1325 North Van Buren, LLC v. T-3 Group, Ltd.

2006 WI 94, 716 N.W.2d 822, 293 Wis. 2d 410, 2006 Wisc. LEXIS 390
CourtWisconsin Supreme Court
DecidedJuly 11, 2006
Docket2004AP352
StatusPublished
Cited by63 cases

This text of 2006 WI 94 (1325 North Van Buren, LLC v. T-3 Group, Ltd.) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
1325 North Van Buren, LLC v. T-3 Group, Ltd., 2006 WI 94, 716 N.W.2d 822, 293 Wis. 2d 410, 2006 Wisc. LEXIS 390 (Wis. 2006).

Opinions

JON P. WILCOX, J.

¶ 1. T-3 Group, Ltd. (T-3) seeks review of a court of appeals decision reversing the entry of summary judgment dismissing all negligence claims brought by 1325 North Van Buren, LLC (1325) entered by the Milwaukee County Circuit Court, Mel Flanagan, Judge. See 1325 N. Van Buren, LLC v. T-3 Group, Ltd., 2005 WI App 121, 284 Wis. 2d 387, 701 N.W.2d 13. Westport Insurance Corporation (Westport) seeks review of the court of appeals' reversal of a declaratory judgment in Westport's favor dismissing all of 1325's claims against it and declaring that Westport has no obligation to defend or indemnify T-3 against 1325's claims. Id.

[417]*417¶ 2. 1325 contracted with T-3 for the purpose of substantially renovating an existing industrial warehouse into a 42-unit condominium building with attached parking garages. After numerous accidents and setbacks, 1325 fired T-3 and filed a lawsuit alleging claims in both tort and contract against T-3. 1325 also sued T-3's commercial general liability (CGL) insurer, Indiana Insurance Company (Indiana), and T-3's professional liability insurer, Westport. The circuit court dismissed 1325's tort claims against T-3, concluding that the economic loss doctrine barred such claims. Left with only contract claims, the circuit court also concluded that neither Indiana's CGL policy nor Westport's professional liability policy provided coverage for 1325's contract claims against T-3.

¶ 3. The court of appeals reversed in all respects, concluding: (1) the economic loss doctrine did not apply because the contract between T-3 and 1325 was purely for services; (2) unresolved factual questions precluded a determination of whether Indiana's CGL policy provided coverage; and (3) Westport's professional liability policy provided coverage.

¶ 4. T-3 petitioned for review and contends the economic loss doctrine precludes 1325's negligence claims. Westport joined T-3's petition for review as a direct-action defendant and filed a separate cross-petition contending that the economic loss doctrine precludes 1325's negligence claims and that its policy does not provide T-3 with coverage against breach of contract claims.1

[418]*418¶ 5. We conclude that the economic loss doctrine applies to the mixed contract between T-3 and 1325 as the predominant purpose of the contract was to construct a 42-unit condominium complex with adjacent parking garages. Furthermore, Westport has a duty to defend and potentially indemnify T-3 for its breach of contract claim under our interpretation of its professional liability insurance contract. As such, the decision of the court of appeals is reversed with respect to T-3's appeal, affirmed with respect to Westport's cross-appeal, and remanded to the circuit court for further proceedings consistent with this opinion.

I — I

A. The Contract Between 1325 and T-3

¶ 6. On March 26, 2001,2 1325 and T-3 entered into a comprehensive 102-page contract consisting of. the following: (1) a customized American Institute of Architects (AIA) "Standard Form of Agreement Between Owner and Construction Manager where the Construction Manager is also the Constructor;" (2) Amendment No. 1; (3) Contract Addendum; (4) Exhibits; (5) General Conditions of the Contract for Construction — AIA Document A201; (6) Supplement to the General Conditions of the Contract for Construction; and (7) various drawings and finish specifications.

¶ 7. T-3 was hired to renovate an industrial warehouse building owned by 1325 into a 42-unit condominium complex, and construct attached parking garages. In addition to providing the necessary materials [419]*419for renovation and construction, T-3 was to provide construction management services, meaning it had to hire, coordinate, and supervise the numerous subcontractors, and generally manage the project to ensure the renovation was completed on time and within budget. The contract called for 1325 to pay the cost of the work plus T-3's construction management fee up to a guaranteed maximum price of $6,099,891. Of this price, $176,000 constituted the fee for construction management. Absent change orders, costs in excess of the guaranteed maximum price would be borne exclusively by T-3.

¶ 8. There are a number of contractual provisions worth noting. First, there is a broad warranty clause that reads in part as follows:

The Contractor warrants to the Owner, the condominium association to be formed, the unit owners and Architect that materials and equipment furnished under the Contract will be of good quality and new unless otherwise required or permitted by the Contract Documents, that the Work3 will be free from defects not inherent in the quality required or permitted, and that the Work will conform with the requirements of the Contract Documents.

The contract also contains the following noteworthy provisions:

(1) T-3 agreed to "promptly remedy damage and loss (other than damage or loss insured under property insurance required by the Contract Documents) to [420]*420property [on the project site] caused in whole or in part by the Contractor, a Subcontractor, a Sub-subcontractor ...
(2) T-3 agreed to indemnify 1325 against any claims for bodily injury or tangible property damage, other than to property that was part of the project, where the loss resulted from the negligent acts or omissions of T-3 or a subcontractor. In addition, the contract required that T-3 purchase contractual liability insurance to cover indemnification claims under § 3.18.1 of the General Conditions.
(3) Explicitly excluded from project costs were "[c]osts due to the negligence or willful acts or omissions of the Construction Manager, any subcontractor, anyone directly or indirectly employed by any of them, or for whose acts any of them may be liable, including but not limited to the correction of defective or non-conforming Work,... or making good any damage to property."
(4) The contract listed reasons for which 1325 could withhold payment.
(5) The contract included a liquidated damages provision requiring T-3 to pay $1,000 per day for each condominium unit not delivered on time.
(6) The contract required T-3 to have a CGL policy with limits of $2,000,000.
(7) The contract required T-3 to have an umbrella policy with limits of $4,000,000.
(8) The contract provided circumstances under which it could be terminated before the project was completed.

¶ 9. Construction began in March of 2001. The contract required the first condominium units to be completed by October 15, 2001, and the last condominium units to be completed by January 15,2002. Near [421]*421the end of October 2001, however, the project was approximately 28 percent complete and none of the condominiums were substantially completed. Subcontractors caused accidental damage throughout the existing structure, and the project was seriously delayed. Dissatisfied with T-3's progress, 1325 notified T-3 that it was in default under the contract by letter dated October 31,2001, and T-3 left the project site that same day. 1325 then entered into a contract with C.G. Schmidt, Inc.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mark Demars v. Fincantieri Marine Group, LLC
Court of Appeals of Wisconsin, 2024
LCB, LLC v. Spectrum Brands, Inc.
Court of Appeals of Wisconsin, 2023
Motorists Mut. Ins. Co. v. Ironics, Inc. (Slip Opinion)
2022 Ohio 841 (Ohio Supreme Court, 2022)
Kemper Independence Insurance Company v. Ismet Islami
2021 WI 53 (Wisconsin Supreme Court, 2021)
Crum & Forster Specialty Insur v. DVO, Inc.
939 F.3d 852 (Seventh Circuit, 2019)
Richard A. Birnschein v. David Sandlund
Court of Appeals of Wisconsin, 2019
Kmart Corp. v. Herzog Roofing, Inc.
2018 WI App 71 (Court of Appeals of Wisconsin, 2018)
Crum & Forster Specialty Ins. Co. v. GHD Inc.
325 F. Supp. 3d 917 (E.D. Wisconsin, 2018)
Wisconsin Pharmacal Co. v. Nebraska Cultures of California, Inc.
2014 WI App 111 (Court of Appeals of Wisconsin, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
2006 WI 94, 716 N.W.2d 822, 293 Wis. 2d 410, 2006 Wisc. LEXIS 390, Counsel Stack Legal Research, https://law.counselstack.com/opinion/1325-north-van-buren-llc-v-t-3-group-ltd-wis-2006.