TJ Landco, LLC v. Harley C. Douglass, Inc.

346 P.3d 777, 186 Wash. App. 249
Court of Appeals of Washington·Decided March 5, 2015·No. Nos. 31992-0-III; 32208-4-III·Published·Cited by 21 cases

Opinion

[252]*252¶1

Korsmo, J.

This appeal arises from the modification of the provisions of a contract governing payment and interest. Concluding that the trial court adopted a reasonable construction of the contract at the bench trial, we affirm the interest rate rulings and remand for an additional hearing of the question of the attorney fee award for work performed by law students.

FACTS

¶2 The subject of the contract was land near the southwest border of the city of Spokane. Respondent TJ Landco LLC agreed in February 2004 to sell the 94 acre parcel of land to appellant Harley C. Douglass Inc. (Douglass) for $3.6 million. The seller was required to obtain preliminary plat approval from the city of Spokane and obtain the city’s agreement to extend water and sewer by the end of 2005.

¶3 The parties used a standard real estate purchase and sale agreement form. An addendum to that form included the following language concerning the purchase price and interest:

1) Purchase price of 3.6 Million Dollars ($3,600,000.00) to be paid as follows:
A) Two Million Dollars ($2,000,000.00) as down payment due at closing
B) The balance of One Million Six Hundred Thousand Dollars will be paid in annual installments of $250,000.00 per year plus interest until paid in full.
C) The unpaid balance will carry and [sic] interest rate of 6% per annum.
D) The first annual payment will begin exactly 2 years from the date of closing.
E) Purchaser and Seller agree that the interest rate for the first two years of this transaction will carry the minimum Federal Rate allowable. At the end of the first two years the interest rate will be 6% per annum until balance is paid in full.
F) . . . .
[253]*253G) Deed releases will be prepared on a per acre basis on the remaining balance of land and executed according to the installment payment schedule noted above.

Clerk’s Papers (CP) at 49.

¶4 Three of the provisions mentioned interest, and two of them gave competing commands concerning the rate to be charged. Subsequent developments were to make the situation more complicated.

f 5 The preliminary plat approval was received October 9, 2006, and the sale closed thereafter. Tod Lasley, the owner of Landco, met on December 22, 2006, with Harley Douglass, the owner of Douglass. The two men agreed that at that point Douglass owed Landco $1,114,558.19. Douglass paid $114,558.19 at that time. On a balance sheet accounting for payments made and balance owing on the land sale, the men added two separate handwritten notes. Each was dated December 22, 2006, and signed by both men. The first stated:

1,000,000.00 Balance,
Payment of 200,000.00 per year for 5 years at zero interest.
The remaining note:
#889
Based on 371 Lots
If less credit will be given out of 1,000,000.00

CP at 68.

¶6 The parties treated these writings as a modification of the original contract. Douglass made a single payment of $200,000 on March 4,2008, but did not make any additional payments thereafter. He later contended that Landco had not fulfilled all of its obligations under the contract and that only 304 of the anticipated 371 lots would be approved. Douglass sold the land to his parents for $500,000 without developing it.

¶7 Landco filed suit in February 2010, contending that Douglass had breached the contract. Douglass defended on [254]*254the basis that he was entitled to an offset due to the limited number of lots approved and, thus, no further moneys were owing. The case proceeded to a four day bench trial in the Spokane County Superior Court. In addition to the questions of breach and offset, the parties hotly contested the interest rate governing any judgment as well as appropriate attorney fees.

¶8 The trial court concluded that Douglass had breached the contract and failed on the counterclaim for an offset. The court awarded Landco the remaining $800,000 on the contract, plus prejudgment interest at 12 percent and postjudgment interest at 12 percent. Detailed findings in support of the bench verdict were entered. Douglass promptly appealed to this court.

¶9 After hearing, the trial court awarded Landco its attorney fees and costs, including $24,514.16 for work done by law student “legal interns.” The court denied Landco’s request for fees for work performed by paralegals. Douglass appealed from the fee award. This court consolidated the two appeals and subsequently heard oral argument.

ANALYSIS

¶10 Douglass challenges the prejudgment and postjudgment interest rates, as well as the fees awarded for the work performed by the law students. Both parties seek attorney fees on appeal under the contract. We initially address the two interest rate arguments as one issue before turning to the two attorney fee contentions.

Interest Rate

¶11 Douglass contends that the 0 percent interest rate in the modification provision governs both the prejudgment and postjudgment interest rates, thus making the court’s judgment in error. Landco contends that the parties did not contract for a rate to govern in the event of a breach of the contract, requiring the court to apply the statutory provi[255]*255sions that currently provide for 12 percent interest. No party contends that the 6 percent rate initially provided by the contract is still in force.1 Because the same operative facts control the outcome, we consider the two arguments together even though different statutes govern the two situations.

¶12 Prejudgment interest is governed by RCW 19.52-.010.2 As relevant here, the statute states in part:

(1) Every loan or forbearance of money, goods, or thing in action shall bear interest at the rate of twelve percent per annum where no different rate is agreed to in writing between the parties ....

¶13 The governing statute for postjudgment interest is found in RCW 4.56.110.3 The relevant provisions relate:

Interest on judgments shall accrue as follows:
(1) Judgments founded on written contracts, providing for the payment of interest until paid at a specified rate, shall bear interest at the rate specified in the contracts: PROVIDED, That said interest rate is set forth in the judgment.
(4) Except as provided under subsections (1), (2), and (3) of this section, judgments shall bear interest from the date of entry at the maximum rate permitted under RCW 19.52.020

Free access — add to your briefcase to read the full text and ask questions with AI

TJ Landco, LLC v. Harley C. Douglass, Inc., 346 P.3d 777, 186 Wash. App. 249 (Wash. Ct. App. 2015).

346 P.3d 777 (TJ Landco, LLC v. Harley C. Douglass, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

B&b Welding, Inc., V. Scarsella Bros., Inc.
Court of Appeals of Washington, 2025
Stanley Xu And Nanling Chen, V. Judgment Services, Llc
Court of Appeals of Washington, 2024
State Of Washington, V. Jason Michael Ramos
Court of Appeals of Washington, 2022
Klein v. Kim
W.D. Washington, 2022
Moraglis, S.a., V. Colorado Tire Corporation
Court of Appeals of Washington, 2022
Jonathan Liffgens, Et Ux, V Luke Dorny
Court of Appeals of Washington, 2022
Milwaukie Lumber v. Popick And Veristone
Court of Appeals of Washington, 2021
State Of Washington v. Joel Zellmer
Court of Appeals of Washington, 2020