behalf of Barron (Barron’s bid) then several minutes later he retrieved it from Quinton and left the room. Later, he resubmitted Barron’s bid with a notation on the outside of the envelope which stated, “DEDUCT $40ooo AL TOWNSEND 1:54 P.M.” Quinton took Barron’s bid to her immediate supervisor, Richard Johnson, who told her that the attempted modification was ineffective. After being told of this, Townsend again retrieved Barron’s bid and immediately left the room. At approximately three minutes before 2:00 p.m., Townsend contacted O.P. Barron, president of Barron, and asked for instruction. O.P. Barron told Townsend to open Barron’s bid envelope and deduct $40,000.00. With approximately two minutes to go before bid opening, Townsend removed documents from Barron’s bid envelope and wrote on them. At five seconds before 2:00 p.m., Quinton instructed Townsend to “hand me something.” Townsend handed Quinton a set of documents with a copy of Barron’s bid on top. At 2:00 p.m., Quinton began announcing that the time for receipt of bids had passed. What happened next is contested by the parties. Defendant contends that simultaneously with Quinton’s announcement, Townsend threw the rest of the Barron bid documents on the table in front of Quinton. After Quinton finished, Thoele took the documents from Quinton and collected the rest of Barron’s bid documents from the table. In contrast, plaintiff avers that up to fifteen seconds after the commencement of Quinton’s announcement, Townsend continued to place the remainder of Barron’s bid documents in the possession of the government and did not relinquish control of all Barron’s bid documents before the 2:00 p.m. bid deadline. The parties agree that nine bids were received and Barron’s was found to have submitted the lowest bid, with a bid price of $9,680,000.00 while the second lowest bidder, Carothers Construction Inc. (Carothers) submitted a bid price of $9,822,045.00.

Plaintiff filed a pre-award protest by letter with the Navy contracting officer (CO) on June 5, 1989, alleging that Barron’s bid was non-responsive because “(1) it was late; (2) it was incomplete; (3) it was not sealed; (4) the bid bond was not submitted with the bid form; (5) Barron did not “submit” its bid but rather had bid documents taken by the Navy’s representative; and (6) there is no evidence that Barron’s representative had authority to make alterations on the bid documents.” After contacting the CO on June 19, 1989, and learning that a decision had not yet been rendered,1 plaintiff filed on that same day a protest by letter with the General Accounting Office (GAO)2 which realleged the contentions in the CO protest.

The Navy agency issued a report on July 26, 1989, which addressed plaintiff’s arguments, as expressed in its letters to the CO and the GAO, and denied its protest.3 In [748]*748response, on August 9, 1989, plaintiff submitted comments on the agency report to the GAO and requested that its protest be sustained because Barron’s bid “(i) was not submitted prior to the scheduled time of submission of bids, and/or (ii) failed to include the required bid bond.”

The GAO issued a recommendation dated October 11, 1989, which determined that Barron’s bid was not submitted late. Relying on the declarations of Quinton, Thoele and Dana Brignole (Brignole), an agency procurement clerk present at the bid opening, the GAO held that “while the manner of the submission of the bid ... was irregular, the evidence clearly shows that the Barron representative relinquished control of its bid (including all bid documents) simultaneously with ... [Quinton’s] ... declaration that the time for receipt of bids had passed. Accordingly, we find that Barron’s bid was not submitted late.”

Plaintiff filed a “Complaint for Declaratory And Injunctive Relief” in this court on October 18, 1989, requesting that the Navy be enjoined from awarding the contract to Barron. The government represented to this court in a telephone conference held on October 19, 1989, that the Navy decided to abide by the recommendation of the GAO, but would not award the contract until November 9, 1989. In addition, on this date, Barron gave notice to the court that it would appear in this action and assert its interest.

On October 25, 1989, defendant filed a motion for summary judgment. On October 31, 1989, plaintiff filed a response to defendant’s motion for summary judgment and a cross-motion for injunctive and declaratory relief. On November 6, 1989, Barron filed a motion to intervene. Oral argument was held on November 7, 1989.4

In the present action, plaintiff asserts that Barron’s bid was untimely submitted. Therefore, such an award would violate Federal procurement law, regulations and policies, and constitute a breach of the Navy’s contractual obligation to consider plaintiffs bid fairly and honestly.

Discussion

Jurisdiction to review pre-award contract decisions of a government agency is conferred on this court pursuant to 28 U.S.C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

California Marine Cleaning, Inc. v. United States
42 Cont. Cas. Fed. 77,398 (Federal Claims, 1998)
Cubic Applications, Inc. v. United States
41 Cont. Cas. Fed. 77,044 (Federal Claims, 1997)
Finley v. United States
39 Cont. Cas. Fed. 76,688 (Federal Claims, 1994)
Blount, Inc. v. United States
36 Cont. Cas. Fed. 75,981 (Court of Claims, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
35 Cont. Cas. Fed. 75,758, 18 Cl. Ct. 745, 1989 U.S. Claims LEXIS 255, 1989 WL 143515, Counsel Stack Legal Research, https://law.counselstack.com/opinion/carothers-construction-inc-v-united-states-cc-1989.