Mechanical, Inc. v. Venture Electrical Contractors, Inc.

CourtCourt of Appeals of Wisconsin
DecidedApril 22, 2020
Docket2018AP002380
StatusUnpublished

This text of Mechanical, Inc. v. Venture Electrical Contractors, Inc. (Mechanical, Inc. v. Venture Electrical Contractors, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mechanical, Inc. v. Venture Electrical Contractors, Inc., (Wis. Ct. App. 2020).

Opinion

2020 WI APP 23 COURT OF APPEALS OF WISCONSIN PUBLISHED OPINION

Case No.: 2018AP2380

Complete Title of Case:

MECHANICAL, INC.,

PLAINTIFF-RESPONDENT,

V.

VENTURE ELECTRICAL CONTRACTORS, INC.,

DEFENDANT-APPELLANT.

Opinion Filed: April 22, 2020 Submitted on Briefs: September 12, 2019

JUDGES: Neubauer, C.J., Reilly, P.J., and Gundrum, J. Concurred: Dissented:

Appellant ATTORNEYS: On behalf of the defendant-appellant, the cause was submitted on the briefs of Scott R. Halloin of Halloin Law Group, S.C., Milwaukee.

Respondent ATTORNEYS: On behalf of the plaintiff-respondent, the cause was submitted on the brief of Roy E. Wagner, Smitha Chintamaneni, and Lauren A. Triebenbach of von Briesen & Roper, S.C., Milwaukee. 2020 WI App 23

COURT OF APPEALS DECISION NOTICE DATED AND FILED This opinion is subject to further editing. If published, the official version will appear in the bound volume of the Official Reports. April 22, 2020 A party may file with the Supreme Court a Sheila T. Reiff petition to review an adverse decision by the Clerk of Court of Appeals Court of Appeals. See WIS. STAT. § 808.10 and RULE 809.62.

Appeal No. 2018AP2380 Cir. Ct. No. 2015CV1472

STATE OF WISCONSIN IN COURT OF APPEALS

APPEAL from an order of the circuit court for Waukesha County: WILLIAM J. DOMINA, Judge. Affirmed.

Before Neubauer, C.J., Reilly, P.J., and Gundrum, J.

¶1 NEUBAUER, C.J. At issue in this construction dispute is whether the economic loss doctrine bars a negligence claim seeking purely economic losses—delay damages—by one subcontractor against another with whom there No. 2018AP2380

was no contract. Each subcontractor did enter a subcontract with the general contractor that addressed their individual obligations, duties of care, schedules of work, changes, and remedies for delays. Because the complaining subcontractor’s negligence claim is rooted in the duties imposed by the interrelated construction contracts, contract law provides the remedies for the economic loss at issue, foreclosing tort remedies. The economic loss doctrine bars the negligence claim. We affirm.

BACKGROUND

¶2 Rising three stories high, spreading over 92,000 square feet, the construction project at issue involved $36,436,603 for design, labor, and material work to build an integrated research laboratory addition to the existing Great Lakes Research Facility for the University of Wisconsin-Milwaukee. In 2012, the State of Wisconsin by the Department of Administration, and represented by the Wisconsin Division of State Facilities (State) awarded the prime construction contract to J.P. Cullen & Sons, Inc., as the general contractor. Cullen hired Mechanical, Inc., to install the HVAC systems, and Venture Electrical Contractors, Inc., to install the electrical systems, under separate but similar subcontracts, both dated August 20, 2012. Venture’s subcontract was for $4,491,812 and Mechanical’s was for $9,190,000.

¶3 Identical in all relevant respects, both subcontracts incorporated the prime contract between the State and Cullen.1 The subcontracts identified the

1 The subcontractors assumed toward Cullen all duties and obligations Cullen owed under the prime contract to the State to the extent of the subcontractors’ work. Cullen had all rights and remedies against the subcontractors that the State had under the prime contract against Cullen.

2 No. 2018AP2380

standard of care: Each subcontractor was required to “use its best care, skill, and diligence in supervising, directing, and performing” its work.

¶4 The subcontracts specified the duties and obligations each subcontractor owed associated with the timely performance of the work, including a schedule of work and a commitment to perform the work in a timely manner.2 Both subcontracts addressed work and schedule changes in an identical manner.3

¶5 Both subcontractors “recognize[d]” that delays could occur. In that event, extensions were to be provided, but that was the subcontractor’s “sole remedy.” Each subcontractor expressly agreed that it would not be entitled to make a claim for “damages or additional compensation based on delay, hindrance of work, impacts on progress, season changes, disruption, loss of productivity or efficiency, or schedule changes resulting from any cause whatsoever.”

¶6 Under its subcontract, Venture sought recovery of over $1,000,000 from Cullen for costs it incurred because of delays and untimely performance. In addition to Mechanical, Venture blamed other subcontractors for its losses. Cullen denied the claim on the grounds that it was untimely, Venture’s damages were self-

2 Under the subcontracts, all work was to be performed on schedule and in strict compliance with the plans and specifications. Shop drawings were to be submitted and punch lists completed within specific time limits. The contractor and subcontractors were required to communicate to promptly set the work schedules. Each subcontractor was responsible for its performance, including the “methods, techniques, means, and sequences for coordinating and completing” the work. 3 If the contractor did not believe the work would be completed timely, the subcontractor was to bear the expense to get it done via overtime, additional shifts, etc.; changes could be made in the schedule without additional compensation; all participants were to cooperate with others and a subcontractor was to immediately advise the general contractor of any interference by another subcontractor.

3 No. 2018AP2380

induced, and the subcontract precluded recovery for delay. Venture did not persist in asserting this claim against Cullen.

¶7 Unrelated to Mechanical’s work for Cullen, Venture asked Mechanical to install concrete embeds to support electrical conduit. Mechanical billed Venture $11,961.31 for this work but allegedly did not get paid. When Mechanical subsequently brought this suit against Venture seeking to recover its $11,961.31, Venture counterclaimed in negligence, now seeking almost $1,100,000 for delay-related damages solely from Mechanical.

¶8 Venture alleged that Mechanical owed Venture a duty to comply with Mechanical’s schedules under its subcontract and to timely perform its project work. Venture contended that Mechanical’s performance was untimely and out of sequence, breaching its duties and causing Venture to incur delay-related losses from overtime hours and cost overruns.

¶9 Mechanical moved for summary judgment dismissal of Venture’s negligence claim on the ground that it was barred by the economic loss doctrine. The circuit court granted Mechanical’s motion. Venture appeals.

DISCUSSION

Standard of Review

¶10 Under a given set of facts, whether the economic loss doctrine applies to bar a claim and whether a contract is primarily for goods or services are questions of law which we review de novo. Linden v. Cascade Stone Co., 2005 WI 113, ¶5, 283 Wis. 2d 606, 699 N.W.2d 189.

The Economic Loss Doctrine

4 No. 2018AP2380

¶11 A judicially created doctrine, the economic loss rule was first adopted in Wisconsin in Sunnyslope Grading, Inc. v. Miller, Bradford & Risberg, Inc., 148 Wis. 2d 910, 437 N.W.2d 213 (1989). In Sunnyslope, when a backhoe failed to perform properly, the buyer sued the manufacturer in tort, seeking damages for costs of parts, extra labor, and lost profits. Id. at 914-15. The manufacturer had provided a limited warranty, which also limited its liability for costs and disclaiming other consequential damages. Id. at 913-14.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Daanen & Janssen, Inc. v. Cedarapids, Inc.
573 N.W.2d 842 (Wisconsin Supreme Court, 1998)
Milwaukee Partners v. Collins Engineers, Inc.
485 N.W.2d 274 (Court of Appeals of Wisconsin, 1992)
Linden v. Cascade Stone Company, Inc.
2005 WI 113 (Wisconsin Supreme Court, 2005)
Hatleberg v. Norwest Bank Wisconsin
2005 WI 109 (Wisconsin Supreme Court, 2005)
Trinity Lutheran Church v. Dorschner Excavating, Inc.
2006 WI App 22 (Court of Appeals of Wisconsin, 2006)
Mose v. Tedco Equities—Potter Road Ltd. Partnership
598 N.W.2d 594 (Court of Appeals of Wisconsin, 1999)
Sunnyslope Grading, Inc. v. Miller, Bradford & Risberg, Inc.
437 N.W.2d 213 (Wisconsin Supreme Court, 1989)
State Farm Mutual Automobile Insurance v. Ford Motor Co.
592 N.W.2d 201 (Wisconsin Supreme Court, 1999)
Chris Hinrichs v. DOW Chemical Company
2020 WI 2 (Wisconsin Supreme Court, 2020)
BRW, Inc. v. Dufficy & Sons, Inc.
99 P.3d 66 (Supreme Court of Colorado, 2004)
Ferris v. Location 3 Corp.
2011 WI App 134 (Court of Appeals of Wisconsin, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
Mechanical, Inc. v. Venture Electrical Contractors, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/mechanical-inc-v-venture-electrical-contractors-inc-wisctapp-2020.