John Babbitt, Res. / X-app. v. Kingsgate Ridge Manor Association, App. / X-res.

CourtCourt of Appeals of Washington
DecidedOctober 29, 2018
Docket76555-8
StatusUnpublished

This text of John Babbitt, Res. / X-app. v. Kingsgate Ridge Manor Association, App. / X-res. (John Babbitt, Res. / X-app. v. Kingsgate Ridge Manor Association, App. / X-res.) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
John Babbitt, Res. / X-app. v. Kingsgate Ridge Manor Association, App. / X-res., (Wash. Ct. App. 2018).

Opinion

• moo..

IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON - •••• ••

•••••• JOHN BABBITT, No. 76555-8-1 Respondent/Cross-Appellant, DIVISION ONE V. 1 KINGSGATE RIDGE MANOR ASSOCIATION OF APARTMENT UNPUBLISHED OPINION OWNERS,a Washington Corporation,

Appellant/Cross-Respondent.

KINGSGATE RIDGE, a Washington Corporation,

Appellant/Cross-Respondent,

V.

TT1 CONSTRUCTION, INC., a Washington Corporation,

Respondent/Cross-Appellant. FILED: October 29, 2018

CHUN, J. — Over the course of several years, John Babbitt and his

corporation, TTI Construction, Inc., performed construction work for Kingsgate

Ridge Manor Association (KRM). When KRM encountered financial trouble, it

requested a loan from Babbitt. KRM also needed replacement of a deteriorating

retaining wall and asked TTI to bid on the project. The parties agreed to and

executed both a promissory note memorializing the loan and a contract for TTI's

construction of the wall. No. 76555-8-1/2

KRM defaulted on repayment of the loan and Babbitt sued to enforce the

note. KRM filed a counterclaim and third party suit against TTI, alleging breach

of contract due to TTI's failure to obtain proper permits for the wall project. The

trial court construed the promissory note and wall construction contract

separately, entering judgment for Babbitt on the promissory note and for KRM on

the breach of contract claim. All parties filed notices of appeal of a number of the

trial court's decisions.

We conclude the trial court properly construed the promissory note and

wall contract as separate agreements but erred in the decisions to pierce the

corporate veil and deny postjudgment interest on the entirety of the judgment for

Babbitt. Therefore, we affirm in part and reverse as to only those two issues.

I. BACKGROUND

KRM is a condominium owners' association for the Kingsgate Ridge

Manor Condominium complex in Kirkland, Washington. Babbitt is the sole officer

and shareholder of TTI, a Washington corporation and licensed and bonded

construction contractor. TTI specializes in logging, utility, and earthwork,

including retaining wall construction.

Beginning in 2009, Babbitt and his contractor corporation& successfully

bid on and completed several maintenance projects for KRM. While working on

these projects for KRM, Babbitt observed that the association experienced

1 Babbitt was previously the sole officer and shareholder of AAA Tree Tech, Inc., which was administratively dissolved in 2011.

2 No. 76555-8-1/3

chronic underfunding. To help KRM, Babbitt offered "value engineering" and

term financing on some of the projects.

In 2012, KRM encountered significant financial trouble. It was

underfunded and had outstanding bills. In addition, rocks began falling out of

one of the retaining walls in its condominium complex and KRM became

concerned about possible injury to people and property. KRM had attempted to

obtain a conventional bank loan but was rejected due to a lack of financial

reserves.

Having exhausted its options, KRM invited Babbitt to an association board

meeting in August 2012 to discuss a loan. KRM gave Babbitt a written proposal

requesting a $600,000 loan at 10 percent fixed interest with monthly payments of

$11,000. The proposal included a condition that Babbitt's construction company

submit an estimate for replacement of the complex's failing rock wall, which KRM

would consider against three other competitive bids.2 Babbitt said he would try to

help KRM, but indicated he needed time to think about the terms and secure

funding for the loan. The parties did not execute a written agreement at that

time.

Babbitt obtained $150,000 in financial assistance from his uncle. Babbitt

then issued a $150,000 cashier's check to KRM for immediate cash reserves.

He paid $56,561.04 towards KRM's homeowners' insurance bill, water district

bill, sewer bill, and Home Depot bill.

2 The proposal erroneously identified Babbitt's corporation as AAA Tree Tech rather than TTI. AAA Tree Tech had already been administratively dissolved by the time of the proposal.

3 No. 76555-8-1/4

TTI prepared an estimate for replacement of the retaining wall. It

proposed construction of a Keystone wall for $299,847. The estimate specified

exclusions for "permits and fees." Two officers of the KRM board approved and

signed the bid on October 9,2012. Due to winter weather conditions, TTI did not

begin construction until March 2013.

In February 2013, Babbitt prepared a promissory note to memorialize the

loan. Prior to the promissory note, Babbitt had advanced money and paid KRM's

bills. The promissory note provided for a loan of $600,000, at 10 percent interest

per annum, with monthly payments of $12,748.23, over a repayment term of five

years. The terms also included late fees, attorney fees, and an acceleration of

debt clause. These terms differed from those of KRM's initial loan proposal.

Babbitt presented the promissory note to the full KRM board on

February 12, 2013. The board agreed to the terms, and two of its officers signed

the note. The Board members knew the promissory note contained terms

differing from the original loan proposal. KRM made its required payments in

February and March 2013. KRM then requested an indefinite deferral on the

remaining payments. Babbitt agreed to defer the payments, with the

understanding interest would continue to accrue during the deferral period.

TTI began demolition and construction of the retaining wall in March 2013.

TTI soon discovered site conditions requiring significant changes to the scope of

work, including a larger wall made up of a different stonework system. After

consulting with KRM's construction manager, TT1 provided a change order

4 No. 76555-8-1/5

reflecting an increase in cost to $331,332.46, reduced by a $10,000 credit for

deferred pipe upgrades.

TTI completed a non-reinforced StoneTerra retaining wall ranging from

two feet to ten feet tall. Despite the requirements of Kirkland's municipal code,

neither TTI nor KRM obtained a permit for construction of the wall.

In April 2014, KRM's new financial manager, Robert Brencic, discovered

the promissory note while reviewing the association's bills and books to create a

budget. KRM's board asked Brencic to investigate the promissory note to

determine the association's obligations. Brencic determined KRM owed Babbitt

a total of $538,194.40 less the two payments made in February and March 2013.

Brencic prepared an amortization schedule for payments over five years.

KRM approved Brencic's findings and asked him to approach Babbitt to

request waiver of the interest on the loan. Babbitt consented to a five year

repayment period and waiver of the late fees to date, but refused to waive

interest. Babbitt also offered the balance of the $600,000, but KRM did not want

the additional money. KRM agreed to Babbitt's terms but made only four

payments. Babbitt filed suit for default on the promissory note in September

2015.

In March 2016, the trial court granted Babbitt's motion for partial summary

judgment for $150,000 as recovery for the cash payment to KRM. The trial court,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Norhawk Investments, Inc. v. Subway Sandwich Shops, Inc.
811 P.2d 221 (Court of Appeals of Washington, 1991)
Boyd v. Davis
897 P.2d 1239 (Washington Supreme Court, 1995)
Pennsylvania Life Insurance v. Department of Employment Security
645 P.2d 693 (Washington Supreme Court, 1982)
Meisel v. M & N Modern Hydraulic Press Co.
645 P.2d 689 (Washington Supreme Court, 1982)
Standard Fire Insurance v. Blakeslee
771 P.2d 1172 (Court of Appeals of Washington, 1989)
Granite Equipment Leasing Corp. v. Hutton
525 P.2d 223 (Washington Supreme Court, 1974)
Erection Co. v. Department of Labor & Industries
852 P.2d 288 (Washington Supreme Court, 1993)
Truckweld Equipment Co. v. Olson
618 P.2d 1017 (Court of Appeals of Washington, 1980)
RSL-3B-IL, Ltd. v. Symetra Life Insurance
271 P.3d 925 (Court of Appeals of Washington, 2012)
Sharbono v. Universal Underwriters Ins. Co.
247 P.3d 430 (Court of Appeals of Washington, 2011)
Branson v. Port of Seattle
101 P.3d 67 (Washington Supreme Court, 2004)
Michak v. Transnation Title Ins. Co.
64 P.3d 22 (Washington Supreme Court, 2003)
In Re Estate of Jones
93 P.3d 147 (Washington Supreme Court, 2004)
Hegwine v. Longview Fibre Co., Inc.
172 P.3d 688 (Washington Supreme Court, 2007)
Noble v. SAFE HARBOR PRESERVATION TRUST
216 P.3d 1007 (Washington Supreme Court, 2009)
In Re Marriage of Rockwell
170 P.3d 572 (Court of Appeals of Washington, 2007)
State v. Trask
990 P.2d 976 (Court of Appeals of Washington, 2000)
Boguch v. Landover Corp.
224 P.3d 795 (Court of Appeals of Washington, 2009)
Davis v. Department of Licensing
977 P.2d 554 (Washington Supreme Court, 1999)
State v. J.M.
28 P.3d 720 (Washington Supreme Court, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
John Babbitt, Res. / X-app. v. Kingsgate Ridge Manor Association, App. / X-res., Counsel Stack Legal Research, https://law.counselstack.com/opinion/john-babbitt-res-x-app-v-kingsgate-ridge-manor-association-app-washctapp-2018.