Dynamic Concrete Resurfacing, LLC v. Fowler and Hammer, Inc.

CourtCourt of Appeals of Wisconsin
DecidedSeptember 9, 2022
Docket2021AP002173
StatusUnpublished

This text of Dynamic Concrete Resurfacing, LLC v. Fowler and Hammer, Inc. (Dynamic Concrete Resurfacing, LLC v. Fowler and Hammer, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dynamic Concrete Resurfacing, LLC v. Fowler and Hammer, Inc., (Wis. Ct. App. 2022).

Opinion

COURT OF APPEALS DECISION NOTICE DATED AND FILED This opinion is subject to further editing. If published, the official version will appear in the bound volume of the Official Reports. September 9, 2022 A party may file with the Supreme Court a Sheila T. Reiff petition to review an adverse decision by the Clerk of Court of Appeals Court of Appeals. See WIS. STAT. § 808.10 and RULE 809.62.

Appeal No. 2021AP2173 Cir. Ct. No. 2019CV157

STATE OF WISCONSIN IN COURT OF APPEALS DISTRICT IV

DYNAMIC CONCRETE RESURFACING, LLC,

PLAINTIFF-RESPONDENT,

V.

FOWLER AND HAMMER, INC.,

DEFENDANT-APPELLANT.

APPEAL from a judgment of the circuit court for La Crosse County: TODD W. BJERKE, Judge. Reversed and cause remanded.

Before Kloppenburg, Fitzpatrick, and Graham, JJ.

Per curiam opinions may not be cited in any court of this state as precedent

or authority, except for the limited purposes specified in WIS. STAT. RULE 809.23(3). No. 2021AP2173

¶1 PER CURIAM. Dynamic Concrete Resurfacing, LLC (Dynamic Concrete) sued Fowler and Hammer, Inc. (Fowler) seeking payment allegedly due pursuant to a June 2018 contract between the two parties.1 The circuit court granted Dynamic Concrete’s motion for summary judgment, ordering Fowler to pay the amount alleged in the complaint. Fowler argues that the circuit court erroneously determined on summary judgment that the parties entered into a “flat-rate contract.”2 Fowler also argues that the parties unambiguously entered into a “time- and-materials contract;”3 that the amount it owes, if any, is based on Dynamic Concrete’s time and material costs for work in addition to the work undertaken pursuant to a prior April 2018 contract between the parties; and that genuine issues of material fact exist as to Dynamic Concrete’s time and material costs incurred pursuant to the June 2018 contract.

¶2 We conclude that the June 2018 contract is unambiguously a time- and-materials contract and that there are disputes of material fact as to the amount

1 Appellant refers to itself as “Fowler & Hammer” in its briefs and logo. We use the name “Fowler and Hammer, Inc.” as it appears in the caption to refer to the company, which we shorten to “Fowler.” We refer to James Fowler, Vice-President and Chief Operating Officer of Fowler, by his first and last name. 2 Both the circuit court and the parties refer to the contract asserted by Dynamic Concrete and found by the circuit court as a “flat-rate contract.” However, Wisconsin courts use the term “fixed-price contract” to refer to what the circuit court and the parties refer to as a “flat-rate contract.” See 1325 N. Van Buren, LLC v. T-3 Grp., Ltd., 2006 WI 94, ¶43, 293 Wis. 2d 410, 716 N.W.2d 822 (defining a “fixed-price contract” as one where the parties bargain on the final price of the project and the price does not change based on the hours worked or what is required to complete the project). We will use the term “flat-rate contract” when referencing the parties’ submissions before the circuit court and the circuit court’s ruling and the term “fixed-price contract” otherwise, consistent with Wisconsin case law. 3 In contrast to a fixed-price contract, a “time-and-materials contract” is one where the parties do not bargain for a specific sum and, instead, the contractor bills for the usual charges associated with the time and materials needed to complete the project. La Velle v. De Luca, 48 Wis. 2d 464, 469, 180 N.W.2d 710, 713 (1970).

2 No. 2021AP2173

of payment due to Dynamic Concrete pursuant to that contract. Accordingly, we reverse and remand to the circuit court for additional proceedings.

BACKGROUND

¶3 The following facts are undisputed for purposes of summary judgment.

¶4 In 2016, Fowler was awarded a contract for a public improvement construction project for the University of Wisconsin-La Crosse (UW-La Crosse) Sciences Lab Building. As the general contractor on the project, Fowler retained Dynamic Concrete to work as a subcontractor. The parties entered into two fixed- price contracts, one for epoxy work pertaining to concrete flooring and one for concrete staining. In April 2018, the parties entered into an additional fixed-price contract pertaining to concrete flooring, in the amount of $209,380.00.

¶5 As the work on both contracts progressed, the parties entered into an additional contract in June 2018, which is the primary subject of their dispute and this appeal. The June 2018 contract was for Dynamic Concrete to perform “deep grinding work” related to the epoxy contract. The contract is contained in a series of emails between Kurt Kopp, Managing Member of Dynamic Concrete, James Fowler, Vice-President and Chief Operating Officer of Fowler, and Eric Lehman, Part-Owner of Fowler. Because this appeal revolves around these emails, we reproduce them in full as follows.

¶6 First, on June 20, 2018, Kopp (at Dynamic Concrete) sent Lehman (at Fowler) an email stating, “Please reply that you received this estimate,” along with a document entitled “Estimate” stating a “[c]ost” of $44,689.28 with the following description:

3 No. 2021AP2173

This change order is for additional work needed for deep grinding in order to remove the majority of the pop outs on the remaining floors of the basement, floor 1, floor 3, and floor 4 at UWL Science Lab Building.

¶7 Second, that same day Lehman replied:

Kurt – we don’t have any [] more dollars to give you. I don’t understand why 2nd floor took 7 days and 3rd floor took 4 days and looked bad. If you would have taken more days it probably would have looked better. If you have to do a deeper grind to get consistency maybe that is a[n] argument we can have with River [Architects] and DFD [Wisconsin Division of Facilities Development].

¶8 Third, also on that same day, Kopp replied:

Ok[.]

We will polish to a salt and pepper finish on 4th floor as per the estimate, [you will] will have to accept it. I’m fine with that since we won[’]t incur extra time and costs. The only extra time that will have to be covered is for the extra seven days of grinding that Jim has us complete on third floor.

¶9 Fourth, the next day James Fowler sent Kopp the following email:

Proceed with the additional deep grinding work that we discussed today at the UW-L Sciences Bldg. I agree that 4th floor will take extra work but that first floor and the basement are expected to be similar to the 2nd floor grinding effort. We are hoping the added cost will be well under the original estimate of $45,000. Keep track of hours spent on each floor to help determine additional costs. Let me know if you need a more formal change order to proceed with the work.

¶10 Dynamic Concrete proceeded with the remaining work and, after it was complete, on July 12, 2018, emailed Fowler an “Invoice” for $44,689.28 for:

[A]dditional work needed for deep grinding in order to remove the majority of the pop outs on the remaining floors of the basement, floor 1, floor 3, and floor 4 at UWL Science Lab Building.

4 No. 2021AP2173

¶11 Fowler did not pay this invoice. In the absence of payment by Fowler, Dynamic Concrete served a Claim of Public Improvement Lien on Fowler and the Wisconsin Department of Administration, Division of State Facilities seeking payment of the $44,689.28 invoice, as well as of other unpaid invoices between the parties that are not at issue in the present appeal.4 Fowler disputed the claim. Dynamic Concrete then brought this action, seeking three categories of payment— retainages, repair around the floor and drain area, and the deep grinding work— based on any one of five alternative claims.5

4 See WIS. STAT.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

1325 North Van Buren, LLC v. T-3 Group, Ltd.
2006 WI 94 (Wisconsin Supreme Court, 2006)
Ramsey v. Ellis
484 N.W.2d 331 (Wisconsin Supreme Court, 1992)
La Velle v. De Luca
180 N.W.2d 710 (Wisconsin Supreme Court, 1970)
State v. McMorris
2007 WI App 231 (Court of Appeals of Wisconsin, 2007)
Schmidt v. Northern States Power Co.
2007 WI 136 (Wisconsin Supreme Court, 2007)
Hoffman v. Red Owl Stores, Inc.
133 N.W.2d 267 (Wisconsin Supreme Court, 1965)
Mohns Inc. v. BMO Harris Bank National Association
2021 WI 8 (Wisconsin Supreme Court, 2021)
Town Bank v. City Real Estate Development, LLC
2010 WI 134 (Wisconsin Supreme Court, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
Dynamic Concrete Resurfacing, LLC v. Fowler and Hammer, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/dynamic-concrete-resurfacing-llc-v-fowler-and-hammer-inc-wisctapp-2022.