Trinity Lutheran Church v. Dorschner Excavating, Inc.

2006 WI App 22, 710 N.W.2d 680, 289 Wis. 2d 252, 2006 Wisc. App. LEXIS 24
CourtCourt of Appeals of Wisconsin
DecidedJanuary 12, 2006
Docket2004AP785
StatusPublished
Cited by19 cases

This text of 2006 WI App 22 (Trinity Lutheran Church v. Dorschner Excavating, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Trinity Lutheran Church v. Dorschner Excavating, Inc., 2006 WI App 22, 710 N.W.2d 680, 289 Wis. 2d 252, 2006 Wisc. App. LEXIS 24 (Wis. Ct. App. 2006).

Opinion

DEININGER, J.

¶ 1. Oudenhoven Construction, Inc. (OCI), a company hired by Trinity Lutheran Church to coordinate the construction of an addition to Trinity's church building, appeals a judgment awarding damages to Trinity for a mishap that occurred during the construction project. OCI argues that the economic loss doctrine bars the negligence claims asserted against it by Trinity and by Dorschner Excavating, Inc., *258 a company separately hired by Trinity to perform excavation work for the project. OCI also argues that expert testimony was necessary to establish whether OCI's conduct was negligent and caused damage to Trinity. Finally, OCI contends the evidence presented at trial was insufficient to permit the jury to find it negligent.

¶ 2. Because no contractual relationship existed between Dorschner and OCI, we conclude Dorschner's negligence claim against OCI for contribution is not barred by the economic loss doctrine. Trinity and OCI entered into a contract regarding the construction project, but their contract is not in the record. Accordingly, we must treat the missing contract as supporting the trial court's conclusion that its predominant purpose was OCI's provision of construction coordination services. Accordingly, we conclude the economic loss doctrine also does not bar Trinity's recovery from OCI.

¶ 3. We also conclude that expert testimony was not required to establish that OCI's conduct was negligent and contributed to Trinity's loss. Finally, we conclude that the record contains sufficient evidence to support the jury's finding that OCI was negligent in discharging its construction coordination duties.

¶ 4. Trinity cross-appeals the trial court's denial of its postverdict motion to change verdict answers or for judgment notwithstanding the verdict, in which it sought to recover against Dorschner on a contractual theory as well as in tort. We accept Dorschner's unre-futed assertion that our rejection of OCI's challenges to the appealed judgment renders Trinity's cross-appeal moot. Accordingly, we affirm the judgment before us in all respects.

*259 BACKGROUND

¶ 5. Trinity Lutheran Church hired several contractors to build a new addition to its church. After the project was completed, the church board and pastor came to the church for a meeting, where they were met by water pouring out of the doors of the church. The cause of the flooding was determined to be a crack in the lateral supplying water to the church. Trinity and its property insurer, Guide One Mutual Insurance Company, commenced this action to recover their respective losses stemming from the water damage to the church. 1

¶ 6. The relationships between the parties involved in this construction project are as follows. Trinity hired OCI to coordinate construction of the addition to its church. The contract between the parties specified that this would be a "design-build" project, meaning that OCI would coordinate the work of the various contractors on the project but would not be responsible for supervising them. OCI entered into a series of subcontracts, including one with Edward Radtke & Sons, Inc., for plumbing work. Radtke, in turn, hired Baumgart Excavating, Inc., to install a water main and sanitary sewer piping. In a separate contract not involving OCI, Trinity contracted with Dorschner Excavating, Inc., to excavate for the project's footings.

¶ 7. Baumgart excavated and installed a lateral water pipe from the city water main to the church. The next day, Baumgart performed a water pressure test on the water lateral and obtained a satisfactory result. The test showed no loss of pressure, confirming the absence of loose connections or cracks in the water pipe. OCI *260 instructed Baumgart as to where the water lateral should enter the church building but did not supervise Baumgart in the installation or testing of the water pipe.

¶ 8. After Baumgart finished its work, Dorschner excavated for the project footings. Dorschner knew that it was excavating above the water pipe because the trench where the ground had previously been disturbed by Baumgart to lay the water lateral was visible on the surface. Dorschner used a backhoe to excavate the footings above the water lateral, and it then employed a prod rod and hand shovels as it got closer to the water lateral pipe.

¶ 9. Only Dorschner used a backhoe in the area of the water lateral after Baumgart had conducted the pressure test on the newly installed lateral. The pipe was not tested again after Dorschner finished its work. Water from the city water main to the church was not turned on while Dorschner did its excavation work, and it remained off until shortly before the church board meeting when the flooding was discovered.

¶ 10. After the flooding, the water lateral was re-excavated. A large crack was discovered in the lateral in the vicinity of where Dorschner excavated for the footings. Trinity's expert opined that the water pipe cracked when the teeth of a backhoe struck it. It was established at trial that only Dorschner and Baumgart had used backhoes in the area where the water lateral pipe was located.

¶ 11. Trinity and its insurer sued Dorschner, alleging claims for breach of contract and negligence. Dorschner, in turn, filed a third-party complaint joining Radtke, Baumgart and OCI, asserting that their negligence had caused Trinity's loss. Trinity asserted no *261 direct claims against Baumgart or OCI until after the jury verdict, when the trial court permitted Trinity to amend its complaint.

¶ 12. The claims were tried to a jury. At the close of Dorschner's case, OCI, Radtke and Baumgart moved for a directed verdict due to insufficient evidence. The parties stipulated to the dismissal of the claim against Radtke because it had been directly responsible for only interior plumbing work. The trial court denied OCI's and Baumgart's motions. The parties stipulated that Trinity and its insurer suffered damages in the amount of $195,596. The jury determined that Dorschner, Baumgart and OCI were all causally negligent, and it allocated causal negligence as follows: Dorschner, 20%; OCI, 60%; and Baumgart 20%. The jury also determined that Dorschner did not breach its contract with Trinity.

¶ 13. OCI filed postverdict motions in which it sought: (1) to change the jury's answers finding it negligent and its negligence causal from "yes" to "no"; (2) to change the jury's answer apportioning "60%" of the causal negligence against OCI to "0%"; and (3) a new trial on the grounds that the "verdict is perverse and against the interest of justice." The trial court denied all of OCI's motions.

¶ 14. Trinity moved postverdict for leave to amend its pleadings to include negligence claims against OCI and Baumgart, which the trial court granted. Trinity also moved for judgment notwithstanding the verdict, or alternatively to change verdict answers, such that its recovery against Dorschner would rest not only on Dorschner's causal negligence but also on Dorschner's alleged breach of contract. The court denied this motion.

*262 ¶ 15.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jalal Kareem Khoury v. American Honda Motor Co. Inc.
Court of Appeals of Wisconsin, 2025
TJ Prop, LLC v. Tim Mueller Mason Contractor, LLC
Court of Appeals of Wisconsin, 2024
Ver Hagen v. BeneTek Inc
E.D. Wisconsin, 2024
Marek A. Misiaszek v. ABC Insurance Company
Court of Appeals of Wisconsin, 2022
Racine County v. Oracular Milwaukee, Inc.
2010 WI 25 (Wisconsin Supreme Court, 2010)
Reuben v. KOPPEN
2010 WI App 63 (Court of Appeals of Wisconsin, 2010)
Racine County v. Oracular Milwaukee, Inc.
2009 WI App 58 (Court of Appeals of Wisconsin, 2009)
Superl Sequoia Ltd. v. THE CW CARLSON CO., INC.
535 F. Supp. 2d 931 (W.D. Wisconsin, 2008)
Plourde Sand & Gravel Co. v. JGI Eastern, Inc.
917 A.2d 1250 (Supreme Court of New Hampshire, 2007)
1325 North Van Buren, LLC v. T-3 Group, Ltd.
2006 WI 94 (Wisconsin Supreme Court, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
2006 WI App 22, 710 N.W.2d 680, 289 Wis. 2d 252, 2006 Wisc. App. LEXIS 24, Counsel Stack Legal Research, https://law.counselstack.com/opinion/trinity-lutheran-church-v-dorschner-excavating-inc-wisctapp-2006.